← LibraryCost Baseline Template & ExampleTemplates & Examples · Project TemplatesLesson 9/23← PrevNext →
TemplatePublished 10 Jul 2026Updated 14 Jul 20263 min readBy Kevin Jogincost managementbudgetcost baselines-curve
KEVOS®
Templates & Examples · Project Templates
Templates & Examples / Project Templates

Cost Baseline

Map time-phased budgets and generate an accurate cumulative S-curve for project performance control with this master template and worked example.

4 min read 3 sections Document Template Worked Example
Doc № KEV-TPL-101 Sec 4 Sheet 1/1 Drawn KEVOS® 10 Jul 2026

§1 Purpose of the Cost Baseline

The Cost Baseline establishes the approved time-phased budget against which project performance is measured.

A total budget figure is insufficient for project control. To know if a project is over or under budget at any given moment, the Project Manager must know how much funding was planned to be spent by that date. The Cost Baseline allocates the estimated direct costs and contingency reserves across the project schedule, creating a cumulative "S-curve."

Contingency vs. Management Reserve The Cost Baseline (Budget at Completion or BAC) includes direct costs plus the Contingency Reserve (managed by the PM for known risks). It does not include the Management Reserve (managed by the sponsor for unknown risks). Total Funding Required equals the Cost Baseline plus the Management Reserve.
Contents

§2 Blank Template

A standardized structure for recording period costs, calculating the cumulative baseline, and rolling up reserve accounts.

COST BASELINE

Project Title [Insert Project Name]
Date Prepared [YYYY-MM-DD]

Plot cumulative cost (S-curve) below. Then complete the monthly cost distribution table.

[ Insert Time-Phased S-Curve Chart Here ]
Period Period Cost (PV) Cumulative (BAC partial) % of Direct
[Month/Phase 1] [$ Amount] [$ Amount] [%]
[Month/Phase 2] [$ Amount] [$ Amount] [%]
[Month/Phase n] [$ Amount] [$ Amount] [%]
Direct Cost Total [Sum] [Sum] 100.0%
+ Contingency Reserve [$ Amount]
= Cost Baseline (BAC) [$ Amount]
+ Management Reserve [$ Amount]
= Total Funding Required [$ Amount]
Contents

§3 Worked Example: Mary's Consulting

A completed example demonstrating the time-phased cost distribution and resulting S-curve for an 8-month implementation project.

Notice how the peak spending occurs in the middle months (July and August) during the heaviest execution phases, resulting in the characteristic steep incline of the "S" shape in the cumulative line.

COST BASELINE

Project Title Mary's Consulting - New Company Website
Date Prepared May 15, 2026

Time-phased cumulative cost (S-curve) and monthly spend distribution. The cost baseline is direct cost plus contingency reserve. Management reserve sits outside the cost baseline.

$150K $125K $100K Cost (USD) $75K $50K $25K $0K BAC $143K May 2026 Jun 2026 Jul 2026 Aug 2026 Sep 2026 Oct 2026 Nov 2026 Dec 2026 Period Cost (PV) Cumulative (S-curve)
Period Period Cost (PV) Cumulative (BAC partial) % of Direct
May 2026 $5,915 $5,915 4.6%
Jun 2026 $6,775 $12,690 9.9%
Jul 2026 $27,201 $39,891 31.2%
Aug 2026 $26,589 $66,480 52.0%
Sep 2026 $22,327 $88,807 69.4%
Oct 2026 $20,733 $109,540 85.6%
Nov 2026 $10,416 $119,956 93.8%
Dec 2026 $7,996 $127,952 100.0%
Direct Cost Total $127,952 $127,952 100.0%
+ Contingency Reserve $15,000
= Cost Baseline (BAC) $142,952
+ Management Reserve (sponsor-held) $7,500
= Total Funding Required $150,452

The Shape of Spending

Projects rarely spend money linearly. Notice how 62% of the direct costs hit during the three peak build months (Jul–Sep), creating the steep vertical rise of the S-curve.

Targeting the BAC

The S-curve tracks towards the Budget at Completion (BAC), which in this case is $142,952. The PM has control over this entire amount, including the contingency.

Holding the Reserve

The Management Reserve ($7,500) is calculated but held out of the Cost Baseline. The PM must formally petition the sponsor to release these funds if unknown risks materialise.

Contents

Continue learning

NEXT LESSON →Work Breakdown Structure (WBS) Template & ExampleTemplate · Project TemplatesProject Funding RequirementsTemplate · Project TemplatesProject Schedule (Gantt Chart) Template & ExampleTemplate · Project TemplatesProject Scope StatementTemplate · Project Templates