Sheet-Metal Bracket: Flat Blank, Nesting, Bending Force and Cost

What flat blank, sheet yield, bending force and cost per part does this bent sheet-metal bracket have?

Cost build-up of a one- or two-bend sheet-metal part: developed flat length from outside dimensions with the bend allowance and deduction (K-factor), parts per sheet in the better orientation with spacing, material utilisation and cost per part, press brake force per bend, and labour cost from bend and blanking times with set-up spread over the batch.

Open the calculatorRuns in your browser. No account needed.

How this tool works

Inputs, units and where to find them

InputUnitTypical source
Part
First flange (outside)mmOutside length of the first flange.
Web (outside)mmOutside length of the web between bends.
Second flange (outside, 0 = one bend)mmOutside length of the second flange (0 for an L-bracket).
Part widthmmWidth of the part along the bend line.
ThicknessmmMaterial thickness.
Inside bend radiusmmInside radius of the bends.
K-factorK-factor locating the neutral axis (about 0.33–0.45 for air bending).
Bend angle°Bend angle of each bend.
Sheet and material
Sheet lengthmmLength of the stock sheet.
Sheet widthmmWidth of the stock sheet.
Spacing and edge marginmmSpacing between blanks and at the sheet edge.
Densitykg/m³Material density.
Sheet price$/kgPrice of the sheet per kilogram.
Tensile strengthMPaTensile strength of the sheet.
Press brake and labour
Die openingmmOpening of the bending die (6–12 × thickness).
Air-bending factorAir-bending force factor (1.33 is common).
Shop rate$/hMachine and labour rate.
Time per bendsHandling and bending time per bend.
Blanking time per partsTime to cut each blank.
Set-up time per batchminSet-up time for the batch.
Batch quantityParts in the batch.

Method and formulas

  1. Bend allowance BA = θ (R + k t); outside setback = (R + t) tan(θ ÷ 2); deduction = 2 × setback − BA (as the bend allowance tool).
  2. Flat length = sum of outside dimensions − bends × deduction.
  3. Parts per sheet = best of the two orientations of ⌊(L_s − gap) ÷ (blank + gap)⌋ × ⌊(W_s − gap) ÷ (width + gap)⌋.
  4. Bend force = k W t² UTS ÷ V; cost = sheet cost ÷ parts + rate × (bends × t_bend + t_blank) + set-up share.
  5. Example: the default bracket blanks at 172.8 × 100 mm, nests 161 per sheet and costs about 2.1571 each.

Limitations

  • Rectangular blanks on a simple grid; true nesting software can do better.
  • Holes, notches and finishing are not costed.
  • Example values are illustrations. Replace them with values for your actual task.

Typical uses

  • Quote a bent bracket or cover
  • Choose sheet size for best yield
  • Check press brake capacity for a part

Who it is for

  • Estimators
  • Fabrication supervisors
  • Design engineers

What you get

  • Flat blank and parts per sheet
  • Bending force
  • Cost per part

Interpreting the result

  • Utilisation under about 75% suggests trying another sheet size or orientation.

References

  • Machinery’s Handbook, 29th edition (Industrial Press, 2012), printed pp. 1346–1353. Topic reference; no source tables or recommended settings are reproduced.