Change Request
Formally propose, assess, and disposition project changes with this structured request form template and worked example.
In this resource
§1 Purpose of the Change Request
The Change Request form is the formal mechanism for proposing modifications to any baselined project artefact, encompassing scope, schedule, cost, or quality requirements.
Before any adjustment to the project baseline can occur, a formal request must be articulated, assessed for impacts, and presented to the Change Control Board (CCB) or project sponsor. This form structures that articulation. It forces the requestor to justify the change and the project team to quantify its secondary effects before a decision is rendered.
§2 Blank Template
A standardized structure for capturing and assessing proposed changes, ready for use on active projects.
This form should be completed iteratively. The Requestor typically completes the description and justification, while the Project Manager or technical leads complete the impact assessment prior to the final disposition decision.
CHANGE REQUEST
Scope: ...
Requirements: ...
Cost: ...
Schedule: ...
Quality: ...]
§3 Worked Example: Mary's Consulting
A completed example demonstrating the assessment of a minor scope addition late in the project lifecycle.
This example details Change Request CR-008 from the "New Company Website" project. It illustrates how a seemingly small request (adding LinkedIn icons) must still be formally assessed for its compounding impacts on cost, requirements traceability, and team effort.
CHANGE REQUEST
Affects ~50 launch-tier consultant cards. Out of scope: any other social platforms; LinkedIn data scraping; sign-in-with-LinkedIn functionality.
Requirements: Adds F-08 LinkedIn-link display to RTM.
Cost: Estimated +$400 (Bob: 4 hrs frontend; Christine: 2 hrs to collect URLs from launch-tier consultants). Drawn from contingency.
Schedule: No critical-path impact. Work fits in existing build buffer.
Quality: No additional accessibility or performance concerns; LinkedIn icon is a well-understood pattern.
Defining Boundaries
Notice how the description explicitly states what is out of scope (scraping, SSO). This prevents the minor addition from spiralling into a major technical feature.
Holistic Impact
The impact assessment recognized that it wasn't just a 4-hour coding task for Bob; it also required 2 hours of administrative effort from Christine to gather the data.
Financial Traceability
The disposition records exactly where the $400 is coming from, ensuring the project contingency balance is accurate and traceable.
