Schedule Risk Check
Are you likely to hit the deadline?
Checks whether the remaining work fits in the remaining working days with the people and productivity available.
Open the calculatorRuns in your browser. No account needed.
How this tool works
Inputs, units and where to find them
| Input | Unit | Typical source |
|---|---|---|
| Remaining work | hr | Bottom-up estimate of remaining effort |
| People available | people | People available for the remaining work |
| Productive hours / person / day | hr | Productive hours per person per day |
| Working days remaining | days | Working days until the deadline |
| Planning efficiency | % | Share of hours that become progress (allowing for rework and interruptions) |
Method and formulas
- Productive capacity = people × hours per day × days × efficiency
- Coverage = capacity ÷ remaining work
- Days needed = remaining work ÷ (people × hours per day × efficiency)
Limitations
- Ignores task dependencies and the critical path
- Assumes productivity stays constant
Typical uses
- Forecasting whether a date will be met
- Deciding between adding people, extending time or cutting scope
Who it is for
- Project managers
- Engineering leads
What you get
- LOW, TIGHT or HIGH delivery risk
- Coverage % and days needed
Interpreting the result
- Coverage under 115% leaves little contingency
- Check the critical path separately: capacity can exist while a sequence still runs late
References
- PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide), schedule management