KEVOS® WORKOS · Planning
Deadline Feasibility
Can you finish this quantity by the deadline?
Checks whether a quantity can be made by a deadline with the resources and hours available.
Open the calculatorRuns in your browser. No account needed.
How this tool works
Inputs, units and where to find them
| Input | Unit | Typical source |
|---|---|---|
| Required quantity | units | Quantity required by the deadline |
| Cycle time | min/unit | Cycle time per unit per resource |
| Parallel resources | resources | Parallel resources available |
| Hours / day | hr | Working hours per day |
| Working days | days | Working days until the deadline |
| Efficiency | % | Demonstrated efficiency |
Method and formulas
- Output per day = hours × 60 × resources × efficiency ÷ cycle
- Deliverable = output per day × days
- Days needed = quantity ÷ output per day
Limitations
- Machine time only; materials and people must be confirmed
Typical uses
- Confirming customer delivery dates
- Planning overtime or extra shifts
Who it is for
- Planners
- Customer service and sales
What you get
- ACHIEVABLE or NOT ACHIEVABLE
- Deliverable quantity, buffer and days needed
Interpreting the result
- Less than 10% spare is fragile; confirm materials before promising the date
WORKOS tools are screening and decision-support utilities. Verify important financial, engineering, safety, legal or operational decisions using appropriate professional standards and your organisation’s approved data.