← ArticlesZoo Relocation Project—Part 3: WBS, Schedule and Critical PathProject Delivery · Principles of Project ManagementLesson 50/58← PrevNext →
GuidePublished 13 Aug 20268 min readBy Kevin Joginproject managementproject deliveryprinciples of project managementwbs
On this page

Ask about this page

KEVOS AIZoo Relocation Project—Part 3: WBS, Schedule and Critical Path

KEVOS knowledge first · trusted web sources when needed

Home/ Project Delivery/ Principles of Project Management

KEVOS® Project Delivery Handbook

Zoo Relocation Project—Part 3: WBS, Schedule and Critical Path

18 months, a zero-casualty mandate, a reuse-enclosures instruction, and a staged-closure strategy that overlaps planning with execution.

9 min read1,793 words Guide 49 of 57Reviewed 2026-08-13
In this handbook article
  1. The Challenge
  2. The PM Framework Applied
  3. Step 1: Scope Baseline — Scope Statement → WBS → WBS Dictionary
  4. Step 2: Build the WBS
  5. Step 3: Decompose to work package level
  6. Step 4: Sequence into a network diagram
  7. Step 5: Calculate the critical path
  8. Step 6: Fast-track or crash where required
  9. Step 7: Baseline the schedule
  10. The Result
  11. The Pitfalls
  12. Knowledge Check
  13. Key Takeaways
  14. References

Source and edition context

Source basis: This handbook article is adapted from the supplied file(s): 50. Inside the Zoo Relocation Project — Part 3.md.

Interpretation rule: Named scenarios, schedules, percentages, monetary values and thresholds are source examples or illustrative proposals unless an identified authority, contract or approved baseline makes them mandatory.

PMI edition context: The supplied notes primarily teach fifth- and sixth-edition process groups and knowledge areas. PMI currently publishes the PMBOK® Guide—Eighth Edition, which retains the principles and performance-domain foundation while presenting evolved, non-prescriptive process guidance. Historical counts in this article remain for source/course context, not as a claim about the current edition.

18 months, a zero-casualty mandate, a reuse-enclosures instruction, and a staged-closure strategy that overlaps planning with execution. Part 3 builds the WBS, network diagram, and critical path.

Series recap. Parts 1–2 produced the Charter, Stakeholder Engagement Plan, and Communications Plan. Part 3 enters the technical heart of project planning: scope decomposition and schedule construction.

The Challenge

The CEO's letter contains requirements that, on paper, do not fit in the available time:

Requirement Time Implication
Sell current site within 12 months Planning and site acquisition must run in parallel with the sale
Operational within 18 months of public closure Closure cannot happen until the new site can re-house animals
Retain and reuse existing enclosures Each exhibit has a dismantle → transport → re-erect cycle
Zero-percent casualty rate Animal transport cannot be rushed or paralleled aggressively
Staged relocation permitted Some flexibility — but only if the new site is partially operational
Full staff retention Workforce must be productively employed throughout

These requirements are not all satisfiable under a naive waterfall schedule. The project must be broken into overlapping workstreams — fast-tracking in PMBOK language, phased delivery in heavy-engineering practice.

The PM Framework Applied

Step 1: Scope Baseline — Scope Statement → WBS → WBS Dictionary

PMBOK's Scope Management (Chapter 5) makes the sequencing explicit. The scope baseline consists of three artefacts:

  1. Project Scope Statement — a prose document of scope, deliverables, acceptance criteria, exclusions, constraints, and assumptions.
  2. WBS — hierarchical decomposition of scope into deliverables and work packages.
  3. WBS Dictionary — detailed information per WBS element.

The scope statement must name what is out of scope: ongoing operation of the new site beyond opening, long-term animal husbandry training programs, capital fundraising beyond sale proceeds, legal disputes from the site handover. Declaring exclusions is how the PM prevents the project absorbing tasks that belong to business-as-usual.

Step 2: Build the WBS

A WBS decomposes project deliverables into progressively smaller components until each bottom-level element (a work package) is small enough to be estimated, assigned, and tracked. The 8/80 rule: no work package under 8 hours or over 80 hours.

Process and relationship map
1.0 Zoo Relocation Project
1.1 Project Management
1.2 Old Site Sale
1.3 New Site Acquisition
1.4 Design & Construction
1.5 Salvage & Asset Transfer
1.6 Animal Relocation
1.7 Staff Transition
1.8 Opening & Commissioning
1.9 Project Closure
1.1.1 Planning & Control
1.1.2 Stakeholder & Comms
1.1.3 Risk Management
1.1.4 Governance Reporting
1.6.1 Welfare Protocols
1.6.2 Transport Procurement
1.6.3 Regulatory Approvals
1.6.4 Staged Species Moves
1.6.5 Quarantine & Monitoring
Relationship details
FromRelationshipTo
1.0 Zoo Relocation Projectleads to1.1 Project Management
1.0 Zoo Relocation Projectleads to1.2 Old Site Sale
1.0 Zoo Relocation Projectleads to1.3 New Site Acquisition
1.0 Zoo Relocation Projectleads to1.4 Design & Construction
1.0 Zoo Relocation Projectleads to1.5 Salvage & Asset Transfer
1.0 Zoo Relocation Projectleads to1.6 Animal Relocation
1.0 Zoo Relocation Projectleads to1.7 Staff Transition
1.0 Zoo Relocation Projectleads to1.8 Opening & Commissioning
1.0 Zoo Relocation Projectleads to1.9 Project Closure
1.1 Project Managementleads to1.1.1 Planning & Control
1.1 Project Managementleads to1.1.2 Stakeholder & Comms
1.1 Project Managementleads to1.1.3 Risk Management
1.1 Project Managementleads to1.1.4 Governance Reporting
1.6 Animal Relocationleads to1.6.1 Welfare Protocols
1.6 Animal Relocationleads to1.6.2 Transport Procurement
1.6 Animal Relocationleads to1.6.3 Regulatory Approvals
1.6 Animal Relocationleads to1.6.4 Staged Species Moves
1.6 Animal Relocationleads to1.6.5 Quarantine & Monitoring

Two deliberate choices: Project Management (1.1) is itself a WBS element — PM activities consume real resources and must be visible in the WBS. Animal Relocation (1.6) is a top-level element — on a project where welfare is the dominant quality constraint, hiding it inside "Operations" is how zero-casualty commitments become 98% casualty rates.

Step 3: Decompose to work package level

Taking branch 1.6:

WBS Code Work Package Effort (hrs) Responsible
1.6.1.1 Welfare protocols — mammals 40 Senior Curator (Mammals)
1.6.1.2 Welfare protocols — reptiles 32 Senior Curator (Herpetology)
1.6.1.3 Welfare protocols — birds 32 Senior Curator (Avian)
1.6.1.4 Welfare protocols — aquatic 48 Senior Curator (Aquatic)
1.6.1.5 Independent vet review 24 External Vet
1.6.2.1 Specialist transport RFP 24 Procurement
1.6.2.2 Transport tender evaluation 16 Procurement + Curators
1.6.3.1 State wildlife permits 40 PM + Legal

Each row passes 8/80, has a single named responsible party, and has a measurable completion criterion.

Step 4: Sequence into a network diagram

The WBS says what. It says nothing about when. Scheduling begins by identifying dependencies. The four dependency types from PMBOK are Finish-to-Start (most common), Start-to-Start, Finish-to-Finish, and Start-to-Finish (rare).

Process and relationship map
Charter Signed
Site Selection
Old Site Sale
Lease Signed
Permits
Design
Salvage
Construction
Staff Transition
Stage 1 Move
Public Closure
Stage 2 Move
Commissioning
Opening
Relationship details
FromRelationshipTo
Startleads toCharter Signed
Charter Signedleads toSite Selection
Charter Signedleads toOld Site Sale
Site Selectionleads toLease Signed
Lease Signedleads toPermits
Lease Signedleads toDesign
Old Site Saleleads toConstruction
Designleads toConstruction
Salvageleads toConstruction
Permitsleads toStage 1 Move
Constructionleads toStage 1 Move
Charter Signedleads toStaff Transition
Stage 1 Moveleads toPublic Closure
Public Closureleads toStage 2 Move
Stage 2 Moveleads toCommissioning
Staff Transitionleads toCommissioning
Commissioningleads toOpening
Openingleads toEnd

Red nodes are the critical path — the longest chain of dependent activities, which determines minimum project duration. A one-day delay to any critical-path activity delays the project by one day.

Step 5: Calculate the critical path

Definition — Critical Path. The sequence of activities that determines the minimum project duration. Critical-path activities have zero total float.

Formally, via forward and backward passes:

TFi=LSi−ESi=LFi−EFiTF_{i} = LS_{i} - ES_{i} = LF_{i} - EF_{i}

For large projects the arithmetic is done by scheduling software (Primavera P6, MS Project). What the PM must understand is the implication: critical-path activities demand disproportionate management attention, and adding resources to non-critical activities is usually a waste of money.

Step 6: Fast-track or crash where required

  • Fast-tracking — overlapping sequential activities. Costs nothing but increases rework risk.
  • Crashing — adding resources to critical-path activities. Costs money, yields diminishing returns.

For the Zoo, fast-tracking might mean beginning salvage of low-risk assets before public closure. Crashing might mean running two construction crews in parallel. Both decisions must be logged against risk.

Step 7: Baseline the schedule

Zoo Relocation — Baseline Schedule
WorkstreamActivityTypeTiming / dependency / duration
InitiationCharter & StakeholderActivitydone · init · 2025-01-01 · 30d
Finance & SiteOld Site SaleActivityactive · sale · 2025-01-15 · 330d
Finance & SiteNew Site SelectionActivityactive · site · 2025-02-01 · 90d
Finance & SiteLease ExecutionMilestonemilestone · lease · after site · 0d
Finance & SiteRegulatory PermitsActivitycrit · perm · after lease · 120d
Design & BuildNew Site DesignActivitycrit · des · after lease · 90d
Design & BuildConstruction Phase 1Activitycrit · b1 · after des · 150d
Design & BuildConstruction Phase 2Activitycrit · b2 · after b1 · 120d
Animal RelocationWelfare ProtocolsActivitywp · 2025-03-01 · 90d
Animal RelocationStage 1 MovesActivitys1 · after b1 · 60d
Animal RelocationPublic ClosureMilestonemilestone · closure · after s1 · 0d
Animal RelocationStage 2 MovesActivitycrit · s2 · after closure · 120d
Animal RelocationQuarantineActivityquar · after s2 · 60d
CommissioningCommissioningActivitycrit · comm · after quar · 60d
CommissioningPublic OpeningMilestonemilestone · open · after comm · 0d
Process and relationship map
Work Breakdown Structure
1.0 Project
1.1 Design
1.2 Procurement
1.3 Build
1.4 Test
Derived Schedule
Design Task
Procurement Task
Build Task
Test Task
Relationship details
FromRelationshipTo
1.0 Projectleads to1.1 Design
1.0 Projectleads to1.2 Procurement
1.0 Projectleads to1.3 Build
1.0 Projectleads to1.4 Test
Design Taskleads toProcurement Task
Procurement Taskleads toBuild Task
Build Taskleads toTest Task
1.1 Designleads toDesign Task
Design Taskleads tolink
1.2 Procurementleads toProcurement Task
Procurement Taskleads tolink
1.3 Buildleads toBuild Task
Build Taskleads tolink
1.4 Testleads toTest Task
Test Taskleads tolink

The Result

Four additional controlled artefacts: Scope Statement, WBS, WBS Dictionary, Baselined Project Schedule. Together with the charter and stakeholder plan, these constitute the performance measurement baseline for scope and schedule.

The Pitfalls

  • Skipping the scope statement. Leaves the WBS with no textual anchor.
  • Decomposing by department rather than deliverable. A WBS organised by "Engineering, HR, Finance" is an org chart, not a WBS.
  • Omitting project management from the WBS. PM is work; work must be in the WBS.
  • Wrong work package sizing. Over 80 hours cannot be estimated accurately; under 8 hours generates tracking overhead exceeding its value.
  • Confusing the WBS with the schedule. The WBS has no time dimension.
  • Fast-tracking without risk analysis. Overlapping previously sequential activities always increases risk.
  • Treating the baseline as unchangeable. The baseline is the reference for measuring change, not a prohibition against it.

Knowledge Check

  1. The site sale takes 14 months instead of 12. Which downstream activities are affected, and does the critical path change?
  2. The lead transport contractor goes into administration two weeks before Stage 2. Which work packages are affected, and what are your options?
  3. During the forward pass you discover construction has 45 days of float but the permit activity has 0. The construction manager asks for an additional crew. How do you respond?

Key Takeaways

  • The scope baseline comprises the Scope Statement, WBS, and WBS Dictionary — all three required.
  • The WBS decomposes into deliverables, not activities.
  • Work packages must obey the 8/80 rule.
  • Project management itself is a WBS element.
  • The critical path is the longest chain of dependent activities through the network.
  • Schedule compression is achieved through fast-tracking or crashing — both carry risk implications.

References

  • Project Management Institute 2017, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 6th edn, PMI, Newtown Square, PA.
  • Kerzner, H 2017, Project Management: A Systems Approach, 12th edn, Wiley, Hoboken, NJ.
  • Burke, R 2013, Project Management: Planning and Control Techniques, 5th edn, Wiley, Chichester.
  • Lewis, JP 2011, Project Planning, Scheduling and Control, 5th edn, McGraw-Hill, New York.
  • University of South Australia 2015, MPM411 Zoo Relocation Project Brief, UniSA, Adelaide.

Continue learning

Zoo Relocation Case StudyZoo Relocation Project—Part 2: Stakeholder Power and Engagement6 min readZoo Relocation Case StudyZoo Relocation Project—Part 4: Risk Management8 min readProject PlanningMastering the Work Breakdown Structure10 min readProject PlanningProject Scheduling, Gantt Charts and the Critical Path13 min read

Prepared for the KEVOS® Knowledge Library. Apply the governing contract, approved project method and current standards to live work.

Continue learning

Zoo Relocation Project—Part 2: Stakeholder Power and EngagementGuide · Principles of Project ManagementNEXT LESSON →Zoo Relocation Project—Part 4: Risk ManagementGuide · Principles of Project ManagementZoo Relocation Project—Part 1: From CEO Letter to Signed CharterGuide · Principles of Project ManagementZoo Relocation Project—Part 5: Implementation Staging PlanGuide · Principles of Project Management