← LibraryActivity Attributes Template & ExampleTemplates & Examples · Project TemplatesLesson 5/22← PrevNext →
TemplatePublished 10 Jul 2026Updated 14 Jul 20265 min readBy Kevin Joginscheduletime managementactivity attributesproject planning
KEVOS®
Templates & Examples · Project Templates
Templates & Examples / Project Templates

Activity Attributes

Define schedule activities by detailing their exact dependencies, expected effort, constraints, and resource requirements.

6 min read 3 sections Document Template Worked Example
A009 A009
Doc № KEV-TPL-088 Sec 4 Sheet 1/1 Drawn KEVOS® 10 Jul 2026

§1 Purpose of Activity Attributes

While the schedule baseline provides the visual timeline, Activity Attributes are the underlying data layer that validates every node in the schedule network.

A simple list of tasks is insufficient for rigorous project control. For a schedule to be reliable, every discrete activity must be fully defined with its precursors, successors, required resources, imposed constraints, and assumptions. This document ensures that when the Project Manager estimates an activity will take "5 days," there is a documented justification for exactly who is doing the work and what materials they require to succeed.

The Building Blocks of Network Diagrams The `Predecessors` and `Successors` logged in these attributes form the direct inputs for generating the project's critical path method (CPM) network diagram. Missing a dependency here guarantees a flawed schedule.
Contents

§2 Blank Template

A standardised framework consisting of a high-level summary table, followed by detailed profiles for each activity.

ACTIVITY ATTRIBUTES

Project Title [Insert Project Name]
Date Prepared [YYYY-MM-DD]

Summary Table

ID Activity WBS Owner Effort (hrs) Duration (days) Predecessors Critical?
[A001] [Activity Name] [#.#.#] [Name] [Hrs] [Days] [ID] [Yes/No]

Detailed Entry Profile

ID: [A001]
Activity: [Insert Activity Name]
Description of Work
[Detailed description of what is actually being done.]
Predecessor Relationship Lead/Lag Successor Relationship Lead/Lag
[ID] [e.g. Finish-to-Start (FS)] [Days] [ID] [e.g. Finish-to-Start (FS)] [Days]
Number & Type of Team Resources Required
[e.g., 2 x Developers, 80 total hours]
Skill Requirements
[Specific competencies needed]
Required Resources (Non-human)
[Software, materials, facilities]
Type of Effort
[Discrete, Apportioned, Level of Effort]
Location of Performance
[Where the work must be physically executed]
Imposed Dates / Constraints
[Hard start/finish dates, external dependencies]
Assumptions
[What must be true for this activity to succeed as planned?]
Contents

§3 Worked Example: Mary's Consulting

A completed example demonstrating the relationship between the high-level activity list and the detailed constraints governing individual tasks.

This example showcases the master schedule data for a website implementation project. Notice how the detailed cards capture exact logical relationships (like Finish-to-Start dependencies) and the assumptions under which the effort estimates were made.

ACTIVITY ATTRIBUTES – SUMMARY

Project Title Mary's Consulting - New Company Website
Date Prepared May 12, 2026

Summary table for all activities. Detailed attribute entries follow for representative activities.

ID Activity WBS Owner Effort (hrs) Duration (days) Predecessors Critical?
A001Develop Project Charter1.1.1Andrew (PM)205Yes
A002Identify Stakeholders1.1.1Andrew (PM)163A001Yes
A003Develop Subsidiary Plans1.1.2Andrew (PM)6012A002Yes
A004Establish Baselines1.1.2Andrew (PM)205A003Yes
A005Project Closeout1.1.4Andrew (PM)408A045Yes
A006Conduct Requirements Interviews1.2.1Andrew (PM)305A004Yes
A007Run Requirements Focus Groups1.2.1Andrew (PM)163A006
A008Distribute Consultant Questionnaire1.2.1Christine127A006Yes
A009Document Requirements & RTM1.2.2Andrew (PM)405A007, A008Yes
A010Develop Information Architecture1.2.3Bill (UX)507A009Yes
A011Develop Visual / Brand Design1.2.4Bill (UX)12015A010Yes
A012Sponsor Design Review & Approval1.2.5Mary (Sponsor)83A011Yes
A013Develop Content Strategy1.3.1Christine304A009
A014Write Marketing Page Copy1.3.2Christine10018A013
A015Produce Case Studies1.3.3Christine8020A013
A016Collect Consultant Bios1.3.4Christine6025A013
A017Write Blog Seed Content1.3.5Christine4010A013
A018Source / License Imagery1.3.6Bill (UX)408A012
A019Draft Legal Pages1.3.7Andrew (PM)164A013
A020Marketing & Legal Content Review1.3.2Andrew (PM)245A014, A015, A016, A017, A018, A019
A021Set Up Dev / Staging / Prod Environments1.4.1Bob (Dev)405A012Yes
A022Configure CMS1.4.2Bob (Dev)607A021Yes
A023Build Component Library1.4.3Bob (Dev)8012A022Yes
A024Build Page Templates1.4.3Bob (Dev)10015A023Yes
A025Develop Backend APIs1.4.4Bob (Dev)12012A022
A026Implement CRM Integration1.4.5Bob (Dev)608A025
A027Configure Search & Analytics1.4.6Bob (Dev)405A024Yes
A028Develop Test Plan1.5.1Andrew (PM)203A009
A029Execute Functional Tests1.5.2Bob (Dev)608A024, A026, A027, A028Yes
A030Execute Performance Tests1.5.3Bob (Dev)304A029Yes
A031Conduct Accessibility Audit1.5.4Bill (UX)405A024
A032Resolve Defects1.5.6Bob (Dev)608A029, A030, A031Yes
A033Conduct UAT1.5.5Andrew (PM)405A032Yes
A034Final UAT Sign-off1.5.5Mary (Sponsor)82A033Yes
A035Develop Launch Communications Plan1.6.1Christine163A012
A036Migrate Content from Legacy Site1.6.2Christine405A020, A024
A037Pre-Launch Internal Communications1.6.1Christine82A034, A035Yes
A038Production Cutover (Go-Live)1.6.3Bob (Dev)161A036, A037Yes
A039Post-Launch Hypercare1.6.4Bob (Dev)6010A038Yes
A040CMS Training for Marketing1.6.6Christine161A038
A045Operations Handoff1.6.5Andrew (PM)203A039, A040Yes

Detailed Activity Profiles

ID: A009
Activity: Document Requirements & RTM
Description of Work
Compile Requirements Documentation and the Requirements Traceability Matrix (RTM).
Predecessor Relationship Lead/Lag Successor Relationship Lead/Lag
A007FS0A010FS0
A008FS0A013FS0
A028FS0
Number & Type of Team Resources Required
1 x Andrew (PM); effort 40 hours over 5 working days
Skill Requirements
PM (planning, facilitation); domain SME for the activity's content area
Required Resources
MS Project; collaboration tools (firm SharePoint); applicable templates
Type of Effort
Discrete (deliverable-based)
Location of Performance
Hybrid - primary at firm office; remote-friendly for individual contributor work
Imposed Dates / Constraints
Earliest start: Jun 26, 2026; Latest finish: Jul 02, 2026; constrained by predecessors
Assumptions
Resource availability per Resource Mgmt Plan; no scope changes during this activity
ID: A024
Activity: Build Page Templates
Description of Work
Home, services, case study, directory, blog templates.
Predecessor Relationship Lead/Lag Successor Relationship Lead/Lag
A023FS0A027FS0
A029FS0
A031FS0
A036FS0
Number & Type of Team Resources Required
1 x Bob (Dev); effort 100 hours over 15 working days
Skill Requirements
Frontend Engineering (HTML, CSS, CMS templating)
Required Resources
Design assets from A011, CMS sandbox environment
Type of Effort
Discrete (deliverable-based)
Location of Performance
Hybrid - primary at firm office; remote-friendly for individual contributor work
Imposed Dates / Constraints
Earliest start: Sep 14, 2026; Latest finish: Oct 02, 2026; constrained by predecessors
Assumptions
Resource availability per Resource Mgmt Plan; no scope changes during this activity
ID: A038
Activity: Production Cutover (Go-Live)
Description of Work
DNS update, SSL validation, smoke tests on production.
Predecessor Relationship Lead/Lag Successor Relationship Lead/Lag
A036FS0A039FS0
A037FS0A040FS0
Number & Type of Team Resources Required
1 x Bob (Dev); effort 16 hours over 1 working days
Skill Requirements
Systems/DevOps Engineering, IT Operations collaboration
Required Resources
Production hosting credentials, Domain registrar access
Type of Effort
Discrete (deliverable-based)
Location of Performance
Hybrid - primary at firm office; remote-friendly for individual contributor work
Imposed Dates / Constraints
Earliest start: Nov 24, 2026; Latest finish: Nov 24, 2026; constrained by predecessors
Assumptions
Resource availability per Resource Mgmt Plan; no scope changes during this activity

Effort vs. Duration

Notice the distinction between effort and duration in the summary table. A009 takes 40 hours of effort, but is spread over 5 days of duration (an 8-hour daily burn rate). Confusing the two leads to severe resourcing errors.

Dependency Logic

The predecessor/successor tables use standard CPM logic like FS (Finish-to-Start). In A038, the DNS cutover cannot start until the legacy content migration (A036) finishes.

Critical Path Marking

The "Critical?" column explicitly marks the tasks that determine the project's end date. If A024 (Build Page Templates) slips by a single day, the entire November 24th Go-Live slips with it.

Contents

Continue learning

NEXT LESSON →Milestone List Template & ExampleTemplate · Project TemplatesActivity List Template & ExampleTemplate · Project TemplatesProject Funding RequirementsTemplate · Project TemplatesProject Schedule (Gantt Chart) Template & ExampleTemplate · Project Templates