§1 Project Context

This assumption log pertains to the "New Company Website" project initiated for Mary's Consulting, a mid-sized B2B advisory firm.

Prepared early in the planning phase (May 2026), the log captures foundational hypotheses about budget limits, technical infrastructure capabilities (such as CRM API integration), and stakeholder bandwidth. Establishing these parameters immediately protects the project schedule by defining what must be verified before the design baselines are locked.

Contents

§2 The Completed Log

The matrix below reflects the real-world execution of our standard Assumption Log framework, distinctly separating testable assumptions (the A-XX series) from fixed management constraints (the C-XX series).

ID Category Assumption / Constraint Responsible Party Due Date Actions Status Comments
A-01 Resources The 3 assigned core team members (Bob, Bill, Christine) will be available at planned allocations through project close. Andrew Ongoing Confirm allocations with functional managers monthly. Open Critical to schedule baseline.
A-02 Schedule The project can launch within approximately 6 months of charter approval. Andrew May 2026 Validate during schedule development. Open To be confirmed in planning.
A-03 Cost $150,000 USD budget is sufficient to cover design, development, content, hosting, and contingency. Mary May 2026 Refine via bottom-up estimating in planning phase. Open Sponsor pre-approved figure.
A-04 Scope Internal consultant portal and client workspaces are excluded; site is marketing-only. Andrew May 2026 Document explicitly in scope statement. Open Listed under project boundaries.
A-05 Stakeholders Consultants worldwide will provide bios and case study content within agreed deadlines. Christine Aug 2026 Establish content collection plan and reminders. Open Risk to content readiness.
A-06 Technical Existing CRM offers a supported integration method (API or connector) for lead capture. Bob Jun 2026 Verify CRM API access during requirements phase. Open Affects technical design.
A-07 Quality WCAG 2.1 AA is the accepted accessibility standard for the site. Bill Jul 2026 Confirm with sponsor / legal counsel. Open Drives design and QA effort.
C-01 Constraint - Brand Final brand and visual direction must be approved personally by the CEO (Mary). Mary Jul 2026 Schedule sponsor design review checkpoints. Open Single decision-maker = bottleneck risk.
C-02 Constraint - Budget Total spend cannot exceed $150,000 USD without sponsor approval. Andrew Ongoing Track via cost baseline and variance analysis. Open Hard cap from charter.
C-03 Constraint - Compliance Site must comply with applicable data privacy regulations (e.g., GDPR) given Fortune 500 audience. Bob Sep 2026 Confirm requirements with legal during planning. Open Affects forms / cookies.
Observation: Notice how A-03 (budget assumption) and C-02 (budget constraint) relate. The team assumes $150k is mathematically enough to buy what they need (A-03, verified by estimation), while leadership strictly constrains them from spending a dollar more (C-02, verified by tracking).
Contents

§3 Analysis of Entries

Delegated Action

Every assumption in this log has a direct "Action" rather than just a passive statement. For instance, A-06 doesn't merely assume the CRM API works; it assigns "Bob" to explicitly run a verification test by June 2026.

Risk Identification

The "Comments" column actively seeds the project's future risk register. Entries like C-01 ("Single decision-maker = bottleneck risk") immediately highlight areas requiring mitigation strategies.