KEVOS
ArticlesServicesCase studiesAboutContact
ArticlesServicesCase studiesAboutContact
← ArticlesWhy Costs Increase When Projects AccelerateProject Delivery · Research ProjectsLesson 125/139← PrevNext →
GuidePublished 16 Aug 202613 min readBy KEVOS Editorialtime cost tradeoff r&dproject acceleration costwhy crashing costs moreconvex time cost curve
On this page

Ask about this page

KEVOS AIWhy Costs Increase When Projects Accelerate

KEVOS knowledge first · trusted web sources when needed

KEVOS/Project Delivery/Research Projects/R&D Management Papers
Project DeliveryResearch ProjectsCoreRd Project Management

Why Costs Increase When Projects Accelerate

Compression does not buy time at a flat price. A 1989 practitioner source names four independent causes of the acceleration penalty, and three of them have nothing to do with adding people to the team.

Reading time14 minutes
LevelCore
Topic streamRd Project Management
Source materialR&D Management Papers
Updated2026-08-16

In brief

  • R4 accepts that R&D projects can almost always be accelerated. Its claim is about the price: time is bought with increased development cost, and the price per unit of time keeps rising.
  • Four separate mechanisms drive that. Only the second is conventional diminishing returns to added people — the mechanism most managers reach for first.
  • The other three are informational (tasks start with less information), probabilistic (you fund approaches serial search would have spared you), and structural (the cheap crashing options run out).
  • Each mechanism produces convexity on its own. Together they make the time-cost tradeoff curve convex to the axes, so cost rises at an increasing rate under further compression.
  • One cost is excluded by design: what the talent pulled onto the accelerated project would have produced elsewhere. R4 says plainly that it will not appear in an accountant's figures.

The shape the penalty takes

R4 is a practitioner review and synthesis article from 1989. It reviews a known tradeoff, offers a causal theory for it, and converts published estimates into a single comparable metric. It opens on a case rather than a model.

A large manufacturer of document-imaging equipment began developing a copier model on a deliberately accelerated schedule, to hold competitive position against overseas manufacturers that had taken market share from it. The product moved quickly into pilot production before a serious quality problem surfaced: a wire harness holding together the wires connecting internal components did not meet quality standards. The harness was quickly redesigned — and then the automatic manufacturing equipment that assembled the harness would not function properly. The manufacturing problem was corrected at a reported cost of $1 million.

  1. Schedule compressed
  2. Task handed on early
  3. Defect found in pilot production
  4. Redesign
  5. Downstream tooling fails
  6. Correction cost
From the source

Not an anomaly — the generic shape

R4 presents this cascade as a common experience rather than an unlucky one. The sequence — rushed handoff, design defect, downstream tooling failure — is offered as the standard form the acceleration penalty takes.

Provenance: the $1 million figure is a cost reported in the business press for one case, quoted by R4. It is not a finding of R4's own, and it is not a benchmark for the cost of a rushed handoff.

What follows is the article's causal account. Read the four mechanisms as independent contributors, because the practical mistake is to notice one of them, price it, and call that the cost of speed.

Mechanism 1 — every task starts with less information

R4 describes R&D as very much a heuristic process, where each step builds on the information gained in previous tasks. That dependency is the mechanism. When a project is compressed, some steps begin to overlap, and each task is begun with less information than it would otherwise have had.

The immediate consequence is mistakes and rework. The consequence that matters for the shape of the curve is the second-order one: as the project is compressed further, greater penalties are exacted, because tasks are initiated under increasing uncertainty. The penalty is not a fixed toll for overlapping — it grows with the degree of overlap.

This is the mechanism the opening case illustrates. Nobody was careless. A task was started before the information that would have prevented the defect existed, and the cost surfaced two handoffs downstream. Where that uncertainty comes from in the first place is treated separately, in sources of uncertainty in R&D projects.

Mechanism 2 — diminishing returns, the one everybody already reaches for

This is the conventional mechanism, and R4 states it conventionally. As more technical people are added to the same R&D project, the marginal contribution of each additional person begins to decline. It happens principally because communication and training burdens grow. R4 identifies this as essentially the familiar software-engineering result about adding people to a project.

Communication is quantified. Assuming pairwise communication requirements between each R&D group, the total communication burden is roughly proportional to the square of the number of groups — or, exactly, proportional to n(n − 1)/2, where n is the total number of groups. That assumption of pairwise communication is stated, and it is what the formula rests on.

Training carries the part of the mechanism that ties specifically to acceleration. New personnel absorb the time of experienced team members who must train them. Add new personnel more rapidly and the effect is more severe, because the ratio of new to experienced people is greater. The rate of addition matters independently of the headcount — which is why a team that could have absorbed six people over a year suffers when it absorbs them over a quarter.

Caution

The cost R4 leaves out of its own accounting

R4 explicitly excludes the loss to other projects when talent is pulled away from them, and states that this opportunity cost would not show up in an accountant's rendering of the costs of acceleration.

That exclusion runs one way only. The measured penalty is systematically lower than the true one, and the gap is largest exactly when you take your best people off your other work. Anyone presenting an acceleration cost from the ledger should say which side of the estimate they are on — the same discipline the library applies to the cost of a late kill in the financial frame for R&D management.

Mechanism 3 — paying for approaches serial search would have spared you

The third mechanism is probabilistic and has nothing to do with staffing levels. R4 sets it up as a small model. A single task can be approached in a number of different ways, but in advance you can only assign success probabilities to the various approaches. For convenience, assume each approach has the same success probability, the same cost, and that all are independent of each other.

Serial search — minimises cost

  • R4's illustration uses ten alternative approaches to one task
  • Attempt each of them in sequence, quitting when one is found to be successful
  • You expect to find a successful approach before trying all ten
  • You pay only for the approaches you actually attempted
  • This is the minimum-cost strategy, and it is slow

Parallel search — minimises time

  • If a successful approach must be found more quickly, several approaches are tried concurrently
  • More approaches must therefore be paid for
  • Under extreme time compression all ten might be tried simultaneously — and all ten paid for
  • The premium is the expected number of approaches you would never have had to fund
  • This is the fastest strategy, and it is strictly worse on cost

The ten approaches are an illustrative figure, not a typical number. The transferable point is the direction of the trade: running everything in parallel is a time strategy that is worse on cost by construction, and the convexity comes from the fact that each further step towards full parallelism buys less time for more money.

Mechanism 4 — the critical path, and a network that gets denser

The fourth mechanism appears when a complex R&D project is viewed as a network of tasks. It is the cleanest single explanation of why the curve is convex, and it requires no assumption about people or uncertainty at all.

How compression proceeds through a task network

  1. Find the critical path

    The earliest normal completion time is estimated by finding the critical path through the network of tasks.

  2. Crash the cheapest task first

    To compress the critical path, a manager would first choose a relatively easy — and therefore inexpensive — task to accelerate.

  3. Then the next cheapest

    If further compression is required, the least expensive remaining task is chosen.

  4. Then the expensive ones

    If increasing compression is required, more expensive choices have to be exercised in order to shorten the critical path. The cheap options are gone.

  5. And the network thickens

    With increasing compression the network becomes denser, with more overlap between tasks, so compression may require simultaneous acceleration of several tasks rather than one.

Under these conditions, R4 concludes, total project cost increases with acceleration. Note what this mechanism does to extrapolation: the price of the first month of compression is drawn from the cheapest option on the network, so using it to forecast the price of the fourth month understates that price by construction.

Why the curve is convex, not linear

THE FOUR MECHANISMS SIDE BY SIDE

MechanismWhat acceleration actually changesWhat you pay forWhy the penalty accelerates
1. Information dependencySteps overlap, so each task begins with less informationMistakes and reworkFurther compression means tasks start under greater uncertainty, so the rework penalty grows
2. Diminishing returnsMore technical people are added, and added fasterCommunication and training burden — pairwise communication scales as n(n − 1)/2The ratio of new to experienced people rises with the rate of hiring
3. Parallel approachesUncertain technical tasks are attacked concurrently rather than in sequenceApproaches that serial search would never have neededEach further move towards full parallelism buys less time for more approaches
4. Network compressionCritical-path tasks are crashed, and the network grows denserProgressively more expensive crashing options, then several at onceYou spend the cheap options first; only expensive ones remain

Only mechanism 2 is the familiar diminishing-returns story. An estimate built on it alone accounts for one of four causes.

From the source

The curve, as R4 states it

Under the influence of these four factors, R&D costs may be expected not only to grow as the duration of the project is reduced, but to grow at an increasing rate under further compression. For these reasons the time-cost tradeoff curve is usually depicted as one which is convex to the time-cost axes.

R4's figure plots cost against project duration: a downward-sloping curve, steep at short durations and flattening at long ones. Cost falls as you allow more time, and the last increments of compression are the dearest.

The practical consequence is that the intuitive linear model — buy ten percent of the time for ten percent more money — is wrong in a specific direction. The same ten percent costs progressively more the closer you already are to the minimum feasible duration.

What this changes about an acceleration estimate

A crashing figure arrives as a single number, and the four mechanisms are the questions that number has to survive. The same interrogation applies to any R&D cost estimate — see risk and uncertainty in R&D financial analysis for why cost-outcome distributions in R&D carry a long tail on the bad side rather than sitting symmetrically around the estimate.

Before you accept a crashing figure

  • Ask which of the four mechanisms it prices. A figure built from staffing costs alone has covered one of four.
  • Ask whether rework from earlier task starts is in it, and at what rate of overlap it was assumed.
  • Ask how many parallel technical approaches will now be funded that a serial search would have avoided.
  • Ask whether the estimate extrapolates from the first increment of compression — if so, it is anchored on the cheapest option in the network.
  • Ask what the people being moved onto the project would otherwise have delivered. That number is excluded by R4's own accounting and will not be in the ledger.
  • Ask where on the curve you already sit. The same compression costs more the nearer you are to the minimum.
Source gap

How thin the evidence under this curve is

R4 is direct about it: for obvious reasons, very little research has been done to establish the exact shape of this important tradeoff curve. The article positions itself as presenting the current state of knowledge about the curve, not a settled result, and closes by saying there is much more to be learned.

The four mechanisms are a causal argument, not a measurement. The article contains no original data of its own — a point worth holding on to when the resulting figure is quoted back at you as though it were a constant.

How large the penalty actually is, which project and firm characteristics make the curve steeper, and how to price a specific acceleration decision are handled on the companion page, managing acceleration: complexity and trade-offs. This page is the causal account; that one is the estimate and the response. If the answer is that the project cannot carry the price of the schedule it has been given, the decision in front of you is a continuation decision — see making better project termination decisions.

What to carry forward

  1. Four mechanisms, not one. Information dependency, diminishing returns, parallel approaches and network compression each push cost up independently.
  2. Only diminishing returns is the familiar story. An acceleration estimate that prices staffing alone has priced a quarter of the problem.
  3. Each mechanism produces convexity by itself, which is why the curve bends rather than tilts. The last month of compression is never priced like the first.
  4. Serial search minimises cost, parallel search minimises time. Choosing speed here means paying for attempts you would not otherwise have made.
  5. The number in the ledger is a floor. What the reassigned people would have produced elsewhere is excluded by design.

Frequently asked questions

Is this just the old rule about adding people to a late project?

That rule is one of the four mechanisms R4 names, and R4 says so. The other three operate even if headcount never changes: tasks begin with less information and generate rework, uncertain technical tasks get attacked in parallel rather than in sequence, and crashing the critical path runs through the cheap options first. Treating the staffing effect as the whole story is the specific error the page is written against.

Why does the curve bend instead of sloping straight down?

Because each mechanism gets worse as compression increases, rather than charging a flat toll. Overlapping tasks start under greater uncertainty; new people arrive at a higher ratio to experienced ones; more approaches must be funded in parallel; and the remaining crashing options are the expensive ones. R4's own summary is that costs grow at an increasing rate under further compression.

Was the $1 million in the opening case a typical acceleration penalty?

No. It is a cost reported in the business press for one specific case, quoted by R4 to illustrate the cascade — rushed handoff, design defect, downstream tooling failure. R4 presents the cascade as common; it does not present the figure as typical, and neither should you.

Does parallel development not reduce risk?

It reduces schedule risk, which is why it is used. R4's point is about the cost side: under serial search you expect to find a workable approach before exhausting the alternatives, so you pay for fewer of them. Running them concurrently means paying for approaches you would never have needed. It is a time strategy that is worse on cost by construction.

Our first month of compression was cheap. Does that mean the rest will be?

The opposite, on R4's account. Compression proceeds by crashing the cheapest task on the critical path first, then the next cheapest. An early crashing success is drawn from the cheapest option available, so extrapolating from it understates every increment that follows.

How should I present the cost of acceleration to a sponsor?

State which mechanisms your figure covers and which it does not, and say explicitly that the opportunity cost of the people being moved is excluded — R4 excludes it and notes it will not appear in accounting figures. A number offered without that boundary will be read as complete when it is a floor.

References and source attribution

  1. R4 - why costs increase when projects accelerate. Practitioner review and synthesis article in a journal for research and technology management, March-April 1989; 3 printed pages; 7 references; one table and one figure. Reviews a known tradeoff, proposes a causal account of it, and synthesises published estimates into a common metric. Not itself an empirical study.
  2. The econometric and software-engineering studies whose estimates R4 recomputes, and the business-press report of the accelerated copier programme, are cited within R4 and were not supplied to this library. They are recorded as R4 describes them.
  3. Eleven copyrighted journal articles on R&D project management, supplied as a reading set for a literature review and profiled for this library. Front matter, abstracts, framework sections, tables and figures were read; article bodies were not reproduced, and all content here is paraphrase. The set is a reading list, not a systematic survey of the field.
  4. Supplied teaching source for this library (research methods and research process materials). Used here for page conventions and voice only; it does not treat schedule compression.

Suggested questions for Ask KEVOS

  • Take our crashing estimate and tell me which of the four mechanisms it has priced.
  • Explain the difference between serial and parallel search on a technical task, using our own project.
  • How do I quantify the rework we should expect if two phases overlap by six weeks?
  • Draft the wording that tells a sponsor our acceleration figure excludes opportunity cost.
  • Why does the communication burden scale with the square of the number of groups?
  • Our first increment of compression was cheap. Help me work out what the next one will cost.

Related KEVOS knowledge

Managing Acceleration: Complexity and Trade-offsAdvanced · rd project managementThe Financial Frame for R&D ManagementCore · rd project managementSources of Uncertainty in R&D ProjectsCore · rd project managementRisk and Uncertainty in R&D Financial AnalysisAdvanced · rd project managementR&D Project Evaluation ToolsCore · rd project managementMaking Better Project Termination DecisionsCore · rd project management
KEVOS® · Project Delivery · Research Projects Page KVS-PM-RES-0125 · v1.0.0 · content 2026.08 Last reviewed 2026-08-16

Continue learning

Real Options Valuation of R&D ProjectsGuide · Research ProjectsNEXT LESSON →Managing Acceleration: Complexity and Trade-offsGuide · Research ProjectsRisk and Uncertainty in R&D Financial AnalysisGuide · Research ProjectsSources of Uncertainty in R&D ProjectsGuide · Research Projects
KEVOS · Engineering, manufacturing and project improvement
ArticlesServicesCase studiesAboutContact
© 2026 KEVOS®