Change Log

Track every project change request from submission through disposition with this master log template and worked case study example.

4 min read 3 sections Document Template Worked Example
CR-001 CR-002 CR-003 Change Log Assessment Approved Deferred Rejected
Doc № KEV-TPL-094 Sec 4 Sheet 1/1 Drawn KEVOS® 14 Jul 2026

§1 Purpose of the Change Log

The Change Log serves as the master record of all change requests received on a project, tracking each from its initial submission through to final disposition.

As a critical project control artefact, the Change Log provides a single source of truth for the project team, sponsors, and stakeholders. It documents what changes were proposed, who proposed them, when they were assessed, and the final decision rendered by the Change Control Board (CCB) or designated authority.

Organizational Process Asset The completed Change Log becomes a valuable post-project asset. It reveals trends in scope creep, uncovers areas where initial requirements gathering may have been weak, and provides historical data to improve estimating on future projects.
Contents

§2 Blank Template

A standardised, unpopulated framework ready for deployment on new engagements.

The structure below maps exactly to standard project management governance requirements. Ensure the status of all logged items is updated continuously as requests progress from Submitted to Under Review, and finally to a closed disposition (Approved, Rejected, or Deferred).

Project Title: [Insert Project Name] Date Prepared: [YYYY-MM-DD]
ID Category Description of Change Requestor Submission Date Status Disposition Disp. Date
[CR-###] [Scope/Schedule/Cost] [Brief summary of the proposed change] [Name] [Date] [Open/Closed] [Pending/Approved/etc] [Date]
 
 
Contents

§3 Worked Example: Mary's Consulting

A fully populated snapshot demonstrating standard usage for a mid-sized digital implementation project.

In this scenario, we observe an active change control process for a "New Company Website" project. Notice how scope requests are categorised, tracked against specific requestors, and resolved with clear dispositions and dates.

Example Summary A total of 8 change requests were received during this project phase. Of these, 6 were Approved, 1 was Rejected (CR-003), and 1 was Deferred to Phase 2 (CR-004). All requests were successfully dispositioned within the timing required by the project's Change Management Plan (5 business days).
Project Title: Mary's Consulting - New Company Website Date Prepared: snapshot Oct 17, 2026
ID Category Description of Change Requestor Submission Date Status Disposition Disp. Date
CR-001 Schedule Move kickoff meeting from Apr 28 to May 8 to accommodate sponsor calendar. Andrew (PM) Apr 25, 2026 Closed Approved Apr 25, 2026
CR-002 Documents Update Project Charter to reflect revised kickoff date. Andrew (PM) Apr 26, 2026 Closed Approved Apr 26, 2026
CR-003 Scope Add real-time chat widget to website (third-party integration). Sales Lead Jul 12, 2026 Closed Rejected Jul 18, 2026
CR-004 Scope Add LinkedIn-link field to consultant directory. Sales Lead Aug 28, 2026 Closed Deferred (Phase 2) Aug 28, 2026
CR-005 Cost Negotiate 5-seat legacy CMS pricing in year 1; 10-seat from year 2. Bob (Tech Lead) Aug 22, 2026 Closed Approved Aug 22, 2026
CR-006 Quality Update brand color tokens to fix WCAG contrast issues found in pre-audit. Bill (UX) Sep 4, 2026 Closed Approved Sep 4, 2026
CR-007 Scope, Cost, Schedule Add Press / Media section to website (2 pages, 15 items at launch). Mary (Sponsor) Sep 13, 2026 Closed Approved Sep 16, 2026
CR-008 Scope, Requirements, Cost Add LinkedIn icons linking to consultant profiles on each bio card. Marketing Lead Oct 15, 2026 Closed Approved Oct 17, 2026

Sequential Logging

Every logged item receives a unique, sequential identifier (e.g. CR-001, CR-002) to ensure traceability across meeting minutes and requirement documents.

Timely Resolution

As demonstrated by CR-003, tracking both the submission and disposition dates provides oversight on CCB turnaround times and bottlenecks.

Categorisation

Tagging the core impact area (Scope, Cost, Quality, Schedule) allows project managers to quickly filter and audit specific areas of project expansion.