Templates & Examples · Assess and Implement Changes

Simple Change Request Form

A handbook-style simple change request form with field guidance, workflow, review checks and source-derived example evidence.

10 min readTemplate & handbookSource-groundedUpdated 13 Aug 2026
Decision supportedcontrol whether a proposed alteration is understood, assessed, authorised and traceable before it changes an approved baseline.
Best used whenThe project needs a visible, reviewable record rather than an informal conversation or undocumented spreadsheet.
Control principleFacts, assumptions, forecasts, approvals and actions should remain distinguishable throughout the artefact lifecycle.
Handbook overview

What this artefact controls

Simple Change Request Form should be treated as a decision instrument, not as paperwork completed for its own sake. Its practical value comes from making the underlying decision, evidence, ownership and review cycle visible. In this handbook, the supplied source structure is retained as the factual basis while the surrounding guidance explains how to complete, review and maintain it in day-to-day project delivery.

The source set repeatedly links project documents to broader control relationships: scope creates the work to be scheduled and costed; resources execute that work; stakeholders influence acceptance and change; risk captures uncertainty; quality establishes evidence of conformance; and performance information explains whether the project is still moving toward its intended outcome. Simple Change Request Form belongs in that integrated system. It should therefore use identifiers and terminology consistent with adjacent project records so that a reviewer can trace a decision across documents without relying on memory.

Before filling any field, write one sentence describing the decision or control action the completed artefact must support. Then identify the accountable owner, contributors, reviewers, approval authority and next review trigger. This prevents a common failure in project documentation: every box is filled, but nobody can explain what decision the document enables or who must act when conditions change.

Inputcurrent approved baseline
Inputchange trigger or request
Inputimpact estimates from affected disciplines
Outputrecorded disposition
Outputapproved or rejected change decision
Outputupdated baseline or implementation action
Integrated visual

How the information fits together

Define
→
Complete
→
Review
→
Approve / act
→
Maintain

This visual is an HTML/CSS interpretation for the KEVOS article reader. It conveys the decision structure without embedding the supplied source artwork as a screenshot.

Field-by-field guidance

Complete the template with traceable information

The following field map is extracted from the supplied blank or completed source document where text was available. Wording has been normalised for web readability, but the source structure remains the basis. Where a field is not applicable, record why rather than silently leaving a potentially important control blank.

Source field / sectionWhat to recordReview test
CHANGE REQUESTRecord the minimum evidence needed for change request to support the control whether a proposed alteration is understood, assessed, authorised and traceable before it changes an approved baseline.The entry is specific, traceable and reviewable.
RequestorRecord the minimum evidence needed for requestor to support the control whether a proposed alteration is understood, assessed, authorised and traceable before it changes an approved baseline.The entry is specific, traceable and reviewable.
IDAssign a unique, stable identifier that can be referenced from reports, changes, risks, requirements or evidence.The entry is specific, traceable and reviewable.
CategoryRecord the minimum evidence needed for category to support the control whether a proposed alteration is understood, assessed, authorised and traceable before it changes an approved baseline.The entry is specific, traceable and reviewable.
[ ] ScopeRecord the minimum evidence needed for [ ] scope to support the control whether a proposed alteration is understood, assessed, authorised and traceable before it changes an approved baseline.The entry is specific, traceable and reviewable.
[ ] QualityState the condition in testable terms and identify the evidence or method that proves it has been satisfied.A separate reviewer can verify it objectively.
[ ] RequirementsState the condition in testable terms and identify the evidence or method that proves it has been satisfied.A separate reviewer can verify it objectively.
[ ] CostRecord currency, price date, inclusion boundary and source of the value; separate estimate, baseline, actual and forecast.Units, currency and basis reconcile.
[ ] ScheduleUse the approved working calendar and state whether the value is effort, elapsed duration, planned date, forecast date or actual date.The entry is specific, traceable and reviewable.
[ ] DocumentsRecord the minimum evidence needed for [ ] documents to support the control whether a proposed alteration is understood, assessed, authorised and traceable before it changes an approved baseline.The entry is specific, traceable and reviewable.
Detailed Description of Proposed ChangeWrite an observable, specific statement that a reviewer outside the drafting team can understand without verbal explanation.The entry is specific, traceable and reviewable.
Justification for Proposed ChangeRecord the minimum evidence needed for justification for proposed change to support the control whether a proposed alteration is understood, assessed, authorised and traceable before it changes an approved baseline.The entry is specific, traceable and reviewable.
Impacts (Summary)Apply the project-defined scale or method and retain the basis for the rating so later reviewers can reproduce it.Scale and calculation method are defined.
DispositionRecord the minimum evidence needed for disposition to support the control whether a proposed alteration is understood, assessed, authorised and traceable before it changes an approved baseline.The entry is specific, traceable and reviewable.
[ ] ApproveRecord the minimum evidence needed for [ ] approve to support the control whether a proposed alteration is understood, assessed, authorised and traceable before it changes an approved baseline.The entry is specific, traceable and reviewable.
[ ] DeferRecord the minimum evidence needed for [ ] defer to support the control whether a proposed alteration is understood, assessed, authorised and traceable before it changes an approved baseline.The entry is specific, traceable and reviewable.
[ ] RejectRecord the minimum evidence needed for [ ] reject to support the control whether a proposed alteration is understood, assessed, authorised and traceable before it changes an approved baseline.The entry is specific, traceable and reviewable.
Justification (CCB / PM)Record the minimum evidence needed for justification (ccb / pm) to support the control whether a proposed alteration is understood, assessed, authorised and traceable before it changes an approved baseline.The entry is specific, traceable and reviewable.
Working template

Blank web-ready structure

This compact version is designed for copying into a project working note or for translating into your organisation’s controlled form. It is not a claim that these are the only fields required by every organisation, contract or jurisdiction.

CHANGE REQUESTEnter controlled project information here…
RequestorEnter controlled project information here…
IDEnter controlled project information here…
CategoryEnter controlled project information here…
[ ] ScopeEnter controlled project information here…
[ ] QualityEnter controlled project information here…
[ ] RequirementsEnter controlled project information here…
[ ] CostEnter controlled project information here…
[ ] ScheduleEnter controlled project information here…
[ ] DocumentsEnter controlled project information here…
Detailed Description of Proposed ChangeEnter controlled project information here…
Justification for Proposed ChangeEnter controlled project information here…
Supplied worked material

What the uploaded example demonstrates

The source set uses a recurring worked project — Mary’s Consulting and its new company website — to show how project artefacts connect. The examples are useful because the same scope, team, costs, risks, stakeholders and milestones recur across multiple forms, allowing the reader to see how one project decision propagates through the documentation system. Any numerical value below is a source example or a calculation explicitly identified as such; it should not be treated as a universal project standard.

  • Project Date Oct 15,
  • Title: Prepared: 2026
  • CR-008 Requestor: Marketing Lead
  • Affects ~50 launch-tier consultant cards. Out of scope: any other social platforms; LinkedIn data scraping;
  • Scope: +1 small element on bio card; +1 data field collected from consultants (LinkedIn URL).
  • Requirements: Adds F-08 LinkedIn-link display to RTM.
  • Cost: Estimated +$400 (Bob 4 hrs frontend; Christine 2 hrs to collect URLs from launch-tier consultants). Drawn from
  • Schedule: No critical-path impact. Work fits in existing build buffer.
How to use the example. Copy the reasoning pattern, not the number. Replace example dates, thresholds, scores, names and amounts with evidence from the actual project, and retain the source or calculation basis for every material value.
Operating method

Step-by-step workflow

Step 1
Capture the trigger and describe the requested change without assuming approval.
Step 2
Check the affected scope, schedule, cost, quality, resources, risk, procurement and stakeholder commitments.
Step 3
Quantify impacts and identify alternatives, including the option to do nothing.
Step 4
Assign a decision owner with the authority required by the governance model.
Step 5
Record the decision, rationale, conditions and effective date.
Step 6
If approved, update controlled baselines and communicate implementation responsibilities.

For controlled project records, the final step is not “save the file”. The final step is to make the current approved state discoverable, communicate the decision to affected people and define the next review trigger. That trigger may be a phase gate, threshold breach, approved change, new stakeholder, supplier event, forecast movement, risk trigger or a scheduled review date.

Verification

Review checklist before approval or use

  • The request is specific enough that two reviewers interpret the same change.
  • Impacts are stated against current baselines, not against memory.
  • Alternatives and consequences of rejection are visible.
  • Approval authority matches the value and risk of the change.
  • Implementation actions have owners and due dates.
  • Superseded documents are identifiable and retained according to document-control rules.

Run the review from the perspective of a competent person who did not attend the drafting meeting. If they cannot reconstruct the basis, current state and required next action from the record and its cited evidence, the artefact is not yet controlled enough for a material decision.

Practical failure modes

Common mistakes and recovery actions

Failure mode 1

Treating a change discussion as an approval.

Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.

Failure mode 2

Assessing cost but ignoring schedule, quality or risk effects.

Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.

Failure mode 3

Allowing work to start before the decision is recorded.

Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.

Failure mode 4

Updating the deliverable but not the baseline documents.

Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.

Failure mode 5

Closing the request without confirming the change was implemented as authorised.

Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.

Governance & hand-offs

Keep the document alive after first approval

A project artefact is only useful while its status is known. Give it a unique identifier, version, owner, approval state and effective date. Define what types of change require reapproval and what updates can be made administratively. Retain superseded versions when the record is needed to explain a historical decision, claim, audit, acceptance or lesson.

Use the document in reviews by focusing on exceptions and decisions rather than reading every field aloud. Ask what has changed since the last review, what assumption has been invalidated, what threshold has been crossed, which decision is now due and which action remains without an owner. This converts the artefact from static documentation into a control mechanism.

At hand-off, confirm that downstream users can interpret the identifiers, units, assumptions and status values without relying on the original author. For project close-out, make sure unresolved items have an operational owner and a clear retention location. A closed project should not leave behind orphaned risks, undocumented support obligations, unverified benefits or ambiguous acceptance evidence.

Source fidelity

Source basis and limitations

This page is an original KEVOS handbook synthesis grounded in the uploaded source files. It intentionally paraphrases and restructures the material for practical application rather than reproducing the source documents as images. Where the source contains an illustrative project value, that value remains an example. Where a required blank source was absent, the limitation is stated explicitly rather than silently inventing a missing form.

  • PMBOK+8+Plans+and+Documents/Assess and Implement changes/Change_Request_Simple_BLANK.pdf
  • PMBOK+8+Plans+and+Documents/Assess and Implement changes/Change_Request_Simple_FILLED.pdf

Current authoritative context used for the reference pages: Project Management Institute, PMBOK® Guide — Eighth Edition and the 2026 PMP Examination Content Outline. The article package does not reproduce substantial PMI publication text.

Continue learning

Related KEVOS pages

Change Request FormManage Project ExecutionChange LogAssess and Implement ChangesChange Request AssessmentAssess and Implement Changes

Continue learning

Change Request AssessmentGuide · Project TemplatesChange LogGuide · Project TemplatesChange Request FormGuide · Project TemplatesResource Breakdown Structure (Template)Guide · Project Templates