Weldment Cost Estimate (Weld Metal, Arc Time, Labour, Filler and Gas by Run)

For a fabrication with several fillet welds of different sizes and lengths, how much weld metal, arc time and cost does it take, and does it fit my quoted price?

Cost estimate of all the fillet welds on a weldment: for each weld run the weld metal per metre from the leg size and excess, then arc time from the deposition rate, paid time from the operating factor, and labour, filler and shielding gas costs (as the weld cost tool, run by run), summed with any fit-up and handling time, against the price you have quoted for the welding.

Open the calculatorRuns in your browser. No account needed.

How this tool works

Inputs, units and where to find them

InputUnitTypical source
Number of weld runsrunsHow many different weld runs (sizes) to include.
Weld run 1
Fillet legmmFillet leg size of weld run 1.
Total lengthmTotal length of weld run 1 on the weldment.
Weld run 2
Fillet legmmFillet leg size of weld run 2.
Total lengthmTotal length of weld run 2.
Weld run 3
Fillet legmmFillet leg size of weld run 3.
Total lengthmTotal length of weld run 3.
Weld run 4
Fillet legmmFillet leg size of weld run 4.
Total lengthmTotal length of weld run 4.
Process and rates
Excess weld metal (convexity, spatter)%Allowance for convexity and spatter over the plain triangle.
Weld metal densityg/cm³Density of the weld metal (7.85 for steel).
Deposition ratekg/hWeld metal deposited per hour of arc time.
Operating factor (arc-on share of paid time)%Share of paid time the arc is on.
Filler deposition efficiency%Share of the filler bought that ends up in the weld.
Labour and overhead rate$/hLabour and overhead per paid hour.
Filler price$/kgPrice of filler wire or rod.
Shielding gas flowL/minShielding gas flow while the arc is on (0 for self-shielded processes).
Gas price$/m³Price of shielding gas.
Fit-up and handling timehTime for fit-up, tacking, turning and handling, charged at the labour rate.
Price quoted for the welding$The price allowed for the welding.

Method and formulas

  1. Weld metal per metre = ½ leg² × (1 + excess) × density; arc time = mass ÷ deposition rate; paid time = arc time ÷ operating factor (as the weld cost tool).
  2. Labour = paid time × rate; filler = mass ÷ efficiency × price; gas = arc minutes × flow × gas price.
  3. Each run multiplied by its length; fit-up time at the labour rate added.
  4. Example: 1.0752 kg of weld metal, 2.6946 h paid including fit-up, $267 in all.

Limitations

  • Fillet welds only; groove welds have a different cross-section.
  • Deposition rate and operating factor vary widely with process, position and shop.
  • Example values are illustrations. Replace them with values for your actual task.

Typical uses

  • Price the welding on a frame or bracket
  • Compare leg sizes on cost
  • Check a welding quote

Who it is for

  • Estimators
  • Fabrication engineers
  • Welding supervisors

What you get

  • Weld metal, arc and paid time by run
  • Labour, filler and gas cost
  • Total against the quote

Interpreting the result

  • Weld metal grows with the square of the leg: one size up on a long run usually costs more than all the short runs.

References

  • Machinery’s Handbook, 29th edition (Industrial Press, 2012), printed pp. 1438–1441. Topic reference; no source tables or recommended settings are reproduced.

WORKOS tools are screening and decision-support utilities. Verify important financial, engineering, safety, legal or operational decisions using appropriate professional standards and your organisation’s approved data.

Open the Weldment Cost Estimate (Weld Metal, Arc Time, Labour, Filler and Gas by Run) calculator