← ArticlesChange Request AssessmentTemplates & Examples · Project TemplatesLesson 34/55← PrevNext →
TemplatePublished 10 Jul 2026Updated 13 Aug 20269 min readBy Kevin Joginchange managementchange assessmentdecision analysisproject control
On this page

Ask about this page

KEVOS AIChange Request Assessment

KEVOS knowledge first · trusted web sources when needed

KEVOS®
Templates & Examples · Project Templates
Templates & Examples / Project Templates

Change Assessment

Working assessment performed by the PM and CCB to support a disposition decision by evaluating alternatives and implementation plans.

10 min read 3 sections Document Template Worked Example
ALT A1 ALT A2 ALT A3 ALT A4 Multi-Criteria Decision 14 Jul 2026

In this resource

  1. Purpose of the Change Request Assessment
  2. Blank Template
  3. Worked Example: Mary's Consulting

§1 Purpose of the Change Request Assessment

The Change Request Assessment is the analytical engine behind project change control. It forces the project team to objectively evaluate multiple paths forward, rather than simply accepting or rejecting a proposal at face value.

While the Change Request form initiates the process, the Change Assessment is conducted independently by the Project Manager (PM) and the Change Control Board (CCB). The core of this document is the Multi-Criteria Decision Analysis (MCDA), which evaluates competing alternatives (e.g., rejecting, deferring, or implementing with variations) against weighted project constraints.

Implementation Planning A secondary function of this document is ensuring that an approved change does not fall through the cracks. The document concludes with a high-level implementation plan assigning ownership for updating baselines, requirements traceability matrices (RTMs), and technical deliverables.
Contents

§2 Blank Template

A standardized structure for comparing alternatives and tracking the disposition logic prior to implementation.

This document should be completed for any non-trivial change request. The weighting assigned in the MCDA matrix should reflect the current phase priorities of the project (e.g., in late delivery stages, schedule risk might carry a 40% weight, whereas in early design, stakeholder value might carry a 50% weight).

CHANGE REQUEST ASSESSMENT

Project Title [Insert Project Name]
Date Prepared [YYYY-MM-DD]

1. Reference

Change Request ID & Title [CR-###] - [Brief Title]
Assessed By [Name and Role]
Requestor [Name and Role]
Submission Date [YYYY-MM-DD]

2. Alternatives Considered

# Alternative Cost Schedule Pros / Cons
A1 [Do nothing / Reject] [$0] [None] + [Pro]
- [Con]
A2 [Defer to Phase X] [Impact] [Impact] + [Pro]
- [Con]
A3 [Implement as requested] [Impact] [Impact] + [Pro]
- [Con]
A4 [Alternative implementation] [Impact] [Impact] + [Pro]
- [Con]

3. Multi-Criteria Decision Analysis

Weighted scoring of the alternatives. Scale: 1 (Poor) to 5 (Excellent). Higher score = better fit.

Criterion Weight A1 A2 A3 A4
Stakeholder value [X]% [Score * W] [Score * W] [Score * W] [Score * W]
Cost impact [X]% [Score * W] [Score * W] [Score * W] [Score * W]
Schedule risk [X]% [Score * W] [Score * W] [Score * W] [Score * W]
Quality / Scope risk [X]% [Score * W] [Score * W] [Score * W] [Score * W]
Strategic fit [X]% [Score * W] [Score * W] [Score * W] [Score * W]
TOTAL 100% [Total] [Total] [Total] [Total]

4. Recommendation & Implementation Plan

Recommendation Logic
[State the recommended alternative and justify the decision based on the MCDA scoring and broader project strategy.]
Implementation Notes (Post-Approval)
[List actionable next steps required to execute the change. Who updates the RTM? Who adjusts the schedule? Who communicates to stakeholders?]
Contents

§3 Worked Example: Mary's Consulting

A completed example demonstrating the evaluation of four implementation alternatives for a proposed scope addition late in the project lifecycle.

This example assesses CR-008 (adding LinkedIn icons to the consultant directory). Notice how the PM explores an alternative that was not explicitly requested (A4: Broader social presence) to ensure all viable options are mathematically weighed against project constraints.

CHANGE REQUEST ASSESSMENT

Project Title Mary's Consulting - New Company Website
Date Prepared Oct 16, 2026

1. Reference

Change Request ID & Title CR-008 Add LinkedIn icons to consultant bio cards
Assessed By Andrew (PM)
Requestor Marketing Lead
Submission Date Oct 15, 2026

2. Alternatives Considered

# Alternative Cost Schedule Pros / Cons
A1 Do nothing (reject the change) $0 None + No risk to baseline.
- Misses a low-cost / high-perceived-value addition; Sales would have to navigate around it.
A2 Defer to Phase 2 $0 now;
~$600 later
None now + Avoids any current build disruption.
- Costs more later (re-context-switching); Marketing Lead support softens.
A3 Implement now (recommended) $400 None + Inexpensive; high perceived value; fits inside existing build buffer.
- Adds one tracked field to the bio intake form (50 consultants).
A4 Implement broader social presence (LinkedIn + Twitter + site) ~$1,500 +3 days + More comprehensive consultant footprint.
- Out of scope; Marketing Lead did not request; consumes contingency for uncertain value.

3. Multi-Criteria Decision Analysis

Criterion Weight A1 (Reject) A2 (Defer) A3 (Implement) A4 (Broader)
Stakeholder value 30% 1 × 30 = 30 3 × 30 = 90 5 × 30 = 150 4 × 30 = 120
Cost impact 25% 5 × 25 = 125 4 × 25 = 100 4 × 25 = 100 2 × 25 = 50
Schedule risk 20% 5 × 20 = 100 5 × 20 = 100 4 × 20 = 80 2 × 20 = 40
Quality / Scope risk 15% 5 × 15 = 75 5 × 15 = 75 4 × 15 = 60 3 × 15 = 45
Strategic fit 10% 2 × 10 = 20 3 × 10 = 30 5 × 10 = 50 4 × 10 = 40
TOTAL 100% 350 395 440 295

4. Recommendation & Implementation Plan

Recommendation Logic
Approve Alternative A3 - Implement now.

Highest weighted score (440) reflects strong stakeholder value with manageable cost and schedule risk. Cost of $400 fits comfortably within the remaining $11,200 contingency. PM recommends routing to the Sponsor for approval given that the change touches the consultant directory (a sponsor-visible deliverable) and extends the bio data the firm collects from consultants.
Implementation Notes (Post-Approval)
  • Christine to add LinkedIn URL field to bio intake form by Oct 18.
  • Bob to add icon component to bio card template by Oct 22.
  • Update the RTM with new requirement F-08 by Oct 17.
  • Update the Change Log with the approved disposition.
  • No baseline updates required (within contingency, no schedule impact).

Objective Scoring

By forcing the CCB to score alternatives against a weighted matrix, emotional bias (e.g., rejecting an idea simply because it arrived late) is removed from the process.

Unrequested Alternatives

The inclusion of A4 (a broader social presence) demonstrates due diligence. It proves the PM explored extending the idea, but mathematical scoring quickly revealed it wasn't worth the cost.

Actionable Next Steps

The implementation section prevents the common pitfall of a change being "approved" but never executed. It lists names, deliverables, and dates before the CCB even signs off.

Contents

Handbook application: from concept to controlled practice

Purpose. This expanded section turns the original page into a practical handbook. It preserves the supplied material and adds a repeatable way to apply, check and review Change Request Assessment. It does not replace a contract, legislation, a controlled standard, competent engineering judgement or specialist advice.

The operating aim is to make the blank artefact usable by explaining what belongs in each field, who supplies it and how it is reviewed. Read the original explanation first, then use the workflow and checks below to convert knowledge into evidence.

Use Change Request Assessment as a decision instrument rather than an administrative form. The subject terms—change, assessment, request, template, example—need an explicit connection to the project objective, business value and stakeholder commitments. Before completing the artefact, write one sentence stating who will use it, what decision it supports and when that decision is required.

Apply a disciplined information model. Separate facts supported by evidence, forecasts derived from a method, assumptions awaiting validation, constraints that limit choice, risks that may occur, issues that already exist and actions assigned to people. Each material entry should have an owner, date, status and next review point. Where probability or impact scores are used, define the scale so different reviewers interpret it consistently.

A baseline is useful only when changes are visible. Give the artefact an identifier, version, approval state and effective date. Define which changes require reapproval, how superseded versions are retained and where supporting evidence is stored. During reviews, focus on exceptions, decisions and trends rather than reading every field aloud. Record the decision and rationale, not merely that a meeting occurred.

Close the loop beyond delivery. Confirm acceptance criteria, unresolved items, transferred responsibilities and operational ownership. Where benefits are expected, identify the outcome measure, baseline, target, observation period and owner who remains accountable after the project team disbands. Lessons should describe the condition, consequence and reusable action; a generic statement such as “communicate better” cannot improve the next project.

Step-by-step operating method

  1. Name the decision. Write the decision, approval, handover or control activity the completed template must support.
  2. Assign ownership. Nominate one accountable owner and identify contributors, reviewers and approvers.
  3. Gather evidence. Use records, estimates, stakeholder input and source references rather than unsupported opinion.
  4. Complete with discipline. Use consistent dates, units, identifiers, status values and version controls.
  5. Review and maintain. Check completeness and logic, approve the baseline, then update it when trigger conditions occur.

Completion and governance protocol

Start with a short drafting workshop involving the accountable owner and the people who hold the evidence. Complete high-consequence fields first: objective, scope, owner, baseline, acceptance, dependencies and escalation. Mark unknowns as assumptions or actions rather than hiding them behind vague prose. Circulate a review draft, resolve conflicting interpretations, baseline the approved version and place the next review date in an owned schedule.

Information typeMinimum useful contentReview test
OutcomeObservable change and intended recipientNot merely a deliverable or activity
MeasureDefinition, baseline, target, frequency and sourceTwo reviewers would calculate it the same way
OwnershipOne accountable role plus contributors and approverAuthority matches responsibility
UncertaintyAssumption, risk or issue with response and triggerStatus reflects current reality
ControlVersion, approval, review date and change ruleCurrent baseline is identifiable

Common failure modes and recovery actions

1. Watch for

Filling every box even when a field is not applicable instead of recording why.

Recovery: Return to the governing definition or requirement and restate the decision in one sentence.

2. Watch for

Writing vague statements without an owner, measure, date or evidence source.

Recovery: Separate evidence from assumption, assign an owner and set a date for validation.

3. Watch for

Copying a previous project without revalidating assumptions and stakeholders.

Recovery: Run a small counterexample, boundary test, pilot or independent check before proceeding.

4. Watch for

Using the document as a private worksheet when it is meant to support a shared decision.

Recovery: Record the consequence, decision and rationale, then update the controlled baseline.

5. Watch for

Creating an approved baseline but failing to define who maintains it and when.

Recovery: Escalate when the issue affects safety, compliance, acceptance, material value or an agreed tolerance.

Review checklist

  • Is the purpose and intended decision clear to a reader outside the team?
  • Are owners, dates, measures and sources complete and internally consistent?
  • Which fields are assumptions and how will they be validated?
  • What event, threshold or review date causes this document to change?
  • Are mandatory requirements distinguished from recommendations and illustrative values?
  • Are sources, assumptions, units, dates and versions recorded closely enough to reproduce the decision?
  • Have safety, legal, ethical, stakeholder and operational consequences been considered at the appropriate level?
  • Is there a named owner and a trigger for review, escalation, change or retirement?

Questions for deeper application

What is the most important distinction a practitioner must preserve when applying Change Request Assessment?

Answer with a fact or cited source where available. Where evidence is incomplete, record the assumption, consequence, responsible owner and next validation action.

Which assumption about change would change the result most if it proved false?

Answer with a fact or cited source where available. Where evidence is incomplete, record the assumption, consequence, responsible owner and next validation action.

What evidence would allow an independent reviewer to reproduce or challenge the conclusion?

Answer with a fact or cited source where available. Where evidence is incomplete, record the assumption, consequence, responsible owner and next validation action.

Which boundary, exception or failure case has not yet been tested?

Answer with a fact or cited source where available. Where evidence is incomplete, record the assumption, consequence, responsible owner and next validation action.

What must be handed over, monitored or reviewed after the immediate work is complete?

Answer with a fact or cited source where available. Where evidence is incomplete, record the assumption, consequence, responsible owner and next validation action.

Authoritative references and use notes

The sources below were selected as institutional or primary guidance for the broader practice. They support the handbook method; they do not imply that every statement or clause in a source applies to every project. Confirm the current edition, jurisdiction, contract and application before treating any requirement as mandatory.

  • PMI Standards and Publications — Project Management Institute. Used for project, program, portfolio and organisational project management. Accessed 2026-08-13.
  • ISO 31000 family — Risk management — International Organization for Standardization. Used for principles and guidance for enterprise risk management. Accessed 2026-08-13.

Original KEVOS® synthesis · Templates & Examples Series · Built 15 Jul 2026

Continue learning

Change Request FormTemplate · Project TemplatesRequirements Documentation Template & ExampleTemplate · Project TemplatesNEXT LESSON →Activity Cost Estimates Template & ExampleTemplate · Project TemplatesBasic Flowchart TemplateTemplate · Project Templates