KEVOS
ArticlesServicesCase studiesAboutContact
ArticlesServicesCase studiesAboutContact
← ArticlesPMI Visual Wall — Master Edition, Part 2Engineering · Engineering MathematicsLesson 139/887← PrevNext →
GuidePublished 12 Aug 2026Updated 13 Aug 202621 min readBy Kevin Jogin
On this page

Ask about this page

KEVOS AIPMI Visual Wall — Master Edition, Part 2

KEVOS knowledge first · trusted web sources when needed

PMI VISUAL WALL · PART 2 OF 2

The complete knowledge system · 22 posters · 10 sections Tip: in the print dialog set paper = A3, layout = Landscape, margins = None, "Background graphics" ON. This prints all 22 posters as one document.

PMI Visual Wall — Master Edition

The complete project-management knowledge ecosystem is organised as a two-part master edition. This file is Part 2 of 2. Each poster shares the same anatomy — Purpose → Visual Map → Key Concepts → Relationships → Exam Concepts → Executive View → Industry Example → Memory Hooks → 60-second Daily Review — and a colour spine coded by domain so the printed wall is navigable at a glance. All content is original instructional design in standard PMI terminology.

Colour code: ■ Master/Strategy   ■ PMBOK 7 / Project   ■ Business Analysis / Value   ■ Risk   ■ EVM / Formulas   ■ Program   ■ Portfolio   ■ OPM

SECTIONS 1–3

  • 01 PMI Ecosystem Master Map
  • 02 The 12 Principles
  • 03 The 8 Performance Domains
  • 04 Value Delivery System
  • 05 Tailoring
  • 06 Models, Methods & Artifacts
  • 07 Business Analysis & Its 6 Domains
  • 08 Needs Assessment
  • 09 Elicitation, Analysis & Requirements
  • 10 Traceability & Solution Evaluation

SECTIONS 4–6

  • 11 Risk — Fundamentals & Principles
  • 12 Risk — Process & Responses
  • 13 Risk — 3 Levels & Quant Tools
  • 14 EVM — Measures, Variances & Indices
  • 15 EVM — Forecasting (EAC/ETC/VAC/TCPI)
  • 16 Program — Fundamentals & Benefits
  • 17 Program — Domains, Life Cycle & Governance

SECTIONS 7–10

  • 18 Portfolio — Fundamentals & Alignment
  • 19 Portfolio — Domains, Selection & Balancing
  • 20 OPM & Organisational Maturity
  • 21 The Formulas Wall
  • 22 Master Revision Wall

Print all, hang in spine-colour order, and drill Poster 22 daily.

Two-part master edition: Part 1 — Posters 01–11 · Part 2 — Posters 12–22
POSTER 12
Section 4 · Risk Management — The Process

The Risk Management Process

An iterative cycle: set the strategy, find risks, size them (qualitatively then, where needed, quantitatively), plan & implement responses, and monitor — repeating throughout the life cycle. The risk register and risk report are the living artifacts that carry it.

Visual Map — Plan → Identify → Analyse → Respond → Monitor

1 · Plan
strategy, RBS, P&I scales
▸ 2 · Identify
ongoing → risk register
▸ 3 · Qualitative
P×I → prioritise
▸ 4 · Quantitative
model overall risk
▸ 5 · Plan Responses ▸ 6 · Implement ▸ 7 · Monitor ↺

Identify and Monitor never stop. Quantitative analysis is optional — used on larger/complex efforts to size overall risk and justify reserves; qualitative is the fast triage every time.

Threat Responses

Avoid
eliminate the threat or its cause (change the plan).
Transfer
shift impact & ownership to a third party (insurance, warranty, fixed-price).
Mitigate
reduce probability and/or impact.
Accept
take no action (passive) or set a contingency (active).
Escalate
raise to the level with authority to act.

Opportunity Responses

Exploit
make certain the opportunity is realised (mirror of Avoid).
Share
partner with someone better able to capture it (mirror of Transfer).
Enhance
increase probability and/or impact (mirror of Mitigate).
Accept
take it if it arrives, but don't actively chase it.
Escalate
raise to the level that can pursue it.

Tools by Step

  • Identify: brainstorming, checklists, RBS, assumption analysis, SWOT, interviews.
  • Qualitative: probability & impact (P-I) matrix, risk categorisation, urgency.
  • Quantitative: EMV, decision tree, Monte Carlo, sensitivity / tornado.
  • Reserves: contingency vs management reserve analysis.

Reserves — Funding Uncertainty

  • Contingency reserve — for known risks; inside the cost baseline; the PM controls it.
  • Management reserve — for unknown risks; outside the baseline; management approves its release.

Exam Concepts

  • Qualitative = subjective P×I, fast; quantitative = numeric model of overall risk.
  • Contingency (known, PM) vs management (unknown, mgmt) reserve.
  • Risk owner manages the risk; a response owner executes an action.
  • A trigger is the early-warning sign a risk is occurring.

Executive View

  • Quantitative analysis defends the contingency ask to the board.
  • Response strategy = a cost-vs-exposure trade, not box-ticking.
  • Watch overall risk, not just the loudest single risk.

Industry Example

Manufacturing
  • Line install: supplier-delay risk → qualitative HIGH → Monte Carlo shows P80 finish +5 wks → response = transfer (LD clause) + mitigate (dual-source).
60-sec Review Recite the 7-step cycle 5 threat responses 5 opportunity responses Qual vs quant Contingency vs management reserve
PMI Visual Wall · Poster 12 · Risk — The Process & Responses · original instructional design · A3 landscape
POSTER 13
Section 4 · Risk Management — Scaling & Quantifying

Risk Across the Three Levels & Quantitative Tools

This standard's signature idea: risk is managed at project, program and portfolio levels — each with a different focus and horizon — and risks cascade and escalate between them. Below: what risk means at each level, plus the quantitative tools that turn uncertainty into numbers.

Visual Map — One Risk Discipline, Three Altitudes

LevelRisk is about…Primary focusHorizonOwner
PortfolioStrategic objectives & the balance/mix of components; aggregate exposure vs risk capacityDoing the right mixLong / strategicPortfolio governance
ProgramRisks between components & their interdependencies; threats to benefits & integrationCoordinated benefitsMediumProgram manager
ProjectRisks to scope, schedule, cost, quality of a specific deliverableReliable deliveryShort / tacticalProject manager

Escalation & cascade: a project risk beyond the PM's authority escalates up to program or portfolio; strategic decisions and constraints cascade down. Consolidated reporting rolls individual risks into an overall picture at each level.

Expected Monetary Value (EMV)

EMV = Σ (probability × impact); impacts are signed (− threat, + opportunity).

  • Threat: 20% × (−$500k) = −$100k
  • Opportunity: 30% × (+$200k) = +$60k
  • Net EMV = −$40k → size the contingency accordingly.

Feed EMVs into a decision tree to choose the option with the best expected value (e.g. build vs buy).

Modelling Overall Risk

  • Monte Carlo: simulate thousands of runs → a range & confidence (e.g. P80 cost/finish).
  • Sensitivity / tornado: rank which risks swing the outcome most.
  • Decision tree: compare options by EMV under uncertainty.
  • Outputs justify reserves and feed the cost baseline (EVM).

Probability & Impact Matrix (Qualitative)

Prob ↓ / Impact →LowMediumHigh
HighMediumHighHigh
MediumLowMediumHigh
LowLowLowMedium

Score = probability × impact → a priority that drives response order & depth.

Exam Concepts

  • Portfolio = strategic / aggregate; program = interdependencies & benefits; project = delivery.
  • Risk capacity (portfolio) sets the ceiling that appetite sits within.
  • Escalate up, cascade down; aggregate vs individual risk.
  • EMV, Monte Carlo & decision trees are quantitative.

Executive View

  • Portfolio risk is a strategy & capacity conversation, not a register.
  • Consolidated, roll-up reporting gives the board one risk picture.

Industry Example — A Defence Prime

Defence
  • Portfolio: balance the mix of bids & live programs against capacity.
  • Program: integrate ship + combat system + training so the capability benefit lands.
  • Project: deliver the radar subsystem on cost & to spec.

Memory Hooks

  • Portfolio = right mix · Program = right benefits · Project = right delivery.
  • "Risk rolls up; response rolls down."
  • Reserves: contingency = knowns I control; management = unknowns the boss controls.
60-sec Review Risk focus at each level Escalate up vs cascade down Compute a 2-line EMV What Monte Carlo gives you Capacity vs appetite
PMI Visual Wall · Poster 13 · Risk — Three Levels & Quantitative Tools · original instructional design · A3 landscape
POSTER 14
Section 5 · Earned Value Management — The Engine

EVM Foundations: Measures, Variances & Indices

EVM fuses scope, schedule and cost into one objective read of performance. Three measures — PV, EV, AC — produce two variances ($) and two indices (ratios). The golden rule: EV starts every formula; subtract for a variance, divide for an index, and positive / > 1 is good.

Visual Map — The EVM S-Curve

Cumulative $ Time → data date (now) PV — planned value (BAC = total PV) EV — earned value AC — actual cost PV = 50k AC = 45k EV = 40k SV = EV − PV = −10k CV = EV − AC = −5k → behind schedule & over cost

EV below PV ⇒ behind schedule; EV below AC ⇒ over budget. The vertical gaps to EV are the variances.

The Three Measures

PV — Planned Value
budgeted cost of work scheduled (the baseline plan). Total PV = BAC, Budget at Completion.
EV — Earned Value
budgeted cost of work performed. EV = % complete × BAC.
AC — Actual Cost
actual cost of the work performed — what you really spent.

Variances ($) & Indices (ratios)

SV = EV − PV
+ ahead · − behind

CV = EV − AC
+ under · − over

SPI = EV ÷ PV
>1 ahead · <1 behind

CPI = EV ÷ AC
>1 under · <1 over

Worked Example

ItemValue
BAC$100k
PV (planned 50%)$50k
EV (40% complete)$40k
AC (spent)$45k
SV = 40−50−$10k behind
CV = 40−45−$5k over
SPI = 40/500.80
CPI = 40/450.89

Exam Concepts

  • Variances in $, indices are ratios. EV is always first.
  • Positive variance & index > 1 = favourable.
  • EV = % complete × BAC.
  • SV weakness: measured in $, it drifts to 0 at the end even if late — pair it with the schedule network or SPI.
  • Cost pair uses AC; schedule pair uses PV.

Executive View

  • One integrated number for scope + schedule + cost.
  • Objective early-warning system — trends, not anecdotes.
  • CPI is famously stable after ~20% complete — trust the trend.
  • Reports up cleanly through program & portfolio.

Relationships

  • Needs a sound scope, schedule & cost baseline first (Poster 6 baselines).
  • Risk reserves sit inside/outside the baseline (Poster 12).
  • Forecasting (EAC/ETC/VAC/TCPI) builds on these — Poster 15.

Industry Example

Capital Project
  • A $100k line-upgrade is 40% built but has consumed $45k by the planned-50% point: SPI 0.80 & CPI 0.89 flag it behind and over early enough to act.

Memory Hooks

  • "EV is the hero — it opens every formula."
  • Variance = minus, Index = divide; + and >1 are good.
  • Cost↔AC, Schedule↔PV (C-A, S-P).
60-sec Review Define PV / EV / AC Write SV, CV, SPI, CPI EV = ? × BAC Why SV in $ is weak Sketch the S-curve
PMI Visual Wall · Poster 14 · EVM — Measures, Variances & Indices · original instructional design · A3 landscape
POSTER 15
Section 5 · Earned Value Management — Forecasting

EVM Forecasting: EAC · ETC · VAC · TCPI

Performance to date predicts the finish. EAC forecasts the total cost, ETC the cost of what's left, VAC the projected over/under, and TCPI the efficiency you must now sustain to hit a target. Pick the EAC formula that matches your assumption about the remaining work.

Visual Map — Choosing Your EAC (assumption → formula)

Assumption about the remaining workEAC formulaReading
Current variance was a one-off / atypicalEAC = AC + (BAC − EV)finish the rest at the budgeted rate
Current cost efficiency continues (the default)EAC = BAC ÷ CPItoday's CPI holds to the end
Both cost & schedule pressure continueEAC = AC + (BAC − EV) ÷ (CPI × SPI)schedule drag worsens cost
Original estimate is no longer validEAC = AC + bottom-up ETCre-estimate the remainder

The Forecasting Family

BAC
Budget at Completion — the baseline total (the plan).
EAC
Estimate at Completion — forecast total cost.
ETC
Estimate to Complete — cost of the remaining work.
VAC
Variance at Completion — projected over/under at the end.
TCPI
To-Complete Performance Index — efficiency needed from here.

Core Formulas

ETC = EAC − AC
what's left to spend

VAC = BAC − EAC
+ under · − over at end

TCPI = (BAC − EV) ÷ (BAC − AC)
to still hit BAC

TCPI = (BAC − EV) ÷ (EAC − AC)
to hit the new EAC

Worked Example (same numbers)

From Poster 14Value
BAC / EV / AC100 / 40 / 45
CPI / SPI0.89 / 0.80
EAC = BAC/CPI$112.5k
ETC = EAC−AC$67.5k
VAC = BAC−EAC−$12.5k
EAC (cost×sched)≈ $129k
TCPI→BAC1.09

Reading TCPI

  • TCPI = work remaining ÷ funds remaining.
  • Compare to your CPI: TCPI 0.89 vs CPI 0.89 = on track.
  • Here TCPI 1.09 > CPI 0.89 → you must run better than you ever have → the BAC is likely unrecoverable.
  • Response: re-baseline, de-scope, or accept the overrun.

Exam Concepts

  • ETC = EAC − AC; VAC = BAC − EAC.
  • EAC = BAC/CPI is the default "current-trend" forecast.
  • Know all four EAC formulas & their assumptions.
  • TCPI > 1 (and > CPI) = must tighten up; recovery is hard.

Executive View

  • EAC & VAC answer the board's question: "Where will we land?"
  • TCPI tells you if a recovery target is realistic before you promise it.
  • Forecasts trigger re-baselining & funding decisions.

Industry Example

Capital Project
  • The $100k line upgrade now forecasts $112.5k (EAC) with a −$12.5k VAC. TCPI 1.09 says recovery to budget is unlikely → present a re-baseline + a de-scope option.

Memory Hooks

  • BAC=plan · EAC=forecast · ETC=what's left · VAC=the surprise.
  • "ETC peels AC off EAC."
  • If TCPI > CPI, you're in trouble.
60-sec Review 4 EAC formulas + assumptions ETC and VAC formulas Both TCPI formulas TCPI vs CPI meaning Recompute EAC from CPI
PMI Visual Wall · Poster 15 · EVM — Forecasting (EAC/ETC/VAC/TCPI) · original instructional design · A3 landscape
POSTER 16
Section 6 · Program Management — Foundations

Programs & Benefits Management

A program is a group of related projects, subsidiary programs & activities managed together to obtain benefits not available by managing them individually. Program management is about coordinated delivery for benefits — the components are related, and together they create synergy.

Project · Program · Portfolio

LensManages…DeliversQuestion
Projecta defined scopean output / deliverablebuild it right
Programrelated components & their interdependenciesbenefits & capabilitiesrealise the benefit
Portfolioall work, related or notstrategic alignmentthe right mix

Why a program (not just projects)? synergy · manage interdependencies · optimise shared resources · deliver outcomes too big for one project.

The Value Chain (program-owned)

Output
component delivers
▸ Capability
ability to act
▸ Outcome
change in state
▸ Benefit
measurable gain

Components produce outputs → integrated into capabilities → used to create outcomes → realised as benefits. Projects stop at outputs; programs push through to benefits.

Visual Map — The Benefits Management Life Cycle

1 · Identify
quantify & justify (business case)
▸ 2 · Analyse & Plan
benefits register, plan, metrics, map
▸ 3 · Deliver
components → capabilities
▸ 4 · Transition
integrate into operations / BAU
▸ 5 · Sustain
benefits endure after closure

The benefits realisation plan & benefits register are the living artifacts. Each benefit has an owner and leading/lagging measures. Sustainment is the giveaway that programs care about value beyond the program's own life.

Exam Concepts

  • Programs exist for benefits & relatedness, not size alone.
  • Capability is delivered by a component; the benefit is realised in operations.
  • Benefits transition hands capability to BAU; sustainment continues after closure.
  • Benefits have owners & metrics — measured, not assumed.

Executive View

  • Programs convert strategy → capability → benefit.
  • The sponsor cares about outcomes, not outputs.
  • Governance gates are benefit-driven — fund what realises value.

Industry Example

Defence
  • A frigate capability program: shipbuild + combat-system + training/sustainment components. Benefit = a deployable, supportable naval capability — sustained over decades, not just a hull delivered.

Relationships

  • Realises the PMBOK 7 value delivery system (Poster 4) at program scale.
  • BA's solution evaluation (Poster 10) feeds benefit measurement.
  • Sits beneath the portfolio (Posters 18–19) and above projects.

Memory Hooks

  • "Projects make outputs; programs make BENEFITS."
  • Benefits cycle — I·A·D·T·S: Identify → Analyse/plan → Deliver → Transition → Sustain.
  • "A program is related; a portfolio is aligned."
60-sec Review Define a program Output→capability→benefit 5 benefits-cycle stages Transition vs sustainment Program vs portfolio
PMI Visual Wall · Poster 16 · Program — Fundamentals & Benefits · original instructional design · A3 landscape
POSTER 17
Section 6 · Program Management — How It Runs

Performance Domains, Life Cycle & Governance

Programs are run through five performance domains that operate concurrently, across a three-phase life cycle (Definition → Delivery → Closure) held together by governance gates. Governance is the value-protection mechanism: it authorises components, reviews benefits, and decides go / no-go.

Visual Map — Five Domains over the Life Cycle

1 Strategy Alignment 2 Benefits Management (Poster 16) 3 Stakeholder Engagement 4 Governance 5 Life Cycle Management
Definition
formulation + planning
⟢ gate ⟣ Delivery
authorise & oversee components · realise benefits
⟢ gate ⟣ Closure
transition + close

The five domains run concurrently throughout; the phases are the timeline; governance gates sit between phases and at component boundaries.

1 · Strategy Alignment

  • Link the program to organisational strategy.
  • Program roadmap & business case.
  • Environmental / readiness assessment.

3 · Stakeholder Engagement

  • Far more numerous, diverse & long-term than a project's.
  • Identify → analyse → plan → engage, continuously.
  • Engagement is strategic, not just communication.

4 · Governance

  • Program board / steering committee + sponsor.
  • Phase-gate reviews & component authorisation.
  • Go / no-go; balances component vs program tension.

The Program Roadmap (≠ schedule)

  • A high-level chronological view linking components, milestones & benefits to strategy.
  • Shows the why-when; the schedule shows the what-when.
  • Anchors gate decisions & sequencing of tranches.

Exam Concepts

  • The 5 domains run concurrently across the life cycle.
  • Governance authorises components & gates phases.
  • Roadmap ≠ schedule — higher-level, benefit/milestone-oriented.
  • The program board makes go / no-go calls.

Executive View

  • Governance is the value-protection mechanism.
  • The board & sponsor own the benefits case.
  • Kill failing components early at the gate.

Industry Example

Defence
  • The frigate program's board gates each tranche; the roadmap sequences build → integration → trials → handover; stakeholders span Navy, government, primes, unions & community.

Memory Hooks

  • 5 domains — S·B·S·G·L: "Some Big Ships Get Launched" (Strategy, Benefits, Stakeholders, Governance, Life cycle).
  • Phases: Define → Deliver → Close.
  • Roadmap = why-when; schedule = what-when.
60-sec Review Name the 5 domains 3 life-cycle phases What governance authorises Roadmap vs schedule Who makes go/no-go
PMI Visual Wall · Poster 17 · Program — Domains, Life Cycle & Governance · original instructional design · A3 landscape
POSTER 18
Section 7 · Portfolio Management — Foundations

Portfolios & Strategic Alignment

A portfolio is the collection of projects, programs, subsidiary portfolios and operations managed as a group to achieve strategic objectives. Portfolio management is "doing the right work" — selecting, prioritising, balancing & authorising the mix that best delivers strategy. Components need not be related.

What's in a Portfolio?

  • Programs — related components run for benefits.
  • Projects — standalone deliverables.
  • Subsidiary portfolios — e.g. by division.
  • Operations / BAU — ongoing work that consumes the same capacity.

The portfolio is the organisation's whole investment basket — and it is ongoing, not temporary.

Portfolio vs Program — The Key Distinction

LensProgramPortfolio
Grouped byRelatedness & synergyStrategic alignment
ComponentsMust be relatedMay be unrelated
GoalCoordinated benefitsOptimal value & balance
DurationTemporary (has an end)Ongoing
QuestionRealise the benefitThe right mix

Visual Map — Strategy Becomes a Funded Plan

Org Strategy
vision, goals, objectives
▸ Portfolio
select · prioritise · balance · authorise
▸ Programs & Projects + Operations
the authorised work
▸ Strategic Objectives
value realised
↺

The portfolio is the bridge between strategy and delivery: it converts intent into a funded, balanced plan, then feeds performance back to continuously realign as strategy shifts. Artifacts: portfolio strategic plan, charter & roadmap.

Value of Portfolio Management

  • Maximise value of the whole portfolio.
  • Align every investment to strategy.
  • Balance risk/reward & short/long term.
  • Optimise scarce resources & funding.
  • Transparency for investment decisions.

Exam Concepts

  • Portfolio = strategic alignment; components may be unrelated.
  • A portfolio includes operations, not just projects/programs.
  • "Right work" (portfolio) vs "work right" (project/program).
  • Portfolio management is ongoing, not temporary.

Executive View

  • The portfolio is the board's investment steering wheel.
  • This is where strategy becomes a funded plan.
  • Decisions are fund / defer / kill against strategy.

Relationships

  • Sits above programs (Posters 16–17) & projects in the hierarchy (Poster 1).
  • Manages aggregate risk & capacity (Poster 13).
  • Governed within OPM (Poster 20).

Industry Example

Defence
  • A prime's portfolio: naval programs + land-vehicle programs + R&D projects + sustainment operations + live bids — unrelated, but all balanced for strategy, capacity & risk.

Memory Hooks

  • "Portfolio = right WORK · project = work RIGHT."
  • "A program is related; a portfolio is aligned."
  • The portfolio is the whole investment basket — and it never ends.
60-sec Review Define a portfolio What it contains (incl. ops) Portfolio vs program Right work vs work right Why it's ongoing
PMI Visual Wall · Poster 18 · Portfolio — Fundamentals & Strategic Alignment · original instructional design · A3 landscape
POSTER 19
Section 7 · Portfolio Management — How It Runs

Performance Domains, Selection & Balancing

Portfolios are run through six performance domains and a recurring cycle that selects and balances components: categorise → evaluate → select → prioritise → balance → authorise → review. The defining skill is balancing the mix against value, risk and capacity — then rebalancing as strategy moves.

Visual Map — The Component Selection & Balancing Pipeline

Identify▸ Categorise
group by type/strategy
▸ Evaluate
score vs criteria
▸ Select▸ Prioritise▸ Balance
optimise mix vs capacity & risk
▸ Authorise▸ Review↺

Categorisation enables apples-to-apples comparison; evaluation uses weighted scoring against strategic criteria; balancing optimises the whole mix — not each component in isolation. The loop never closes.

Balancing Tool — Risk vs Reward Bubble Chart

Value / reward → Risk → high value · low risk — FUND high value · high risk — BALANCE low value · high risk — DEFER / KILL efficient frontier A B D C E bubble size = investment / cost

The Six Performance Domains

  • 1 Strategic Management — align to strategy; portfolio roadmap & value proposition.
  • 2 Governance — decision framework; authorise / terminate components; oversight & optimisation.
  • 3 Capacity & Capability — balance resource & funding demand vs supply.
  • 4 Stakeholder Engagement — engage decision-makers & sponsors.
  • 5 Value Management — define, maximise, deliver & measure value.
  • 6 Risk Management — manage aggregate risk & the risk/return balance.

Balancing & Optimisation Tools

  • Weighted scoring models against strategic criteria.
  • Prioritisation matrices & ranking.
  • Bubble / quadrant charts (risk vs reward, above).
  • Efficient frontier — best value for a given risk.
  • Portfolio roadmap & dashboards for transparency.

Exam Concepts

  • Portfolio management continuously balances & reprioritises.
  • Governance authorises & terminates components.
  • Capacity management = demand vs supply of resources/funding.
  • Value & risk are managed at the aggregate level.

Executive View

  • Rebalance as strategy shifts — the mix is never "done".
  • Governance kills the zombies that drain capacity.
  • One dashboard for the entire investment.

Industry Example

Defence
  • The prime scores bids & programs against strategic criteria, balances naval vs land vs air, checks engineering capacity, and the board authorises the optimal mix — re-reviewed each quarter.

Memory Hooks

  • Pipeline — C·E·S·P·B·A: Categorise, Evaluate, Select, Prioritise, Balance, Authorise.
  • "Pick · balance · fund · review — forever."
  • Bubble chart = risk vs reward; size = cost.
60-sec Review Name the 6 domains Recite the C-E-S-P-B-A pipeline Sketch a risk/reward chart Capacity = demand vs ? What governance authorises
PMI Visual Wall · Poster 19 · Portfolio — Domains, Selection & Balancing · original instructional design · A3 landscape
POSTER 20
Section 8 · Organisational Project Management

OPM & Organisational Maturity

OPM is the framework that integrates portfolio, program & project management with organisational enablers so that strategy is delivered consistently & predictably. It is the organisation's strategy-execution operating system — owned at the executive level, not on any single project.

Visual Map — What OPM Integrates

Portfolio
the right work
+ Program
the right benefits
+ Project
the right delivery
+ Organisational Enablers
structure · culture · governance · methodology · people · knowledge
= OPM
strategy delivered, repeatably

OPM is the layer that makes good delivery systematic rather than heroic. Organisational enablers — a PMO, consistent & tailored methodology, governance, capability development, knowledge management — are what turn one good project into a repeatable capability.

Organisational Enablers

  • Structural: PMO, governance bodies, reporting lines.
  • Cultural: values, executive sponsorship, risk-awareness.
  • Methodology: consistent, tailored practices & templates.
  • People / HR: competency, training, career paths.
  • Knowledge: lessons learned, KM, continuous learning.

Maturity — The OPM3 Idea

Maturity = the ability to deliver consistently & predictably. The improvement cycle repeats:

Acquire Knowledge▸ Perform Assessment▸ Manage Improvement↺

Progression of practice: Standardise → Measure → Control → Continuously Improve (SMCI), built from best practices → capabilities → outcomes → KPIs.

Exam Concepts

  • OPM integrates portfolio + program + project + enablers.
  • OPM is a strategy-execution framework, not a methodology by itself.
  • OPM3 = maturity model; cycle = Acquire → Assess → Improve.
  • Maturity path = SMCI (Standardise, Measure, Control, Improve).

Executive View

  • OPM is the C-suite's strategy-delivery engine.
  • Maturity = predictability — fewer surprises, better forecasts.
  • Invest in enablers (PMO, methodology, capability), not just projects.

Industry Example

Manufacturing
  • A multi-plant manufacturer standardises stage gates, stands up a PMO, and uplifts PM capability. Maturity climbs from ad-hoc to measured & controlled — and strategic initiatives start landing on time, plant after plant.

Relationships

  • Wraps the entire hierarchy of Poster 1 — portfolio, program & project together.
  • Provides the governance & methodology that tailoring (Poster 5) operates within.
  • Feeds on lessons learned & benefits data from every delivery.

Memory Hooks

  • "OPM = strategy delivered, consistently."
  • PPP + enablers = OPM (Portfolio, Program, Project + the org).
  • Maturity ladder — S·M·C·I; improvement loop — Acquire → Assess → Improve.
60-sec Review What OPM integrates Name 3 organisational enablers The OPM3 cycle SMCI maturity ladder Maturity = ?
PMI Visual Wall · Poster 20 · Organisational Project Management & Maturity · original instructional design · A3 landscape
POSTER 21
Section 9 · Quick Reference — Every Formula in One Place

The Formulas Wall

All the maths across the wall, grouped by family. Golden rules: in EVM, EV starts every formula — a variance subtracts (EV − x), an index divides (EV ÷ x), and positive / > 1 is favourable. Cost pairs use AC; schedule pairs use PV.

Earned Value — Variances & Indices

SV = EV − PV
+ ahead · − behind

CV = EV − AC
+ under · − over

SPI = EV ÷ PV
>1 ahead

CPI = EV ÷ AC
>1 under budget

CV% = CV ÷ EV

SV% = SV ÷ PV

Earned Value — Forecasting

EAC = BAC ÷ CPI
current trend (default)

EAC = AC + (BAC − EV)
variance was one-off

EAC = AC + (BAC−EV) ÷ (CPI×SPI)
cost & schedule

EAC = AC + bottom-up ETC
re-estimate

ETC = EAC − AC

VAC = BAC − EAC

TCPI = (BAC−EV) ÷ (BAC−AC)
to hit BAC

TCPI = (BAC−EV) ÷ (EAC−AC)
to hit EAC

Estimating

PERT (Eₑ) = (O + 4M + P) ÷ 6
beta / weighted

σ = (P − O) ÷ 6
std deviation

Variance = ((P − O) ÷ 6)²

Triangular = (O + M + P) ÷ 3

Ranges: ±1σ ≈ 68% · ±2σ ≈ 95% · ±3σ ≈ 99.7% of outcomes.

Schedule / Critical-Path Network

Total Float = LS − ES = LF − EF

Free Float = ESₙₑₓₜ − EF − 1

Forward: EF = ES + Dur − 1

Backward: LS = LF − Dur + 1

Critical path = longest path = zero total float. (Drop the −1 / +1 if you count from day 0.)

Communication & Risk

Channels = n(n − 1) ÷ 2

EMV = Σ (Probability × Impact)
− threat · + opportunity

Finance (decision)

  • NPV — higher is better; already discounted.
  • IRR — higher is better.
  • ROI = (gain − cost) ÷ cost; higher better.
  • Payback — shorter is better.
  • BCR = benefits ÷ costs; > 1 good.

Contract (bonus)

PTA = ((Ceiling − Target Price) ÷ buyer share) + Target Cost

Point of total assumption — above it, the seller bears all extra cost (incentive contracts).

Sign-Reading & Golden Rules

  • EV first in every EVM formula.
  • Variance = subtract; index = divide.
  • Positive variance & index > 1 = good.
  • Cost ↔ AC; Schedule ↔ PV.
  • EV = % complete × BAC.
  • ETC = EAC − AC; VAC = BAC − EAC.
  • TCPI > CPI ⇒ recovery is hard.
  • Float 0 ⇒ on the critical path.

Most-Tested

  • CPI / SPI interpretation & EAC = BAC/CPI.
  • PERT (O+4M+P)/6 and σ = (P−O)/6.
  • Channels n(n−1)/2.
  • Total float = LS − ES.
  • EMV for decision trees.
Daily Drill All 4 EAC formulas PERT + σ + variance Float = LS − ES Channels for n = 10 Compute an EMV
PMI Visual Wall · Poster 21 · The Formulas Wall · original instructional design · A3 landscape
POSTER 22
Section 10 · The Whole System on One Sheet

Master Revision Wall

Everything, distilled. The hierarchy, the one-line essence of each area, the master mnemonics, the high-value distinctions and an exam-day playbook — the complete 22-poster wall on a single page. Drill this daily; reach for the other posters when a line here needs unpacking.

The Hierarchy — Strategy to Value

Strategy▸ Portfolio
right work
▸ Program
right benefits
▸ Project
right delivery
▸ Output▸ Outcome▸ Benefit▸ Value

Money & direction flow down ▼; value & information flow up ▲. Risk spans every level; OPM wraps the whole thing; Business Analysis runs across it finding the right problem & proving value.

Each Area in One Line

  • 12 Principles: how to act when the playbook runs out.
  • 8 Domains: concurrent activity areas that replaced the knowledge areas.
  • Tailoring: fit the approach to context — appropriate rigour.
  • Models/Methods/Artifacts: think · do · show.
  • Business Analysis: right problem → right solution → real value.
  • Risk: max opportunity, min threat; managed at 3 levels.
  • EVM: one number for scope+schedule+cost; forecast the finish.
  • Program: related work → benefits that outlive the program.
  • Portfolio: the right work; balance the mix to strategy.
  • OPM: deliver strategy consistently (PPP + enablers); mature.

Master Mnemonics

  • 12 Principles: "Stewards Tend Stakeholders' Value · Systems Lead Tailored Quality · Complexity, Risk, Adaptability, Change."
  • 8 Domains: "Some Teams Develop Plans, Producing Deliverables Measured under Uncertainty."
  • BA domains (NSEATS): "Never Stop Eliciting And Tracing Solutions."
  • Risk: threats A-T-M-A-E · opps E-S-E-A-E · "rolls up, response rolls down."
  • EVM: EV opens every formula; minus = variance, divide = index; +/>1 good.
  • Program (SBSGL): "Some Big Ships Get Launched."
  • Portfolio (CESPBA): Categorise·Evaluate·Select·Prioritise·Balance·Authorise.
  • OPM: PPP + enablers; maturity = S-M-C-I.

High-Value Distinctions — Know These Cold

PairThe difference
Project / Program / Portfoliooutput · related→benefits · aligned→mix
Output / Outcome / Benefit / Valuething made · change · gain · worth
Risk vs Issuefuture & uncertain · now & certain
Threat vs Opportunitynegative risk · positive risk
Validation vs Verificationright thing · thing right
Contingency vs Mgmt reserveknown, PM · unknown, management
PairThe difference
Qualitative vs Quantitativesubjective P×I · numeric model
Appetite / Tolerance / Thresholdwilling · acceptable variation · trigger
Predictive vs Adaptivestable, plan-driven · uncertain, iterative
Leading vs Laggingpredicts · confirms
Accuracy vs Precisionclose to true · repeatable
Roadmap vs Schedulewhy-when · what-when

Exam-Day Playbook

  • Read the stem for MOST · BEST · FIRST · NEXT · EXCEPT · NOT.
  • Prefer proactive, value-driven, stakeholder-respecting answers.
  • Principles over rigid process; tailor to context.
  • Address the root cause; gather information before drastic action.
  • Consult the plan / follow the process before escalating.
  • Escalate only when beyond your authority.
  • Manage risk — don't ignore it or "always avoid".
  • EVM: apply the sign rules; EAC = BAC/CPI unless told otherwise.
  • Distrust absolutes ("always / never"); eliminate the clearly wrong first.
  • The PM is an ethical servant-leader: Responsibility, Respect, Fairness, Honesty.

Colour-Code Navigation

Navy — Master / Strategy (1, 22)
Blue — PMBOK 7 / Project (2–6)
Gold — BA & Value (4, 7–10)
Red — Risk (11–13)
Green — EVM & Formulas (14–15, 21)
Teal — Program (16–17)
Violet — Portfolio (18–19)
Slate — OPM (20)
Daily Revision Cadence Recite the hierarchy aloud One mnemonic per area 5 distinctions from memory 3 formulas + their signs One exam rule applied
PMI Visual Wall · Poster 22 · Master Revision Wall · original instructional design · A3 landscape · END OF WALL

Continue learning

PMI Visual Wall — Master Edition, Part 1Guide · Engineering MathematicsFlashcards & Self-QuizGuide · Engineering MathematicsNEXT LESSON →Divisibility, Ideals and Unique FactorizationGuide · Engineering MathematicsEuler's Phi Function and Fermat's Little TheoremGuide · Engineering Mathematics
KEVOS · Engineering, manufacturing and project improvement
ArticlesServicesCase studiesAboutContact
© 2026 KEVOS®