Schedule Risk Check

Are you likely to hit the deadline?

Checks whether the remaining work fits in the remaining working days with the people and productivity available.

Open the calculatorRuns in your browser. No account needed.

How this tool works

Inputs, units and where to find them

InputUnitTypical source
Remaining workhrBottom-up estimate of remaining effort
People availablepeoplePeople available for the remaining work
Productive hours / person / dayhrProductive hours per person per day
Working days remainingdaysWorking days until the deadline
Planning efficiency%Share of hours that become progress (allowing for rework and interruptions)

Method and formulas

  1. Productive capacity = people × hours per day × days × efficiency
  2. Coverage = capacity ÷ remaining work
  3. Days needed = remaining work ÷ (people × hours per day × efficiency)

Limitations

  • Ignores task dependencies and the critical path
  • Assumes productivity stays constant

Typical uses

  • Forecasting whether a date will be met
  • Deciding between adding people, extending time or cutting scope

Who it is for

  • Project managers
  • Engineering leads

What you get

  • LOW, TIGHT or HIGH delivery risk
  • Coverage % and days needed

Interpreting the result

  • Coverage under 115% leaves little contingency
  • Check the critical path separately: capacity can exist while a sequence still runs late

References

  • PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), schedule management

WORKOS tools are screening and decision-support utilities. Verify important financial, engineering, safety, legal or operational decisions using appropriate professional standards and your organisation’s approved data.