Two ultrasonic stripping lines, from contractor scopes to handover
Dual-line ultrasonic jig-stripping facility
Alchin Long Group · Building-hardware manufacturing · Sydney, NSW
A capital installation of two ultrasonic stripping and wash lines, with gantries, hoists and segregated chemical transfer, taken from contractor scopes to handover.
Commissioned and handed over
- Capital project delivery
- Contractor scoping
- Chemical transfer
- Executive cost reporting
Read the full case study
Employment contextExperience of the founder of KEVOS®, gained while employed by Alchin Long Group as Operations Excellence Engineer (from November 2024). It is professional track record, not a KEVOS® client engagement.
The brief
Production jigs collect coating build-up and must be stripped clean to stay in service. The business invested in a dedicated facility: two ultrasonic stripping and wash lines, lifting equipment to move jig loads between tanks, and chemical transfer that keeps incompatible chemistries apart. It had to be installed safely around live production, through specialist trades, within an approved capital budget, while other capital, tooling and maintenance work drew on the same toolroom, contractors and production windows.
How the work was approached
- Scopes before quotes
Contractor scopes were defined for the stripping and pressure-wash tanks, the gantry, hoists and trolleys, chemical transfer and services, so quotations could be compared like for like.
- Options tested on paper
Pump options for chemical transfer were assessed for duty, safety and maintenance, and air-operated double-diaphragm (AODD) pumps were procured for the duty.
- Segregation and lifting designed in
Chemical transfer was kept segregated, chemical containers were given bunded storage, and the gantry, hoists and trolleys were specified to move jig loads safely between the stripping and wash stages.
- Specialist trades coordinated
Electrical work for the tanks and hoists, pneumatic and plumbing modifications and specialist installers were sequenced around production. Hoist limit switches, wiring and strikers were installed so hoist travel was controlled before commissioning.
- When every project needs the same toolroom
The facility sat in one register with the other active capital, tooling and maintenance work, each tracked by owner, stage, cost, main risk, dependencies and next action. Clashes over trades, contractors and production windows were raised early with costed options, so management could set priorities on safety, production impact and urgency.
- Cost visible to the executive
Approved allocation was compared with committed, actual and forecast cost and reported to the executive team, because a raised purchase order is future spend before any invoice arrives.
Outcome
Two ultrasonic stripping and wash lines were installed, commissioned and handed over to production, with cost reported against the approved allocation throughout.
Why it mattersClear scopes and visible cost keep a multi-trade capital project under control from the first quote to handover.
Commercial figures are not shown. Investment decisions and approvals sat with management.