Work Performance Data: Template & Example
A handbook-style work performance data: template & example with field guidance, workflow, review checks and source-derived example evidence.
What this artefact controls
Work Performance Data: Template & Example should be treated as a decision instrument, not as paperwork completed for its own sake. Its practical value comes from making the underlying decision, evidence, ownership and review cycle visible. In this handbook, the supplied source structure is retained as the factual basis while the surrounding guidance explains how to complete, review and maintain it in day-to-day project delivery.
The source set repeatedly links project documents to broader control relationships: scope creates the work to be scheduled and costed; resources execute that work; stakeholders influence acceptance and change; risk captures uncertainty; quality establishes evidence of conformance; and performance information explains whether the project is still moving toward its intended outcome. Work Performance Data: Template & Example belongs in that integrated system. It should therefore use identifiers and terminology consistent with adjacent project records so that a reviewer can trace a decision across documents without relying on memory.
Before filling any field, write one sentence describing the decision or control action the completed artefact must support. Then identify the accountable owner, contributors, reviewers, approval authority and next review trigger. This prevents a common failure in project documentation: every box is filled, but nobody can explain what decision the document enables or who must act when conditions change.
How the information fits together
This visual is an HTML/CSS interpretation for the KEVOS article reader. It conveys the decision structure without embedding the supplied source artwork as a screenshot.
Complete the template with traceable information
The following field map is extracted from the supplied blank or completed source document where text was available. Wording has been normalised for web readability, but the source structure remains the basis. Where a field is not applicable, record why rather than silently leaving a potentially important control blank.
| Source field / section | What to record | Review test |
|---|---|---|
| WORK PERFORMANCE DATA | Record the minimum evidence needed for work performance data to support the convert raw execution data into analysed information and decision-ready reporting. | The entry is specific, traceable and reviewable. |
| Schedule – Activity Status | Use a small defined status set and apply it consistently; status should reflect current reality, not desired progress. | Status matches evidence and next action. |
| ID | Assign a unique, stable identifier that can be referenced from reports, changes, risks, requirements or evidence. | The entry is specific, traceable and reviewable. |
| Activity | Use the identifier from the approved scope or schedule model so the record can be traced to the work it controls. | The entry is specific, traceable and reviewable. |
| Planned | Record the minimum evidence needed for planned to support the convert raw execution data into analysed information and decision-ready reporting. | The entry is specific, traceable and reviewable. |
| Actual | Record the minimum evidence needed for actual to support the convert raw execution data into analysed information and decision-ready reporting. | The entry is specific, traceable and reviewable. |
| Notes | Record the minimum evidence needed for notes to support the convert raw execution data into analysed information and decision-ready reporting. | The entry is specific, traceable and reviewable. |
| Finish | Use the approved working calendar and state whether the value is effort, elapsed duration, planned date, forecast date or actual date. | Date meaning and calendar are unambiguous. |
| Complete | Record the minimum evidence needed for complete to support the convert raw execution data into analysed information and decision-ready reporting. | The entry is specific, traceable and reviewable. |
| Cost – Actual Cost (AC) Through Sep 13 | Record currency, price date, inclusion boundary and source of the value; separate estimate, baseline, actual and forecast. | Units, currency and basis reconcile. |
| Cost Item | Record currency, price date, inclusion boundary and source of the value; separate estimate, baseline, actual and forecast. | Units, currency and basis reconcile. |
| Planned (PV) | Record the minimum evidence needed for planned (pv) to support the convert raw execution data into analysed information and decision-ready reporting. | The entry is specific, traceable and reviewable. |
| Actual (AC) | Record the minimum evidence needed for actual (ac) to support the convert raw execution data into analysed information and decision-ready reporting. | The entry is specific, traceable and reviewable. |
| Variance | Record the minimum evidence needed for variance to support the convert raw execution data into analysed information and decision-ready reporting. | The entry is specific, traceable and reviewable. |
| Quality – Defect Counts (Cumulative) | State the condition in testable terms and identify the evidence or method that proves it has been satisfied. | A separate reviewer can verify it objectively. |
| Defect Status | Use a small defined status set and apply it consistently; status should reflect current reality, not desired progress. | Status matches evidence and next action. |
| Notable Events This Period | Record the minimum evidence needed for notable events this period to support the convert raw execution data into analysed information and decision-ready reporting. | The entry is specific, traceable and reviewable. |
| Events | Record the minimum evidence needed for events to support the convert raw execution data into analysed information and decision-ready reporting. | The entry is specific, traceable and reviewable. |
Blank web-ready structure
This compact version is designed for copying into a project working note or for translating into your organisation’s controlled form. It is not a claim that these are the only fields required by every organisation, contract or jurisdiction.
What the uploaded example demonstrates
The source set uses a recurring worked project — Mary’s Consulting and its new company website — to show how project artefacts connect. The examples are useful because the same scope, team, costs, risks, stakeholders and milestones recur across multiple forms, allowing the reader to see how one project decision propagates through the documentation system. Any numerical value below is a source example or a calculation explicitly identified as such; it should not be treated as a universal project standard.
- Raw observations and measurements collected during project execution. Reporting period: Sep 7–13, 2026 (Week 19 of project).
- ID Activity Planned Actual % Notes
- Cost – Actual Cost (AC) Through Sep 13
- Note: This is raw data, not analysis. Variance calculations (CV, SV, CPI, SPI), forecasts (EAC, ETC, VAC), and trend analysis
- A021 Set Up Dev/Staging/Prod Aug 14 Aug 13 100% Complete (1 day early)
- A022 Configure CMS Aug 25 Aug 26 100% Complete (1 day late)
- A023 Build Component Library Sep 11 Sep 11 100% Complete (on time)
- A024 Build Page Templates Oct 2 — 35% In progress; 4 of 12 templates complete
Step-by-step workflow
For controlled project records, the final step is not “save the file”. The final step is to make the current approved state discoverable, communicate the decision to affected people and define the next review trigger. That trigger may be a phase gate, threshold breach, approved change, new stakeholder, supplier event, forecast movement, risk trigger or a scheduled review date.
Review checklist before approval or use
- Data cut-off dates are explicit.
- Raw data is distinguished from analysed information.
- Variance is explained in operational terms.
- Forecast assumptions are visible.
- Reported status aligns with underlying logs and baselines.
- Actions and decisions are assigned rather than buried in narrative.
Run the review from the perspective of a competent person who did not attend the drafting meeting. If they cannot reconstruct the basis, current state and required next action from the record and its cited evidence, the artefact is not yet controlled enough for a material decision.
Common mistakes and recovery actions
Reporting numbers without interpretation.
Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.
Mixing data from different reporting periods.
Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.
Using traffic-light status without criteria.
Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.
Hiding forecast deterioration behind favourable historical actuals.
Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.
Producing a report that has no decision or action section.
Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.
Keep the document alive after first approval
A project artefact is only useful while its status is known. Give it a unique identifier, version, owner, approval state and effective date. Define what types of change require reapproval and what updates can be made administratively. Retain superseded versions when the record is needed to explain a historical decision, claim, audit, acceptance or lesson.
Use the document in reviews by focusing on exceptions and decisions rather than reading every field aloud. Ask what has changed since the last review, what assumption has been invalidated, what threshold has been crossed, which decision is now due and which action remains without an owner. This converts the artefact from static documentation into a control mechanism.
At hand-off, confirm that downstream users can interpret the identifiers, units, assumptions and status values without relying on the original author. For project close-out, make sure unresolved items have an operational owner and a clear retention location. A closed project should not leave behind orphaned risks, undocumented support obligations, unverified benefits or ambiguous acceptance evidence.
Source basis and limitations
This page is an original KEVOS handbook synthesis grounded in the uploaded source files. It intentionally paraphrases and restructures the material for practical application rather than reproducing the source documents as images. Where the source contains an illustrative project value, that value remains an example. Where a required blank source was absent, the limitation is stated explicitly rather than silently inventing a missing form.
- PMBOK+8+Plans+and+Documents/Manage Project Execution/Work_Performance_Data_BLANK.pdf
- PMBOK+8+Plans+and+Documents/Manage Project Execution/Work_Performance_Data_FILLED.pdf
Current authoritative context used for the reference pages: Project Management Institute, PMBOK® Guide — Eighth Edition and the 2026 PMP Examination Content Outline. The article package does not reproduce substantial PMI publication text.