← LibraryProject Schedule (Gantt Chart) Template & ExampleTemplates & Examples · Project TemplatesLesson 8/22← PrevNext →
TemplatePublished 10 Jul 2026Updated 14 Jul 20263 min readBy Kevin Joginscheduletime managementgantt chartproject planning
KEVOS®
Templates & Examples · Project Templates
Templates & Examples / Project Templates

Project Schedule

Visualize activity durations, logical dependencies, and the critical path to establish the baseline for project execution.

6 min read 3 sections Document Template Worked Example
Critical Path
Doc № KEV-TPL-091 Sec 4 Sheet 1/1 Drawn KEVOS® 10 Jul 2026

§1 Purpose of the Schedule

The Project Schedule integrates activities, durations, logic, and resource availability into a dynamic model that calculates the project's critical path.

While an Activity List defines what needs to happen and Duration Estimates define how long tasks take, the Project Schedule (typically visualised as a Gantt chart) defines exactly when work will occur. By feeding all previous planning documents into scheduling software, the Project Manager calculates the sequence of tasks that determines the absolute minimum time required to complete the project—known as the Critical Path.

The Critical Path The critical path is the longest sequence of dependent activities in a project plan. Any delay to an activity on the critical path will directly delay the final project delivery date. Tasks not on the critical path have "float" (schedule slack).
Contents

§2 Blank Template

A standardized tabular framework for summarizing the schedule model outputs prior to graphical representation.

While the visual Gantt chart is the most common presentation format for stakeholders, the underlying tabular data (Start/Finish dates and logic) forms the actual, auditable baseline.

PROJECT SCHEDULE DATA

Project Title [Insert Project Name]
Date Prepared [YYYY-MM-DD]
ID Activity Start Finish Duration Predecessors
[ID] [Activity Name] [Date] [Date] [Days] [ID(s)]
[ID] [Activity Name] [Date] [Date] [Days] [ID(s)]
 
Contents

§3 Worked Example: Mary's Consulting

A completed example demonstrating the visual Gantt chart output for an 8-month implementation project, featuring dynamic critical path highlighting.

This chart is a visual translation of the schedule network logic. The horizontal axis represents the 8-month timeline (May to December). Activity bars are positioned based on their calculated early start/early finish dates. The red outline identifies the critical path.

PROJECT SCHEDULE - GANTT CHART

Project Title Mary's Consulting - New Company Website
Date Prepared May 12, 2026
Task Name
May '26
Jun '26
Jul '26
Aug '26
Sep '26
Oct '26
Nov '26
Dec '26
A001 Develop Project Charter
A001
A002 Identify Stakeholders
A003 Develop Subsidiary Plans
A003
A004 Establish Baselines
A006 Conduct Requirements Interviews
A007 Run Requirements Focus Groups
A008 Distribute Consultant Questionnaire
A008
A009 Document Requirements & RTM
A010 Develop Information Architecture
A013 Develop Content Strategy
A028 Develop Test Plan
A014 Write Marketing Page Copy
A014
A015 Produce Case Studies
A015
A016 Collect Consultant Bios
A016
A017 Write Blog Seed Content
A017
A019 Draft Legal Pages
A011 Develop Visual / Brand Design
A011
A012 Sponsor Design Review & Approval
A018 Source / License Imagery
A018
A021 Set Up Dev / Staging / Prod
A035 Develop Launch Comms Plan
A022 Configure CMS
A020 Marketing & Legal Content Review
A023 Build Component Library
A023
A025 Develop Backend APIs
A025
A024 Build Page Templates
A024
A026 Implement CRM Integration
A026
A027 Configure Search & Analytics
A031 Conduct Accessibility Audit
A036 Migrate Content from Legacy Site
A029 Execute Functional Tests
A029
A030 Execute Performance Tests
A032 Resolve Defects
A032
Milestones
Critical Path Activity Project Mgmt Requirements Design Content Build Test Milestone

The Critical Path

Notice the tasks highlighted with a red outline (e.g., A024 Build Page Templates → A029 Execute Functional Tests). This is the critical path. A one-day delay to any of these tasks pushes the final project end date back by one day.

Schedule Float (Slack)

Observe tasks like A014-A017 (Content Creation). They are scheduled concurrently with the design and early build phases. Because their duration is shorter than the design/build critical path, they have "float" and their exact start dates are flexible.

Hard Logic

The visual cascade is driven entirely by the predecessor logic defined in the Activity Attributes. Task A027 (Configure Search) cannot begin until A024 (Build Page Templates) is 100% complete.

Contents

Continue learning

Project Funding RequirementsTemplate · Project TemplatesActivity Attributes Template & ExampleTemplate · Project TemplatesMilestone List Template & ExampleTemplate · Project TemplatesNEXT LESSON →Cost Baseline Template & ExampleTemplate · Project Templates