← ArticlesWork Performance Information (WPI) Template & ExampleTemplates & Examples · Project TemplatesLesson 1/2← PrevNext →
GuidePublished 13 Aug 20269 min readBy Kevin Joginworkperformanceinformationwpi
On this page

Ask about this page

KEVOS AIWork Performance Information (WPI) Template & Example

KEVOS knowledge first · trusted web sources when needed

Templates & Examples · Monitor and Control Project Performance

Work Performance Information (WPI) Template & Example

A handbook-style work performance information (wpi) template & example with field guidance, workflow, review checks and source-derived example evidence.

10 min readTemplate & handbookSource-groundedUpdated 13 Aug 2026
Decision supportedconvert raw execution data into analysed information and decision-ready reporting.
Best used whenThe project needs a visible, reviewable record rather than an informal conversation or undocumented spreadsheet.
Control principleFacts, assumptions, forecasts, approvals and actions should remain distinguishable throughout the artefact lifecycle.
Handbook overview

What this artefact controls

Work Performance Information (WPI) Template & Example should be treated as a decision instrument, not as paperwork completed for its own sake. Its practical value comes from making the underlying decision, evidence, ownership and review cycle visible. In this handbook, the supplied source structure is retained as the factual basis while the surrounding guidance explains how to complete, review and maintain it in day-to-day project delivery.

The source set repeatedly links project documents to broader control relationships: scope creates the work to be scheduled and costed; resources execute that work; stakeholders influence acceptance and change; risk captures uncertainty; quality establishes evidence of conformance; and performance information explains whether the project is still moving toward its intended outcome. Work Performance Information (WPI) Template & Example belongs in that integrated system. It should therefore use identifiers and terminology consistent with adjacent project records so that a reviewer can trace a decision across documents without relying on memory.

Before filling any field, write one sentence describing the decision or control action the completed artefact must support. Then identify the accountable owner, contributors, reviewers, approval authority and next review trigger. This prevents a common failure in project documentation: every box is filled, but nobody can explain what decision the document enables or who must act when conditions change.

Inputactual work data
Inputapproved baselines and thresholds
Inputforecast assumptions
Outputwork performance information
Outputforecast and variance interpretation
Outputstatus report or dashboard
Integrated visual

How the information fits together

Define
→
Complete
→
Review
→
Approve / act
→
Maintain

This visual is an HTML/CSS interpretation for the KEVOS article reader. It conveys the decision structure without embedding the supplied source artwork as a screenshot.

Field-by-field guidance

Complete the template with traceable information

The following field map is extracted from the supplied blank or completed source document where text was available. Wording has been normalised for web readability, but the source structure remains the basis. Where a field is not applicable, record why rather than silently leaving a potentially important control blank.

Source field / sectionWhat to recordReview test
WORK PERFORMANCE INFORMATION – VARIANCERecord the minimum evidence needed for work performance information – variance to support the convert raw execution data into analysed information and decision-ready reporting.The entry is specific, traceable and reviewable.
ANALYSISRecord the minimum evidence needed for analysis to support the convert raw execution data into analysed information and decision-ready reporting.The entry is specific, traceable and reviewable.
Schedule VarianceUse the approved working calendar and state whether the value is effort, elapsed duration, planned date, forecast date or actual date.The entry is specific, traceable and reviewable.
Planned ResultRecord the minimum evidence needed for planned result to support the convert raw execution data into analysed information and decision-ready reporting.The entry is specific, traceable and reviewable.
Actual ResultRecord the minimum evidence needed for actual result to support the convert raw execution data into analysed information and decision-ready reporting.The entry is specific, traceable and reviewable.
VarianceRecord the minimum evidence needed for variance to support the convert raw execution data into analysed information and decision-ready reporting.The entry is specific, traceable and reviewable.
Root Cause (Schedule)Use the approved working calendar and state whether the value is effort, elapsed duration, planned date, forecast date or actual date.The entry is specific, traceable and reviewable.
Planned Response (Schedule)Use the approved working calendar and state whether the value is effort, elapsed duration, planned date, forecast date or actual date.The entry is specific, traceable and reviewable.
Cost VarianceRecord currency, price date, inclusion boundary and source of the value; separate estimate, baseline, actual and forecast.Units, currency and basis reconcile.
Root Cause (Cost)Record currency, price date, inclusion boundary and source of the value; separate estimate, baseline, actual and forecast.Units, currency and basis reconcile.
Planned Response (Cost)Record currency, price date, inclusion boundary and source of the value; separate estimate, baseline, actual and forecast.Units, currency and basis reconcile.
WORK PERFORMANCE INFORMATION – EARNED VALUERecord the minimum evidence needed for work performance information – earned value to support the convert raw execution data into analysed information and decision-ready reporting.The entry is specific, traceable and reviewable.
Quality VarianceState the condition in testable terms and identify the evidence or method that proves it has been satisfied.A separate reviewer can verify it objectively.
Budget at Completion (BAC)Record currency, price date, inclusion boundary and source of the value; separate estimate, baseline, actual and forecast.Units, currency and basis reconcile.
Current Reporting PeriodRecord the minimum evidence needed for current reporting period to support the convert raw execution data into analysed information and decision-ready reporting.The entry is specific, traceable and reviewable.
Current PeriodRecord the minimum evidence needed for current period to support the convert raw execution data into analysed information and decision-ready reporting.The entry is specific, traceable and reviewable.
Past Period CumulativeRecord the minimum evidence needed for past period cumulative to support the convert raw execution data into analysed information and decision-ready reporting.The entry is specific, traceable and reviewable.
(Sep 2026)Record the minimum evidence needed for (sep 2026) to support the convert raw execution data into analysed information and decision-ready reporting.The entry is specific, traceable and reviewable.
Working template

Blank web-ready structure

This compact version is designed for copying into a project working note or for translating into your organisation’s controlled form. It is not a claim that these are the only fields required by every organisation, contract or jurisdiction.

WORK PERFORMANCE INFORMATION – VARIANCEEnter controlled project information here…
ANALYSISEnter controlled project information here…
Schedule VarianceEnter controlled project information here…
Planned ResultEnter controlled project information here…
Actual ResultEnter controlled project information here…
VarianceEnter controlled project information here…
Root Cause (Schedule)Enter controlled project information here…
Planned Response (Schedule)Enter controlled project information here…
Cost VarianceEnter controlled project information here…
Root Cause (Cost)Enter controlled project information here…
Planned Response (Cost)Enter controlled project information here…
WORK PERFORMANCE INFORMATION – EARNED VALUEEnter controlled project information here…
Supplied worked material

What the uploaded example demonstrates

The source set uses a recurring worked project — Mary’s Consulting and its new company website — to show how project artefacts connect. The examples are useful because the same scope, team, costs, risks, stakeholders and milestones recur across multiple forms, allowing the reader to see how one project decision propagates through the documentation system. Any numerical value below is a source example or a calculation explicitly identified as such; it should not be treated as a universal project standard.

  • Budget at Completion (BAC): $142,952
  • Overall Status: At Risk – cost overrun forecast recoverable within contingency; sponsor to be notified.
  • (Sep 2026) Cumulative (Aug 31, 2026)
  • Project Date Sep 30,
  • Title: Prepared: 2026
  • Build phase 75% complete by Sep 30. Build phase 71% complete. A024 forecast SV = -$2,307 (-2.6%)
  • A024 (Page Templates) finishing Oct 2; Oct 5 (3-day slip); A025 forecast Oct 2 SPI = 0.974
  • A025 (Backend APIs) finishing Sep 30. (2-day slip due to CRM API workaround). Schedule slip: 2–3 days on A024/A025
How to use the example. Copy the reasoning pattern, not the number. Replace example dates, thresholds, scores, names and amounts with evidence from the actual project, and retain the source or calculation basis for every material value.
Operating method

Step-by-step workflow

Step 1
Collect raw facts using agreed definitions and cut-off dates.
Step 2
Validate completeness, source and units before analysis.
Step 3
Compare actual and forecast values with approved baselines or targets.
Step 4
Explain material variance, trend and likely consequence.
Step 5
Escalate exceptions with options and recommended actions.
Step 6
Publish a decision-oriented report and track resulting commitments.

For controlled project records, the final step is not “save the file”. The final step is to make the current approved state discoverable, communicate the decision to affected people and define the next review trigger. That trigger may be a phase gate, threshold breach, approved change, new stakeholder, supplier event, forecast movement, risk trigger or a scheduled review date.

Verification

Review checklist before approval or use

  • Data cut-off dates are explicit.
  • Raw data is distinguished from analysed information.
  • Variance is explained in operational terms.
  • Forecast assumptions are visible.
  • Reported status aligns with underlying logs and baselines.
  • Actions and decisions are assigned rather than buried in narrative.

Run the review from the perspective of a competent person who did not attend the drafting meeting. If they cannot reconstruct the basis, current state and required next action from the record and its cited evidence, the artefact is not yet controlled enough for a material decision.

Practical failure modes

Common mistakes and recovery actions

Failure mode 1

Reporting numbers without interpretation.

Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.

Failure mode 2

Mixing data from different reporting periods.

Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.

Failure mode 3

Using traffic-light status without criteria.

Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.

Failure mode 4

Hiding forecast deterioration behind favourable historical actuals.

Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.

Failure mode 5

Producing a report that has no decision or action section.

Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.

Governance & hand-offs

Keep the document alive after first approval

A project artefact is only useful while its status is known. Give it a unique identifier, version, owner, approval state and effective date. Define what types of change require reapproval and what updates can be made administratively. Retain superseded versions when the record is needed to explain a historical decision, claim, audit, acceptance or lesson.

Use the document in reviews by focusing on exceptions and decisions rather than reading every field aloud. Ask what has changed since the last review, what assumption has been invalidated, what threshold has been crossed, which decision is now due and which action remains without an owner. This converts the artefact from static documentation into a control mechanism.

At hand-off, confirm that downstream users can interpret the identifiers, units, assumptions and status values without relying on the original author. For project close-out, make sure unresolved items have an operational owner and a clear retention location. A closed project should not leave behind orphaned risks, undocumented support obligations, unverified benefits or ambiguous acceptance evidence.

Source fidelity

Source basis and limitations

This page is an original KEVOS handbook synthesis grounded in the uploaded source files. It intentionally paraphrases and restructures the material for practical application rather than reproducing the source documents as images. Where the source contains an illustrative project value, that value remains an example. Where a required blank source was absent, the limitation is stated explicitly rather than silently inventing a missing form.

  • PMBOK+8+Plans+and+Documents/Monitor and Contorl Project Performance/Work_Performance_Information_BLANK.pdf
  • PMBOK+8+Plans+and+Documents/Monitor and Contorl Project Performance/Work_Performance_Information_FILLED.pdf

Current authoritative context used for the reference pages: Project Management Institute, PMBOK® Guide — Eighth Edition and the 2026 PMP Examination Content Outline. The article package does not reproduce substantial PMI publication text.

Continue learning

Related KEVOS pages

Work Performance Data: Template & ExampleManage Project ExecutionWork Performance Report Template & ExampleMonitor and Control Project Performance

Continue learning

NEXT LESSON →Work Performance Report Template & ExampleGuide · Project TemplatesWork Performance Data: Template & ExampleGuide · Project TemplatesIndividual Performance Assessment ExampleGuide · Project TemplatesIndividual Performance Assessment: UX Designer ExampleGuide · Project Templates