Risk Register Example:
Website Redesign
A completed risk register detailing both initial analysis and response planning for a corporate website overhaul, featuring 15 identified risks and opportunities.
§1Identification & Initial Analysis
Outputs from identifying risks and performing qualitative risk analysis. Probability and Impact are each scored from 1 to 5. The total score is computed as Probability multiplied by the maximum Impact observed across the four core objectives.
| ID | Category | Risk Statement | Owner | P | Impact | Score | Level | Response Strategy | |||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Sc | Qu | Sch | Co | ||||||||
| R-01 | Technical | CRM API integration may be more complex than expected, delaying lead-form go-live. | Bob (Dev) | 3 | 2 | 2 | 4 | 3 | 12 | Med-High | Mitigate |
| R-02 | Technical | WCAG 2.1 AA audit may surface Severity-1 findings late in the project, requiring rework. | Bill (UX) | 3 | 1 | 5 | 3 | 3 | 15 | High | Mitigate |
| R-03 | External | Frontend contractor may be unavailable when needed, delaying frontend build. | Andrew (PM) | 2 | 1 | 1 | 3 | 2 | 6 | Low | Mitigate |
| R-04 | Organisational | Sponsor (Mary) may delay design approval beyond planned 5-day window, slipping the design milestone (M04). | Andrew (PM) | 4 | 1 | 1 | 4 | 2 | 16 | Critical | Mitigate |
| R-05 | Organisational | Consultants (500+) may not provide bios on time, delaying directory and content launch. | Christine | 4 | 4 | 4 | 2 | 1 | 16 | Critical | Mitigate |
| R-06 | Organisational | Bob, Bill, or Christine may take an unplanned absence (illness, family) during build phase. | Andrew (PM) | 2 | 1 | 2 | 4 | 3 | 8 | Medium | Mitigate |
| R-07 | External | Hosting/CMS vendor outage during cutover (A038) could prevent Go-Live. | Bob (Dev) | 1 | 1 | 1 | 5 | 1 | 5 | Low | Transfer/Mitigate |
| R-08 | External | Legal/Compliance review may identify GDPR or privacy issues late, blocking launch. | Andrew (PM) | 2 | 2 | 3 | 3 | 2 | 6 | Low | Mitigate |
| R-09 | Project Mgmt | Effort estimates for build activities (A024, A025) may be optimistic, exceeding the cost baseline. | Andrew (PM) | 3 | 1 | 1 | 2 | 4 | 12 | Med-High | Accept (active) |
| R-10 | Technical | Site performance may not meet LCP < 2.5s target on image-heavy pages (case studies, directory). | Bob (Dev) | 3 | 1 | 4 | 2 | 2 | 12 | Med-High | Mitigate |
| R-11 | Organisational | Marketing Lead may want to expand scope post-design approval (e.g., add a careers section). | Andrew (PM) | 4 | 4 | 1 | 3 | 3 | 16 | Critical | Mitigate |
| R-12 | Organisational | FY2026 budget pressure could reduce the project's funding mid-stream. | Mary (Sponsor) | 1 | 5 | 2 | 5 | 5 | 5 | Low | Avoid (Sponsor-managed) |
| R-13 | Project Mgmt | IT/Hosting Operations may not be ready to accept handoff at Go-Live, leaving the PM team holding production support. | Andrew (PM) | 3 | 1 | 2 | 1 | 3 | 9 | Medium | Mitigate |
| R-14 | Opportunity | Consultants featured in case studies may proactively share the new site, providing free marketing reach. | Marketing Lead | 4 | 1 | 1 | 1 | -2 | 8 | Medium | Enhance |
| R-15 | Opportunity | WCAG 2.1 AA compliance may attract clients who require accessibility-compliant vendors (gov, healthcare, education). | Sales Lead | 3 | 1 | 1 | 1 | -3 | 9 | Medium | Exploit |
§2Response Plan & Monitoring
Outputs from continuous monitoring routines. The 'Residual Score' represents the risk exposure after the response plan is implemented. Negative cost values outline calculated realisable opportunity.
| ID | Action Plan | Responsible Party | Trigger / Symptom | Resid. P | Resid. Score | Status | Comments |
|---|---|---|---|---|---|---|---|
| R-01 |
|
Bob (Dev)-primary; Marketing Lead secondary | API discovery during A025 reveals missing fields or undocumented behaviour. | 2 | 4 | Mitigating | Vendor call booked Aug 18. |
| R-02 |
|
Bill (UX); Bob ensures linter in CI | Audit report identifies Sev-1 findings. | 2 | 4 | Mitigating | Internal pre-audit booked Oct 1. |
| R-03 |
|
Andrew (PM); Procurement | Contractor declines or doesn't respond to SOW by Aug 5. | 1 | 2 | Closed | SOW signed June 28. |
| R-04 |
|
Andrew (PM) | > 5 business days elapse between design submission and Mary's response. | 2 | 4 | Mitigating | Calendar booked. |
| R-05 |
|
Christine; supported by Mary's email | < 50% bio response rate by week 2 of A016. | 3 | 6 | Mitigating | Firm-wide email scheduled June 15. |
| R-06 |
|
Andrew (PM); each team member | Team member unavailable for > 5 consecutive business days. | 2 | 4 | Mitigating | Documentation in progress. |
| R-07 |
|
Bob (Dev); IT/Hosting Operations | Vendor status page shows incident on cutover day. | 1 | 2 | Mitigating | Cutover tentatively Tue Nov 24. |
| R-08 |
|
Andrew (PM); Legal | Legal flags any Sev-1 issue in the privacy review. | 1 | 1 | Mitigating | Legal joined kickoff. |
| R-09 |
|
Andrew (PM) | EAC trends > BAC at any phase gate. | 3 | 6 | Open | Watch CPI weekly. |
| R-10 |
|
Bob (Dev) | Performance test (A030) shows 75th-percentile LCP > 2.5s. | 2 | 4 | Mitigating | CDN selected. |
| R-11 |
|
Andrew (PM); Marketing Lead | Any scope-add request from Marketing Lead post-M04. | 3 | 3 | Mitigating | Phase 2 backlog established. |
| R-12 |
|
Mary (Sponsor) | CFO communicates budget reallocation. | 1 | 1 | Closed | Sponsor confirmed June 1. |
| R-13 |
|
Andrew (PM); IT/Hosting Operations | IT raises concerns about runbooks or monitoring in late October. | 2 | 2 | Mitigating | IT engaged at kickoff. |
| R-14 |
|
Marketing Lead; Christine | Launch announcement. | 4 | 12 | Open | Social-share kit drafted. |
| R-15 |
|
Sales Lead; Marketing Lead | Audit pass + sales messaging update. | 3 | 12 | Open | Sales briefed. |
Mitigation Tracking
Risk statuses naturally shift from 'Open' to 'Mitigating' to 'Closed'. Ensure ongoing oversight of mitigation actions at every stage gate review.
Residual Acceptability
Review any risk where the residual score remains elevated. It may require an executive management reserve to handle in the case of realisation.
Opportunity Enhancement
Negative impacts denote opportunities. Strategy focus shifts to 'Enhance' or 'Exploit', maximising project returns where possible.