KEVOS
ArticlesServicesCase studiesAboutContact
ArticlesServicesCase studiesAboutContact
← ArticlesMaking Things Differently: Additive Manufacturing and Composite Primary StructureEngineering · MechanicalLesson 9/14← PrevNext →
GuidePublished 4 Aug 2026Updated 13 Aug 202610 min readBy Kevin JoginManufacturingCompositesMeasurement and TestingDesign Practice
On this page

Ask about this page

KEVOS AIMaking Things Differently: Additive Manufacturing and Composite Primary Structure

KEVOS knowledge first · trusted web sources when needed

Knowledge LibraryEngineeringMechanical EngineeringKL-ENG-HIST-1668

Making Things Differently: Additive Manufacturing and Composite Primary Structure

Complexity became free and volume became the cost driver. The demonstrations were early; the qualification took thirty years, because when the process is the material, material qualification is a manufacturing qualification.

Part 9 of 14 Period 1983-2015 Milestones 3 Reading 5 min Updated 2026-08-04

01Executive summary

Three milestones that removed the link between geometric complexity and cost, and then took twenty-eight and thirty-two years respectively to reach certified service.

Chuck Hull built parts by curing photopolymer layer by layer in 1983. A large airliner entered service in 2011 with a carbon fibre fuselage and wing, forty-eight years after usable carbon fibre was first produced. A printed metal component entered certified service in a commercial jet engine in 2015, consolidating around twenty separate parts into one. The recurring theme is that the manufacturing demonstration is early and the qualification is long.

Layer by layerGeometry becomes almost free; tooling constraints largely disappear
~20 → 1Part count consolidation in the certified printed component
48 yrsFrom usable carbon fibre to a composite primary airframe in service
AnisotropicBoth processes give direction-dependent properties

02Additive manufacture: what it actually changes

Conventional manufacture is subtractive or formative. Machining removes material, so internal features unreachable by a tool cannot be made. Casting and moulding require the part to leave the tool, so undercuts and enclosed voids are impossible or require cores. In both, cost rises with geometric complexity because complexity means more operations, more tooling or more setups.

Building layer by layer breaks that link. An internal cooling channel that follows a curved surface, a lattice that varies in density through a part, or twenty components fused into one costs essentially the same to print as a simple block of the same volume. Complexity becomes free; volume and build time become the cost drivers.

What it enables

Conformal internal features

Cooling channels that follow the surface they cool, rather than straight-drilled approximations. This alone justifies the process in tooling and in hot-section components.

What it enables

Part consolidation

Assemblies become single components. Every joint removed is a leak path, a fastener, an inspection and a failure mode removed with it.

What it constrains

Anisotropy and residual stress

Properties differ between build direction and in-plane, and rapid local solidification leaves residual stress that can distort a part or crack it during build. Orientation is a design decision.

What it constrains

Support, surface and post-processing

Overhangs need supports that must be removed, sometimes from places nothing can reach. As-built surfaces are rough. Stress relief, hot isostatic pressing and machining of critical faces are usually required.

Why qualification took thirty years

The process was demonstrated in 1983. Certified service in a critical aerospace application came in 2015. The gap is not machine capability; it is the evidence needed to argue that a part will behave as designed. Every powder lot, every machine, every build orientation and every parameter set potentially changes the material. Establishing allowable design properties requires enormous coupon testing, and establishing that production remains within the qualified envelope requires in-process monitoring and rigorous control. As with composites in the earlier series: the process is the material, so the material qualification is a manufacturing qualification.

03Composite primary structure: the long path to a certified airframe

Carbon fibre reached usable stiffness in 1963. It was used in secondary structure — fairings, control surfaces, interiors — for decades before a large airliner flew with a composite fuselage and wing in 2011. The intervening period was spent building the analytical methods, manufacturing processes and certification evidence needed to trust it with primary load paths.

What a composite primary structure changes, beyond the material
AspectAluminium airframeComposite airframe
FatigueGoverning design case; crack growth and inspection intervals dominateFar less fatigue-critical, permitting higher cabin pressure differential and larger windows
CorrosionRequires protection schemes, drainage and inspectionFibres do not corrode, but galvanic attack of adjacent aluminium fittings must be prevented
Damage detectionCracks are visible or found by established methodsImpact damage may leave no visible mark while removing compressive strength internally
ManufactureSheet forming, fastening, riveted jointsFibre placement and curing in autoclave; a fuselage barrel made as one piece
RepairWell-established riveted patch methods, performed widelyBonded repairs requiring controlled conditions, cure and specialised inspection
LightningAluminium conducts strike current readilyConductive mesh must be built in to provide a path and protect the structure

The lightning row is a good illustration of second-order consequences. Replacing a metal skin removes a property nobody specified because it was inherent — electrical conductivity — and it must then be deliberately reintroduced. This is exactly the pattern seen with grid inertia in the previous series. Whenever a material or technology is substituted, the audit question is what was being provided incidentally by the thing being replaced.

04Designing for a process that removes constraints

Engineers trained on subtractive manufacture carry constraints that are no longer binding, and the most common failure in adopting additive manufacture is printing an existing design. That captures none of the benefit and usually costs more than machining it.

  1. Re-examine the requirementStart from what the part must do, not from its current geometry. The existing shape encodes the old process’s limitations.
  2. ConsolidateLook for assemblies where joints exist only because the parts could not be made together. Each removed joint removes failure modes.
  3. Put material on the load pathTopology optimisation and lattice structures place material where stress requires it, which is rarely a shape a machinist could produce.
  4. Design for the buildOrientation, support requirement, thermal distortion and removable support access must be resolved during design, not after.
  5. Plan the qualificationDecide early what testing establishes properties, what monitoring shows the process stayed in envelope, and what inspection finds internal defects.
Where additive is genuinely the wrong answer

For simple geometry in volume, conventional processes remain far cheaper and faster, and this is not close. Additive earns its place where complexity is high, volume is low, lead time matters, part consolidation removes significant assembly, or the geometry is impossible otherwise. Selecting it as a default rather than against those criteria produces expensive parts that a mill would have made better.

05Takeaways for current practice

  • Do not print an existing design. Its geometry encodes constraints the new process does not have.
  • Count the joints you can delete. Part consolidation removes leak paths, fasteners, inspections and failure modes at once.
  • The process is the material. Qualification of powder, machine, orientation and parameters is the real programme cost.
  • Audit what the incumbent material provided incidentally. Conductivity, damping, thermal path and corrosion behaviour are frequently unspecified because they were inherent.
  • Expect decades between demonstration and certified service. The interval is filled with evidence generation, and planning for it is the difference between a programme and a prototype.
Previous in seriesReverse osmosis and rainfall independenceNext in seriesIsolation, tunnels, spans and towersSeries indexMilestones of the Modern Era, 1970-2020

KL-ENG-HIST-1668 · KEVOS® Knowledge Library · Engineering / Mechanical Engineering

  • Manufacturing
  • Composites
  • Measurement and Testing
  • Design Practice
  • Aerospace
  • History of Engineering
  • Mechanical Engineering

Original KEVOS® synthesis. Historical dates, attributions and device descriptions are drawn from general engineering history; the analysis, structure, standards commentary and Australian practice notes are our own. Figures are indicative and are given for teaching purposes — verify against the governing standard or manufacturer data before using them in design.

© KEVOS® — Precision to Vision. Prepared by Kevin Jogin.

Handbook application: from concept to controlled practice

Purpose. This expanded section turns the original page into a practical handbook. It preserves the supplied material and adds a repeatable way to apply, check and review Making Things Differently: Additive Manufacturing and Composite Primary Structure. It does not replace a contract, legislation, a controlled standard, competent engineering judgement or specialist advice.

The operating aim is to carry the subject from function and assumptions through design evidence, verification and controlled release. Read the original explanation first, then use the workflow and checks below to convert knowledge into evidence.

Apply Making Things Differently: Additive Manufacturing and Composite Primary Structure by beginning with the duty, not the component or software command. Convert the key ideas—additive, manufacturing, composite, primary, structure—into measurable requirements and interfaces. Record operating and non-operating environments, duty cycle, expected life, loads, energy sources, human interaction and reasonably foreseeable abnormal conditions. When a value is not a project requirement or verified supplier datum, identify it as an assumption or illustrative value.

Create a calculation and evidence trail that another competent person can audit. Every input should carry a source, unit, revision and uncertainty or tolerance where relevant. Every model should state its boundary conditions and limitations. Keep nominal capacity separate from design capacity, and keep verification margin separate from an arbitrary safety factor. If a code or standard governs the work, confirm the applicable edition and contractual status rather than copying a number from a secondary summary.

Design for manufacture, assembly, inspection, operation and maintenance at the same time. A technically valid geometry can still fail because it cannot be fixtured, measured, cleaned, guarded, reached or replaced. Review process capability, datum or reference strategy, tolerance accumulation, access, error-proofing and changeover. Where people interact with plant, apply the hierarchy of controls and consult those who will operate, clean, maintain and recover the equipment.

Plan verification before release. Define the characteristic, method, equipment, sample or test condition, acceptance criterion, record and responsible person. Validation then asks a different question: whether the resulting system is effective and suitable in the intended use context. A passed drawing check or analysis does not by itself validate usability, maintainability or production performance.

Step-by-step operating method

  1. Define the duty. Capture the required function, interfaces, operating environment, life, loads and unacceptable outcomes.
  2. Establish the model. Identify governing principles, units, material or process data, assumptions and uncertainty.
  3. Develop alternatives. Compare feasible concepts against performance, manufacturability, safety, maintainability and cost.
  4. Verify the design. Use analysis, test, inspection or demonstration with acceptance criteria defined before execution.
  5. Release and learn. Baseline the design, control changes, retain evidence and feed operating results into the next revision.

Illustrative design review record

Illustrative values only. Build a one-page record with the required function, input sources, assumptions, governing load or process condition, failure consequences, selected concept, verification method and acceptance criterion. Mark every numerical input as project requirement, verified supplier data, measured value, calculation output or assumption. Review the weakest evidence first. If an assumption can change safety, compliance, interchangeability or capacity, it must be resolved before release rather than buried in a calculation note.

Evidence classQuestionRelease expectation
RequirementWhat must the design do and under which conditions?Approved and traceable
InputWhere did the load, property, tolerance or process limit come from?Source, unit and revision recorded
AnalysisWhich model and assumptions connect input to result?Checkable calculation or simulation
VerificationHow will conformity be demonstrated?Method and acceptance criterion agreed
ValidationWill the solution work for intended users and conditions?Representative use evidence

Common failure modes and recovery actions

1. Watch for

Starting detailed design before interfaces and operating limits are agreed.

Recovery: Return to the governing definition or requirement and restate the decision in one sentence.

2. Watch for

Using catalogue or typical values as though they were certified project inputs.

Recovery: Separate evidence from assumption, assign an owner and set a date for validation.

3. Watch for

Checking nominal performance while ignoring tolerances, degradation and foreseeable misuse.

Recovery: Run a small counterexample, boundary test, pilot or independent check before proceeding.

4. Watch for

Confusing verification of requirements with validation of user need.

Recovery: Record the consequence, decision and rationale, then update the controlled baseline.

5. Watch for

Releasing drawings or procedures without configuration, inspection and change controls.

Recovery: Escalate when the issue affects safety, compliance, acceptance, material value or an agreed tolerance.

Review checklist

  • What function and failure consequence govern this decision?
  • Which inputs are measured, specified, assumed or illustrative?
  • How will conformity be demonstrated and recorded?
  • What change would invalidate the current evidence?
  • Are mandatory requirements distinguished from recommendations and illustrative values?
  • Are sources, assumptions, units, dates and versions recorded closely enough to reproduce the decision?
  • Have safety, legal, ethical, stakeholder and operational consequences been considered at the appropriate level?
  • Is there a named owner and a trigger for review, escalation, change or retirement?

Questions for deeper application

What is the most important distinction a practitioner must preserve when applying Making Things Differently: Additive Manufacturing and Composite Primary Structure?

Answer with a fact or cited source where available. Where evidence is incomplete, record the assumption, consequence, responsible owner and next validation action.

Which assumption about additive would change the result most if it proved false?

Answer with a fact or cited source where available. Where evidence is incomplete, record the assumption, consequence, responsible owner and next validation action.

What evidence would allow an independent reviewer to reproduce or challenge the conclusion?

Answer with a fact or cited source where available. Where evidence is incomplete, record the assumption, consequence, responsible owner and next validation action.

Which boundary, exception or failure case has not yet been tested?

Answer with a fact or cited source where available. Where evidence is incomplete, record the assumption, consequence, responsible owner and next validation action.

What must be handed over, monitored or reviewed after the immediate work is complete?

Answer with a fact or cited source where available. Where evidence is incomplete, record the assumption, consequence, responsible owner and next validation action.

Authoritative references and use notes

The sources below were selected as institutional or primary guidance for the broader practice. They support the handbook method; they do not imply that every statement or clause in a source applies to every project. Confirm the current edition, jurisdiction, contract and application before treating any requirement as mandatory.

  • SOLIDWORKS Design Help — Dassault Systèmes SOLIDWORKS. Used for feature-based CAD, sketches, structures and manufacturing outputs. Accessed 2026-08-13.
  • NASA Systems Engineering Handbook — NASA. Used for requirements, design, verification, validation and technical management. Accessed 2026-08-13.

Continue learning

Manufacturing Drinking Water: Seawater Reverse Osmosis and Supply SecurityGuide · Civil & StructuralNEXT LESSON →Modern Civil Works: Base Isolation, the Channel Tunnel, Cable-Stayed Spans and Supertall TowersGuide · Civil & StructuralGeneration Without Fuel: Photovoltaics and the Modern Wind TurbineGuide · MechanicalClosing the Loop: Fly-by-Wire, Functional Safety and Propulsive LandingGuide · Mechanical
KEVOS · Engineering, manufacturing and project improvement
ArticlesServicesCase studiesAboutContact
© 2026 KEVOS®