← ArticlesZoo Relocation Project—Part 5: Implementation Staging PlanProject Delivery · Principles of Project ManagementLesson 52/58← PrevNext →
GuidePublished 13 Aug 20268 min readBy Kevin Joginproject managementproject deliveryprinciples of project managementstage
On this page

Ask about this page

KEVOS AIZoo Relocation Project—Part 5: Implementation Staging Plan

KEVOS knowledge first · trusted web sources when needed

Home/ Project Delivery/ Principles of Project Management

KEVOS® Project Delivery Handbook

Zoo Relocation Project—Part 5: Implementation Staging Plan

The CEO's letter explicitly permits a staged relocation. A practical KEVOS handbook for project delivery teams.

7 min read1,488 words Guide 51 of 57Reviewed 2026-08-13
In this handbook article
  1. The Challenge
  2. The PM Framework Applied
  3. Step 1: Define staging criteria
  4. Step 2: Define the stages
  5. Step 3: Stage gates — non-negotiable decision points
  6. Step 4: Rollback options
  7. Step 5: Stage-to-schedule overlay
  8. Step 6: Dual-site operations protocols
  9. Step 7: Stage-level success criteria
  10. The Result
  11. The Pitfalls
  12. Knowledge Check
  13. Key Takeaways
  14. References

Source and edition context

Source basis: This handbook article is adapted from the supplied file(s): 52. Inside the Zoo Relocation Project — Part 5.md.

Interpretation rule: Named scenarios, schedules, percentages, monetary values and thresholds are source examples or illustrative proposals unless an identified authority, contract or approved baseline makes them mandatory.

PMI edition context: The supplied notes primarily teach fifth- and sixth-edition process groups and knowledge areas. PMI currently publishes the PMBOK® Guide—Eighth Edition, which retains the principles and performance-domain foundation while presenting evolved, non-prescriptive process guidance. Historical counts in this article remain for source/course context, not as a claim about the current edition.

PRINCE2 edition context: The current PRINCE2 Project Management Version 7 uses seven principles, seven practices and seven processes, with explicit attention to people, sustainability, digital/data and tailoring. Earlier counts are retained only where the supplied source discusses an earlier edition.

The CEO's letter explicitly permits a staged relocation. Part 5 turns that one-line permission into a full phased delivery plan with stage gates, rollback options, and dual-site protocols.

Series recap. Parts 1–4 produced the Charter, Stakeholder Plan, Scope Baseline, WBS, Schedule, and Risk Register. Part 5 addresses the requirement that appears in the Group Report rubric explicitly: the Implementation Staging Plan.

The Challenge

Read the CEO's letter carefully and one sentence stands out:

"It will be advantageous to acquire the site as soon as possible so that a staged relocation can commence. The Zoo accepts that some exhibits may be shut down and relocated prior to the closure of the Zoo to the public."

This is not throwaway language. The CEO has pre-authorised phased delivery, signalling that the board has already accepted the operational complexity of running old and new sites simultaneously.

"Staged relocation" hides enormous complexity. It implies decisions about: which exhibits move first and on what criteria, how long both sites operate, when the old site closes (a one-way door), how staff are deployed during the overlap, what the exit trigger is from each stage, and what the rollback option is if a stage fails.

The PM Framework Applied

Step 1: Define staging criteria

Before deciding which exhibits move in which stage, establish what makes an exhibit a good candidate for early movement. A weighted scoring model:

Criterion Weight Rationale
Animal welfare sensitivity 30% High-sensitivity species move last, when the new site is fully mature
Enclosure reuse complexity 20% Low salvage-rebuild complexity = earlier move
Regulatory approval status 20% Permits already in hand = early-stage candidate
Visitor draw 15% Major attractions remain at old site to preserve revenue
Infrastructure independence 10% Shared systems make detachment harder
Staff availability 5% Willing specialist keepers enable earlier movement

Each candidate exhibit is scored against each criterion, weighted, and summed. High scores = early-stage; low scores = late-stage.

Step 2: Define the stages

Process and relationship map
Stage 0 — Pre-Move — Months 1–6
Charter & Planning
Site Acquisition
Design & Permits
Stage 1 — Early Migration — Months 7–11
Low-Sensitivity Moves
Non-Critical Transfers
Old Site Still Open
Gate Decision — Month 12
Sale Closes
Closure Decision
Stage 2 — Full Migration — Months 13–16
High-Sensitivity Moves
Major Enclosure Transfer
Staff Transition
Stage 3 — Commissioning — Months 17–18
Testing
Soft Opening
Launch
Relationship details
FromRelationshipTo
Stage 0 — Pre-Move — Months 1–6leads toStage 1 — Early Migration — Months 7–11
Stage 1 — Early Migration — Months 7–11leads toGate Decision — Month 12
Gate Decision — Month 12leads toStage 2 — Full Migration — Months 13–16
Stage 2 — Full Migration — Months 13–16leads toStage 3 — Commissioning — Months 17–18

The red Gate Decision box is the most consequential decision on the entire project. Until that moment, both sites are open. After, the old site closes irreversibly and the project enters a race against the 18-month deadline while generating zero visitor revenue.

Step 3: Stage gates — non-negotiable decision points

Every stage ends with a formal stage gate. Four possible outcomes (PRINCE2-influenced):

  • Go — proceed as planned
  • Go with conditions — proceed with remedial actions in parallel
  • Hold — pause until conditions met
  • Stop — escalate to board
Gate Entry Criteria (all required)
Gate 1 (S0 → S1) Lease executed; Stage 1 permits approved; enclosures commissioned; transport contractor mobilised; vet-signed protocols
Gate 2 (S1 → Decision) Stage 1 animals in quarantine with zero casualties; Stage 2 construction ≥ 70%; sale contracts exchanged
Gate 3 (Decision → S2) Sale complete; grant drawn; Stage 2 enclosures commissioned; high-sensitivity protocols confirmed
Gate 4 (S2 → S3) All animals relocated; quarantine clear; regulatory final inspection passed
Gate 5 (S3 → Ops) Soft opening complete; visitor flow tested; board sign-off on opening date

Gates are not performative. They are the PM's contractual instrument for refusing to proceed into a stage that is not ready.

Step 4: Rollback options

Rollback narrows dramatically as the project progresses:

Stage Rollback Option Cost
Stage 0 Full cancellation; limited sunk cost Low
Stage 1 Return early-moved animals; halt construction Moderate
Decision Delay closure 30–60 days via bridging finance Moderate
Stage 2 No rollback — old site closed, animals in transit Contingency only
Stage 3 No rollback — commissioning must succeed Emergency only

Gates at Stage 1 and the Decision Point are the last points at which rollback is cheap.

Step 5: Stage-to-schedule overlay

Zoo Relocation — Staging Overlay
WorkstreamActivityTypeTiming / dependency / duration
Stage 0Planning & CharterActivitydone · s0a · 2025-01-01 · 30d
Stage 0Site AcquisitionActivitydone · s0b · 2025-02-01 · 90d
Stage 0Design & PermitsActivitys0c · 2025-04-01 · 120d
Stage 0Gate 1Milestonemilestone · g1 · 2025-07-01 · 0d
Stage 1Stage 1 ConstructionActivitys1a · 2025-07-01 · 90d
Stage 1Low-Sensitivity MoveActivitys1b · 2025-09-15 · 60d
Stage 1Stage 1 QuarantineActivitys1c · 2025-11-15 · 30d
Stage 1Gate 2Milestonemilestone · g2 · 2025-12-15 · 0d
DecisionSale CompletionActivitycrit · ds · 2025-12-15 · 30d
DecisionPublic ClosureMilestonemilestone · dp · 2026-01-15 · 0d
DecisionGate 3Milestonemilestone · g3 · 2026-01-15 · 0d
Stage 2High-Sensitivity MoveActivitycrit · s2a · 2026-01-15 · 90d
Stage 2Enclosure TransferActivitycrit · s2b · 2026-01-15 · 120d
Stage 2Staff TransitionActivitys2c · 2026-02-01 · 90d
Stage 2Gate 4Milestonemilestone · g4 · 2026-05-15 · 0d
Stage 3CommissioningActivitys3a · 2026-05-15 · 45d
Stage 3Soft OpeningActivitys3b · 2026-06-30 · 14d
Stage 3LaunchMilestonemilestone · launch · 2026-07-15 · 0d

Step 6: Dual-site operations protocols

During Stage 1, the Zoo operates two sites simultaneously. This is the most operationally complex period and typically under-planned. The staging plan must specify:

  • Staffing split — which staff work where on which days
  • Asset tracking — inventory as it moves between sites
  • Veterinary coverage — full vet support at both sites
  • Communications — consistent messaging about which exhibits are where
  • Emergency response — incident protocols working across both sites
  • Security — cover at a progressively emptying site
  • Utilities — progressive decommissioning of old site utilities
Process and relationship map
Old Site
Exhibits
Staff
Equipment
New Site
Exhibits
Staff
Equipment
Months
Month 1
Month 6
Month 12
Month 18
Relationship details
FromRelationshipTo
Exhibitsleads toExhibits
Exhibitsleads totransfer
Equipmentleads toEquipment
Equipmentleads totransfer
Month 1leads toExhibits
Month 6leads toStaff
Month 12leads toEquipment
Month 18leads toEquipment

Step 7: Stage-level success criteria

Each stage has its own success criteria:

Stage Criteria
Stage 0 Charter signed; site selected; permits lodged; design ≥ 80%
Stage 1 100% low-sensitivity moved with zero casualties; no welfare incidents; staff morale ≥ baseline
Decision Sale proceeds received; Stage 2 inspection-ready; board endorsement
Stage 2 100% animals moved; old site vacated; all staff transitioned
Stage 3 All systems passing final inspection; soft opening positive

The Result

The Implementation Staging Plan is now a standalone controlled document. It is referenced by every other planning artefact: the schedule shows gates as milestones, the risk register tags risks by stage, the communications plan has stage-specific messaging, and the budget has stage-specific spend profiles.

The Pitfalls

  • Treating staging as just "chunking the schedule." A staging plan has its own gate logic and rollback analysis.
  • Under-investing in dual-site operations. Teams plan move-out and move-in but forget they are running two operations with the same staff and budget during overlap.
  • Making gates advisory. If a gate can be overridden without sponsor escalation, it is not a gate.
  • Locking the stage structure before risk analysis. Risks may reveal early candidates are not actually safe to move first.
  • Ignoring the emotional weight of the Decision Point. Closing the old site is a cultural moment for staff, members, and community — the plan must include ceremony, not just logistics.
  • Treating rollback as defeatism. Defining rollback is diligence. A PM who cannot describe how to undo each stage is not ready to execute it.

Knowledge Check

  1. During Stage 1 quarantine, two relocated birds show severe stress. The vet recommends return to the old site (still open). What does the staging plan require, and which gate is now in jeopardy?
  2. The sale is delayed 45 days, pushing the Decision Point beyond the planned date. Which stages are affected and what are your options?
  3. A board member asks whether Stage 1 and Stage 2 can be merged to save time. Draft a one-paragraph response explaining why the staging structure exists.

Key Takeaways

  • The CEO's one-line "staged relocation" permission implies a complete phased-delivery governance structure.
  • A staging plan is a separate controlled document overlaying the WBS and schedule with gate-based governance.
  • Stage gates have four outcomes and must have non-negotiable entry criteria.
  • Rollback options diminish rapidly as the project progresses.
  • Dual-site operations during stage overlap is the most frequently under-planned element.
  • The decision to close the old site is a one-way door — the most consequential decision in the project.

References

  • Project Management Institute 2017, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 6th edn, PMI, Newtown Square, PA.
  • Office of Government Commerce 2017, Managing Successful Projects with PRINCE2, 6th edn, TSO, London.
  • Turner, JR 2014, Handbook of Project-Based Management, 4th edn, McGraw-Hill, New York.
  • Morris, PWG 2013, Reconstructing Project Management, Wiley-Blackwell, Chichester.
  • University of South Australia 2015, MPM411 Zoo Relocation Project Brief, UniSA, Adelaide.

Continue learning

Zoo Relocation Case StudyZoo Relocation Project—Part 4: Risk Management8 min readZoo Relocation Case StudyZoo Relocation Project—Part 6: Closure and Benefits Realisation9 min readPostgraduate Project Management StudyHow to Score a High Distinction on a Postgraduate Project Management Group Report28 min readZoo Relocation Case AnalysisAnatomy of the Zoo Relocation Case Study18 min read

Prepared for the KEVOS® Knowledge Library. Apply the governing contract, approved project method and current standards to live work.

Continue learning

Zoo Relocation Project—Part 4: Risk ManagementGuide · Principles of Project ManagementNEXT LESSON →Zoo Relocation Project—Part 6: Closure and Benefits RealisationGuide · Principles of Project ManagementZoo Relocation Project—Part 3: WBS, Schedule and Critical PathGuide · Principles of Project ManagementHow to Score a High Distinction on a Postgraduate Project Management Group ReportGuide · Principles of Project Management
KEVOS · Engineering, manufacturing and project improvement
ArticlesServicesCase studiesAboutContact
© 2026 KEVOS®