← LibraryDuration Estimating WorksheetTemplates & Examples · Project TemplatesLesson 2/23← PrevNext →
TemplatePublished 10 Jul 2026Updated 14 Jul 20263 min readBy Kevin Joginscheduletime managementduration estimatespert
KEVOS®
Templates & Examples · Project Templates
Templates & Examples / Project Templates

Duration Estimating Worksheet

Calculate activity durations using parametric, analogous, and three-point (PERT) estimating techniques to build a realistic schedule baseline.

4 min read 3 sections Document Template Worked Example
Parametric Analogous PERT (3-Point) Duration Estimate
Doc № KEV-TPL-100 Sec 4 Sheet 1/1 Drawn KEVOS® 10 Jul 2026

§1 Purpose of the Estimating Worksheet

This worksheet documents the mathematical and historical basis for your schedule duration estimates, providing transparency into how timelines are calculated.

Project managers rarely rely on a single estimating method. Instead, they apply different techniques depending on the nature of the work and the historical data available. By documenting the exact parameters, multipliers, and PERT weightings used, the PM defends the schedule against arbitrary cuts and ensures the estimates can be independently validated.

The Three Techniques
  • Parametric: Statistical scaling (e.g., 4 hours per page × 10 pages).
  • Analogous: Historical comparison (e.g., "The last server migration took 5 days").
  • Three-Point (PERT): Weighted average of Optimistic, Pessimistic, and Most Likely outcomes to manage high-uncertainty tasks.
Contents

§2 Blank Template

A structured format to break down the calculations for each estimating method.

DURATION ESTIMATING WORKSHEET

Project Title [Insert Project Name]
Date Prepared [YYYY-MM-DD]

This worksheet documents the basis of duration estimates for the project. Three estimating techniques are used: parametric, analogous, and three-point (PERT).

Parametric Estimates

Formula: Duration = Effort ÷ (Resources × Hours/day × %Available × Performance Factor).

ID Effort Hours Resource Quantity % Available Performance Factor Duration Estimate
[ID] [Hrs] [Role/Count] [%] [1.0] [Days]
 

Analogous Estimates

Used when reliable history exists. Multiplier accounts for differences in scope, complexity, or team size.

ID Previous Activity Previous Duration Current Activity Multiplier Duration Estimate
[ID] [Historical Task] [Days] [Current Task] [1.0] [Days]
 

Three-Point (PERT) Estimates

PERT (beta) weighting: tE = (O + 4M + P) / 6. Used for activities with significant uncertainty.

ID Optimistic (O) Most Likely (M) Pessimistic (P) Equation Expected Duration
[ID] [Days] [Days] [Days] (O + 4M + P) / 6 [Days]
 
Contents

§3 Worked Example: Mary's Consulting

A completed example demonstrating how a PM calculates and justifies duration timelines across a mix of highly predictable and highly uncertain tasks.

DURATION ESTIMATING WORKSHEET

Project Title Mary's Consulting - New Company Website
Date Prepared May 12, 2026

This worksheet documents the basis of duration estimates for the project. Three estimating techniques are used: parametric, analogous, and three-point (PERT).

Parametric Estimates

Formula: Duration = Effort ÷ (Resources × Hours/day × %Available × Performance Factor).

ID Effort Hours Resource Quantity % Available Performance Factor Duration Estimate
A006 30 hrs 1 PM 75% 1.0 5 days
A014 100 hrs 1 writer 70% 1.0 18 days
A016 60 hrs 1 writer 30% (waiting) 0.5 25 days

Analogous Estimates

Used when reliable history exists. Multiplier accounts for differences in scope, complexity, or team size.

ID Previous Activity Previous Duration Current Activity Multiplier Duration Estimate
A001 Charter (prior internal project) 5 days Develop Project Charter 1.0 5 days
A011 Brand refresh (prior project) 12 days Develop Visual / Brand Design 1.25 15 days
A039 Prior site launch hypercare 10 days Post-Launch Hypercare 1.0 10 days

Three-Point (PERT) Estimates

PERT (beta) weighting: tE = (O + 4M + P) / 6. Used for activities with significant uncertainty.

ID Optimistic (O) Most Likely (M) Pessimistic (P) Equation Expected Duration
A009 3 5 9 (O + 4M + P) / 6 5.3 → 5 days
A024 12 15 22 (O + 4M + P) / 6 15.7 → 16 days
A032 5 8 14 (O + 4M + P) / 6 8.5 → 8 days

Fractional Availability

Observe A016 (Parametric). The writer only has 60 hours of active effort, but is waiting on 500+ consultants to reply. By setting "% Available" to 30%, the PM mathematically defends extending the duration to 25 days.

Multiplier Adjustment

In A011 (Analogous), the historical brand refresh took 12 days. However, the PM recognises the current project is more complex and applies a 1.25 multiplier to safely estimate 15 days.

PERT Weighting

The PERT formula uses a "Beta" distribution. By multiplying the Most Likely (M) estimate by 4, it heavily weights the average toward reality while still absorbing the outlier risk of the Pessimistic (P) scenario.

Contents

Continue learning

Project Calendar Template & ExampleTemplate · Project TemplatesNEXT LESSON →Duration Estimates Template & ExampleTemplate · Project TemplatesActivity List Template & ExampleTemplate · Project TemplatesActivity Attributes Template & ExampleTemplate · Project Templates