PERT Schedule Check (Three-Point Estimates, Expected Duration, Chance of Meeting the Deadline)
With optimistic, most likely and pessimistic durations for the activities on the critical path, what is the expected completion time, how likely is it to meet the deadline, and what duration can I promise at my confidence level?
PERT analysis of up to five activities in sequence on a critical path: the expected duration and variance of each activity from its three-point estimate, the expected path duration and standard deviation, the probability of finishing by the deadline from the normal distribution, and the duration to promise at the confidence you require, against that confidence.
Open the calculatorRuns in your browser. No account needed.
How this tool works
Inputs, units and where to find them
| Input | Unit | Typical source |
|---|---|---|
| Activity 1 | ||
| Activity 1 optimistic | days | Shortest realistic duration of activity 1 if everything goes well. |
| Activity 1 most likely | days | Most likely duration of activity 1. |
| Activity 1 pessimistic | days | Longest realistic duration of activity 1 if things go badly (not a disaster case). |
| Activity 2 | ||
| Activity 2 optimistic | days | Shortest realistic duration of activity 2 if everything goes well. |
| Activity 2 most likely | days | Most likely duration of activity 2. |
| Activity 2 pessimistic | days | Longest realistic duration of activity 2 if things go badly (not a disaster case). |
| Activity 3 | ||
| Activity 3 optimistic | days | Shortest realistic duration of activity 3 if everything goes well. |
| Activity 3 most likely | days | Most likely duration of activity 3. |
| Activity 3 pessimistic | days | Longest realistic duration of activity 3 if things go badly (not a disaster case). |
| Activity 4 | ||
| Activity 4 optimistic | days | Shortest realistic duration of activity 4 if everything goes well. |
| Activity 4 most likely | days | Most likely duration of activity 4. |
| Activity 4 pessimistic | days | Longest realistic duration of activity 4 if things go badly (not a disaster case). |
| Activity 5 (0, 0, 0 to leave out) | ||
| Activity 5 optimistic | days | Shortest realistic duration of activity 5 if everything goes well. |
| Activity 5 most likely | days | Most likely duration of activity 5. |
| Activity 5 pessimistic | days | Longest realistic duration of activity 5 if things go badly (not a disaster case). |
| Target | ||
| Deadline (from the start) | days | Working days from the start to the deadline or shutdown end. |
| Confidence required | % | Probability of finishing on time that you need to be able to promise. |
What each input means
Open an input to see what it is, its units, the worked example and the common mistakes, with a small diagram.
Activity 1
What this means: Activity 1 optimistic
- What it is
- The shortest time activity 1 on the critical path could realistically take if everything goes well, the optimistic end of its three-point estimate.
- Units and format
- Enter a number in days: days. The form accepts 0 days to 100000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 5 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Lowers the expected duration slightly and, by widening the range to the pessimistic value, raises the variance.
- Get it right
- Ask the people doing activity 1; an optimistic value that could never happen narrows the spread falsely.
What this means: Activity 1 most likely
- What it is
- The duration of activity 1 that is most likely to happen, the peak of its three-point estimate, weighted four times in the expected value.
- Units and format
- Enter a number in days: days. The form accepts 0 days to 100000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 8 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Moves the expected duration by two-thirds of any change; it does not change the variance.
- Get it right
- It must lie between the optimistic and pessimistic values for activity 1.
What this means: Activity 1 pessimistic
- What it is
- The longest time activity 1 could realistically take if things go badly, short of a disaster, the pessimistic end of its three-point estimate.
- Units and format
- Enter a number in days: days. The form accepts 0 days to 100000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 14 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Raises the expected duration and, with the square of the range, the variance of the path.
- Get it right
- Use a credible bad case for activity 1; enter 0 for all three values of activity 5 to leave it out.
Activity 2
What this means: Activity 2 optimistic
- What it is
- The shortest time activity 2 on the critical path could realistically take if everything goes well, the optimistic end of its three-point estimate.
- Units and format
- Enter a number in days: days. The form accepts 0 days to 100000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 10 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Lowers the expected duration slightly and, by widening the range to the pessimistic value, raises the variance.
- Get it right
- Ask the people doing activity 2; an optimistic value that could never happen narrows the spread falsely.
What this means: Activity 2 most likely
- What it is
- The duration of activity 2 that is most likely to happen, the peak of its three-point estimate, weighted four times in the expected value.
- Units and format
- Enter a number in days: days. The form accepts 0 days to 100000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 12 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Moves the expected duration by two-thirds of any change; it does not change the variance.
- Get it right
- It must lie between the optimistic and pessimistic values for activity 2.
What this means: Activity 2 pessimistic
- What it is
- The longest time activity 2 could realistically take if things go badly, short of a disaster, the pessimistic end of its three-point estimate.
- Units and format
- Enter a number in days: days. The form accepts 0 days to 100000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 20 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Raises the expected duration and, with the square of the range, the variance of the path.
- Get it right
- Use a credible bad case for activity 2; enter 0 for all three values of activity 5 to leave it out.
Activity 3
What this means: Activity 3 optimistic
- What it is
- The shortest time activity 3 on the critical path could realistically take if everything goes well, the optimistic end of its three-point estimate.
- Units and format
- Enter a number in days: days. The form accepts 0 days to 100000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 3 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Lowers the expected duration slightly and, by widening the range to the pessimistic value, raises the variance.
- Get it right
- Ask the people doing activity 3; an optimistic value that could never happen narrows the spread falsely.
What this means: Activity 3 most likely
- What it is
- The duration of activity 3 that is most likely to happen, the peak of its three-point estimate, weighted four times in the expected value.
- Units and format
- Enter a number in days: days. The form accepts 0 days to 100000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 5 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Moves the expected duration by two-thirds of any change; it does not change the variance.
- Get it right
- It must lie between the optimistic and pessimistic values for activity 3.
What this means: Activity 3 pessimistic
- What it is
- The longest time activity 3 could realistically take if things go badly, short of a disaster, the pessimistic end of its three-point estimate.
- Units and format
- Enter a number in days: days. The form accepts 0 days to 100000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 9 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Raises the expected duration and, with the square of the range, the variance of the path.
- Get it right
- Use a credible bad case for activity 3; enter 0 for all three values of activity 5 to leave it out.
Activity 4
What this means: Activity 4 optimistic
- What it is
- The shortest time activity 4 on the critical path could realistically take if everything goes well, the optimistic end of its three-point estimate.
- Units and format
- Enter a number in days: days. The form accepts 0 days to 100000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 6 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Lowers the expected duration slightly and, by widening the range to the pessimistic value, raises the variance.
- Get it right
- Ask the people doing activity 4; an optimistic value that could never happen narrows the spread falsely.
What this means: Activity 4 most likely
- What it is
- The duration of activity 4 that is most likely to happen, the peak of its three-point estimate, weighted four times in the expected value.
- Units and format
- Enter a number in days: days. The form accepts 0 days to 100000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 9 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Moves the expected duration by two-thirds of any change; it does not change the variance.
- Get it right
- It must lie between the optimistic and pessimistic values for activity 4.
What this means: Activity 4 pessimistic
- What it is
- The longest time activity 4 could realistically take if things go badly, short of a disaster, the pessimistic end of its three-point estimate.
- Units and format
- Enter a number in days: days. The form accepts 0 days to 100000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 15 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Raises the expected duration and, with the square of the range, the variance of the path.
- Get it right
- Use a credible bad case for activity 4; enter 0 for all three values of activity 5 to leave it out.
Activity 5 (0, 0, 0 to leave out)
What this means: Activity 5 optimistic
- What it is
- The shortest time activity 5 on the critical path could realistically take if everything goes well, the optimistic end of its three-point estimate.
- Units and format
- Enter a number in days: days. The form accepts 0 days to 100000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 0 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Lowers the expected duration slightly and, by widening the range to the pessimistic value, raises the variance.
- Get it right
- Ask the people doing activity 5; an optimistic value that could never happen narrows the spread falsely.
What this means: Activity 5 most likely
- What it is
- The duration of activity 5 that is most likely to happen, the peak of its three-point estimate, weighted four times in the expected value.
- Units and format
- Enter a number in days: days. The form accepts 0 days to 100000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 0 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Moves the expected duration by two-thirds of any change; it does not change the variance.
- Get it right
- It must lie between the optimistic and pessimistic values for activity 5.
What this means: Activity 5 pessimistic
- What it is
- The longest time activity 5 could realistically take if things go badly, short of a disaster, the pessimistic end of its three-point estimate.
- Units and format
- Enter a number in days: days. The form accepts 0 days to 100000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 0 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Raises the expected duration and, with the square of the range, the variance of the path.
- Get it right
- Use a credible bad case for activity 5; enter 0 for all three values of activity 5 to leave it out.
Target
What this means: Deadline (from the start)
- What it is
- The number of working days from the start of the path to the deadline, such as the end of a shutdown or a delivery date.
- Units and format
- Enter a number in days: days. The form accepts 0.000001 days to 1000000 days. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 40 days as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- A later deadline raises the chance of finishing on time.
- Get it right
- Count in the same day units as the activity estimates, working days or calendar days.
What this means: Confidence required
- What it is
- The probability of finishing on time that you need before promising a date, used to find the duration to promise.
- Units and format
- Enter a number in %: percent: the number is read as a percentage, so type 8 for 8 %. The form accepts 50% to 99.9%. Required: the tool does not calculate until every input is valid.
- Example
- The form opens with 85% as a worked example. It is an illustration, not a recommended value: replace it with your own figure.
- Effect on the result
- Raises the duration to promise and the bar the deadline must clear.
- Get it right
- Higher confidence needs a longer promise; 50 % is simply the expected duration.
Method and formulas
- Each activity: expected duration t_e = (a + 4m + b) ÷ 6 and variance σ² = ((b − a) ÷ 6)² (PERT, Malcolm et al. 1959).
- Path: T = Σ t_e and σ_T = √(Σ σ²), activities treated as independent.
- Probability of finishing by the deadline = Φ((deadline − T) ÷ σ_T); duration at confidence c = T + z_c σ_T, with the normal distribution.
- Example: expected 36.333 days (σ 2.8771); a 89.874 % chance of finishing within 40 days.
Limitations
- Covers one path: a near-critical parallel path can finish later and makes the real chance of meeting the deadline lower (merge bias); check every path that could become critical.
- Assumes independent activities and a normal path total; common causes (weather, one supplier) make delays move together and widen the real spread.
- Example values are illustrations. Replace them with values for your actual task.
Typical uses
- Set a realistic delivery date for a machine build
- Check the chance of meeting a shutdown window
- Decide how much schedule buffer to hold
Who it is for
- Project managers
- Planners and schedulers
- Engineering managers
What you get
- Expected duration and variance of each activity
- Expected path duration and standard deviation
- Probability of meeting the deadline
- Duration to promise at your confidence
Interpreting the result
- Each activity’s spread adds as variance, so one activity with a long pessimistic tail can dominate the path’s uncertainty: tighten that estimate first.
References
- Malcolm D. G., Roseboom J. H., Clark C. E. and Fazar W., Application of a Technique for Research and Development Program Evaluation, Operations Research 7 (5), 646–669 (1959).
- Machinery’s Handbook, 29th edition (Industrial Press, 2012), printed pp. 128–133. Topic reference; no source tables or recommended settings are reproduced.
Learn the Concepts Behind This Tool
These KEVOS® Library readings explain the method this tool uses, with worked examples.
Explains the concept · Library collection
How confident is that finish date? Ranges, parallel work and what a schedule's probability measures
In Project Estimates, Schedules and Costs
What it covers: A finish date without a confidence level is one point from a range of futures. How to use three-point estimates, why parallel streams lower your real odds and when detailed modelling helps.
Useful alongside · KEVOS® original book
A fixed deadline: the cost of delay as a cliff
In Front-End Planning by the Numbers
What it covers: A step cost of delay at 31 January 2028, A$630k plus A$41k a week, and a seeded simulation: a 44.2% chance of missing on the rush path against 5.3% on the planned path.
Useful alongside · Library collection
Critical path scheduling explained: building the network, calculating float and keeping the schedule honest
In Project Planning and Control
What it covers: A schedule models how work depends on other work. How to sequence activities, run the forward and backward pass, read total and free float, and keep the critical path credible.