Anodizing Plan (Time, Current, Tank Heat, Loads and Cost per Part)

How long does this anodizing load take to reach thickness, can the rectifier supply it, how much heat must the tank cooling remove, and what does each part cost?

Plan of a sulfuric acid anodizing job: growth rate and time to thickness by the 720 rule with your efficiency factor, build-up per surface (as the anodizing time tool), current for the load against the rectifier capacity, the electrical heat the tank cooling must remove at the bath voltage, loads and line hours for the batch, energy, and cost per part from energy and line time.

Open the calculatorRuns in your browser. No account needed.

How this tool works

Inputs, units and where to find them

InputUnitTypical source
Current densityA/dm²Anodic current density (about 1.2–2 A/dm² for sulfuric acid anodizing).
Coating thickness wantedµmTotal coating thickness wanted.
Efficiency factor%Factor on the 720 rule for alloy and bath (100% for the rule as written; calibrate from thickness checks).
Area per partdm²Anodized area of one part.
Parts per loadParts on one jig load.
Parts in the batchParts to anodize.
Rectifier capacityALargest current the rectifier supplies.
Bath voltage at the currentVVoltage across the bath at this current density.
Bath cooling capacitykWHeat the bath chiller or cooling coil can remove.
Handling time per loadminTime to rack, rinse, seal and unload a load.
Electricity price$/kWhElectricity price.
Line labour and overhead rate$/hLabour and overhead per hour of line time.

Method and formulas

  1. 720 rule: thickness (mil) = A/ft² × minutes ÷ 720, giving growth rate (µm/min) = 25.4 × 9.290 ÷ 720 × J × efficiency (as the anodizing time tool); build-up per surface ≈ thickness ÷ 3.
  2. Current = J × area per part × parts per load; bath heat ≈ V × I.
  3. Loads = batch ÷ parts per load (rounded up); hours = loads × (time + handling) ÷ 60; cost per part = (energy × price + hours × rate) ÷ batch.
  4. Example: 20 µm takes 40.682 min at 75 A per load, putting 1.35 kW into the bath; each part costs about 1.1182.

Limitations

  • Rule of thumb for Type II sulfuric acid anodizing; hard anodizing and other baths differ.
  • Costs exclude chemicals, dyes, sealing and waste treatment.
  • Example values are illustrations. Replace them with values for your actual task.

Typical uses

  • Plan an anodizing batch
  • Size the bath chiller for a bigger load
  • Quote anodizing per part

Who it is for

  • Platers and anodizers
  • Process engineers
  • Estimators

What you get

  • Growth rate, time and build-up
  • Current against the rectifier and heat against the cooling
  • Loads, hours and cost per part

Interpreting the result

  • Most of the electrical power ends up as heat in the bath: the chiller often limits the load before the rectifier does.

References

  • Machinery’s Handbook, 29th edition (Industrial Press, 2012), printed pp. 1500–1516. Topic reference; no source tables or recommended settings are reproduced.