GuidePublished 13 Aug 202610 min readBy Kevin Joginpmiprocesschartpmbok
On this page

Ask about this page

KEVOS AIPMI Process Chart: PMBOK® 6th vs 8th Edition Synthesis

KEVOS knowledge first · trusted web sources when needed

Templates & Examples · Reference Documents

PMI Process Chart: PMBOK® 6th vs 8th Edition Synthesis

A practical KEVOS reference for pmi process chart: pmbok® 6th vs 8th edition synthesis, connecting supplied project-management charts, domains, processes and decision use.

11 min readReference guideSource-groundedUpdated 13 Aug 2026
Decision supportedprovide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.
Best used whenThe project needs a visible, reviewable record rather than an informal conversation or undocumented spreadsheet.
Control principleFacts, assumptions, forecasts, approvals and actions should remain distinguishable throughout the artefact lifecycle.
Edition note. The supplied material juxtaposes the legacy 49-process view with PMBOK® Guide Eighth Edition performance-domain and focus-area language. Use the page as a synthesis and navigation aid, not as a claim that one chart is a mandatory sequence for every project.
Handbook overview

What this artefact controls

PMI Process Chart: PMBOK® 6th vs 8th Edition Synthesis should be treated as a decision instrument, not as paperwork completed for its own sake. Its practical value comes from making the underlying decision, evidence, ownership and review cycle visible. In this handbook, the supplied source structure is retained as the factual basis while the surrounding guidance explains how to complete, review and maintain it in day-to-day project delivery.

The source set repeatedly links project documents to broader control relationships: scope creates the work to be scheduled and costed; resources execute that work; stakeholders influence acceptance and change; risk captures uncertainty; quality establishes evidence of conformance; and performance information explains whether the project is still moving toward its intended outcome. PMI Process Chart: PMBOK® 6th vs 8th Edition Synthesis belongs in that integrated system. It should therefore use identifiers and terminology consistent with adjacent project records so that a reviewer can trace a decision across documents without relying on memory.

Before filling any field, write one sentence describing the decision or control action the completed artefact must support. Then identify the accountable owner, contributors, reviewers, approval authority and next review trigger. This prevents a common failure in project documentation: every box is filled, but nobody can explain what decision the document enables or who must act when conditions change.

Inputsupplied process charts and training references
InputPMI source documents in the uploaded set
Inputprocess-output relationships
Outputcross-reference model
Outputterminology map
Outputprocess/domain comparison
Integrated visual

How the information fits together

Governance
Scope
Schedule
Finance
Stakeholders
Resources
Risk

This visual is an HTML/CSS interpretation for the KEVOS article reader. It conveys the decision structure without embedding the supplied source artwork as a screenshot.

Field-by-field guidance

Complete the template with traceable information

The following field map is extracted from the supplied blank or completed source document where text was available. Wording has been normalised for web readability, but the source structure remains the basis. Where a field is not applicable, record why rather than silently leaving a potentially important control blank.

Source field / sectionWhat to recordReview test
PMBOK 8th Edition Process ChartRecord the minimum evidence needed for pmbok 8th edition process chart to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
Andrew Ramdayal, PMP Exam Prep CourseRecord the minimum evidence needed for andrew ramdayal, pmp exam prep course to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
PerformanceRecord the minimum evidence needed for performance to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
InitiatingRecord the minimum evidence needed for initiating to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
PlanningRecord the minimum evidence needed for planning to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
ExecutingRecord the minimum evidence needed for executing to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
MonitoringRecord the minimum evidence needed for monitoring to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
ClosingRecord the minimum evidence needed for closing to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
DomainsRecord the minimum evidence needed for domains to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
Focus AreaRecord the minimum evidence needed for focus area to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
and ControllingRecord the minimum evidence needed for and controlling to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
FocusRecord the minimum evidence needed for focus to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
AreaRecord the minimum evidence needed for area to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
GovernanceRecord the minimum evidence needed for governance to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
 InitiateRecord the minimum evidence needed for  initiate to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
 Integrate andRecord currency, price date, inclusion boundary and source of the value; separate estimate, baseline, actual and forecast.The entry is specific, traceable and reviewable.
 Manage ProjectRecord the minimum evidence needed for  manage project to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
 Monitor andRecord the minimum evidence needed for  monitor and to support the provide a navigable reference model that helps practitioners connect concepts, processes, domains, outputs and delivery approaches without turning guidance into a rigid recipe.The entry is specific, traceable and reviewable.
Working template

Blank web-ready structure

This compact version is designed for copying into a project working note or for translating into your organisation’s controlled form. It is not a claim that these are the only fields required by every organisation, contract or jurisdiction.

PMBOK 8th Edition Process ChartEnter controlled project information here…
Andrew Ramdayal, PMP Exam Prep CourseEnter controlled project information here…
PerformanceEnter controlled project information here…
InitiatingEnter controlled project information here…
PlanningEnter controlled project information here…
ExecutingEnter controlled project information here…
MonitoringEnter controlled project information here…
ClosingEnter controlled project information here…
DomainsEnter controlled project information here…
Focus AreaEnter controlled project information here…
and ControllingEnter controlled project information here…
FocusEnter controlled project information here…
Supplied worked material

What the uploaded example demonstrates

The source set uses a recurring worked project — Mary’s Consulting and its new company website — to show how project artefacts connect. The examples are useful because the same scope, team, costs, risks, stakeholders and milestones recur across multiple forms, allowing the reader to see how one project decision propagates through the documentation system. Any numerical value below is a source example or a calculation explicitly identified as such; it should not be treated as a universal project standard.

  •  Power: Level of authority
  •  Urgency: Immediate attention
  •  Legitimacy: How appropriate is their
  •  Directions of Influence:
  •  Upward: Senior management
  •  Downward: Team members
  •  Outward: Vendors, government, public,
  •  Sideward: peers such as other project
How to use the example. Copy the reasoning pattern, not the number. Replace example dates, thresholds, scores, names and amounts with evidence from the actual project, and retain the source or calculation basis for every material value.
Operating method

Step-by-step workflow

Step 1
Start with the business or delivery question, not the chart.
Step 2
Locate the relevant domain, process or document family.
Step 3
Identify the inputs and outputs that connect the current decision to adjacent work.
Step 4
Check whether the project context is predictive, adaptive, hybrid or mixed.
Step 5
Use the reference as a navigation aid, then apply judgement and project-specific governance.
Step 6
Record the actual method chosen so the team can work consistently.

For controlled project records, the final step is not “save the file”. The final step is to make the current approved state discoverable, communicate the decision to affected people and define the next review trigger. That trigger may be a phase gate, threshold breach, approved change, new stakeholder, supplier event, forecast movement, risk trigger or a scheduled review date.

Verification

Review checklist before approval or use

  • The reference distinguishes historical process models from current principles and domains.
  • Illustrative process maps are not described as mandatory sequencing.
  • Edition and source context are explicit.
  • Links between governance, scope, schedule, finance, stakeholders, resources and risk are visible.
  • The page helps users find the right template or decision artefact.
  • Current PMI facts are separated from the supplied training material.

Run the review from the perspective of a competent person who did not attend the drafting meeting. If they cannot reconstruct the basis, current state and required next action from the record and its cited evidence, the artefact is not yet controlled enough for a material decision.

Practical failure modes

Common mistakes and recovery actions

Failure mode 1

Memorising a chart without understanding the decision it supports.

Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.

Failure mode 2

Treating one delivery approach as universally correct.

Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.

Failure mode 3

Combining editions without stating the differences.

Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.

Failure mode 4

Using an exam-preparation heuristic as a contractual requirement.

Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.

Failure mode 5

Confusing process names with organisational job titles.

Recovery: return to the approved objective or baseline, identify the missing evidence or decision owner, and record the corrective action before proceeding.

Governance & hand-offs

Keep the document alive after first approval

A project artefact is only useful while its status is known. Give it a unique identifier, version, owner, approval state and effective date. Define what types of change require reapproval and what updates can be made administratively. Retain superseded versions when the record is needed to explain a historical decision, claim, audit, acceptance or lesson.

Use the document in reviews by focusing on exceptions and decisions rather than reading every field aloud. Ask what has changed since the last review, what assumption has been invalidated, what threshold has been crossed, which decision is now due and which action remains without an owner. This converts the artefact from static documentation into a control mechanism.

At hand-off, confirm that downstream users can interpret the identifiers, units, assumptions and status values without relying on the original author. For project close-out, make sure unresolved items have an operational owner and a clear retention location. A closed project should not leave behind orphaned risks, undocumented support obligations, unverified benefits or ambiguous acceptance evidence.

Source fidelity

Source basis and limitations

This page is an original KEVOS handbook synthesis grounded in the uploaded source files. It intentionally paraphrases and restructures the material for practical application rather than reproducing the source documents as images. Where the source contains an illustrative project value, that value remains an example. Where a required blank source was absent, the limitation is stated explicitly rather than silently inventing a missing form.

  • PMBOK+8+Process+Chart.pdf
  • PM+Processes.pdf
  • Process+Flow.pdf
  • Major+Outputs+by+process+groups.pdf
  • Project+Documents.pdf
  • PMBOK+Process+Presentation.pdf
  • PM+Predictive+Terms.pdf

Current authoritative context used for the reference pages: Project Management Institute, PMBOK® Guide — Eighth Edition and the 2026 PMP Examination Content Outline. The article package does not reproduce substantial PMI publication text.

Continue learning

Related KEVOS pages

Communications Management Plan ExamplePlan Communication ManagementIssue Log Template & ExampleManage Project ExecutionManaging Uncertainty in Modern ProjectsReference Documents

Continue learning

Managing Uncertainty in Modern ProjectsGuide · Reference DocumentsPMI Process Chart: PMBOK® 6th vs 8th Edition SynthesisTemplate · Reference DocumentsMathematical Notation and Symbols: a ReferenceGuide · Engineering MathematicsCommunications Management Plan ExampleGuide · Project Templates
KEVOS · Engineering, manufacturing and project improvement
ArticlesServicesCase studiesAboutContact
© 2026 KEVOS®