Work Performance Data

Unmodified observations, metrics, and figures gathered directly during project execution activities.

2 min read 3 sections Execution Phase Monitor & Control

§1 Overview

Work Performance Data captures the raw, unvarnished realities of the project as work is performed.

This data serves as a foundational input for the Monitor and Control Project Work process. It is vital to separate raw metrics (such as the actual dollars spent or the exact number of defects logged) from the analytical interpretation of those metrics. Variance calculations, forecasting (EAC, ETC, VAC), and broader trend analyses do not belong here—they are generated downstream as Work Performance Information (WPI).

Key distinction: This document captures what happened. It does not calculate why it happened or what it means for the final project outcome. Those interpretations occur later and are typically published in a Project Status Report.
Contents

§2 Blank Template Structure

The layout below illustrates the typical structure required to capture execution metrics logically. This framework groups related work, costs, and quality events to facilitate seamless downstream reporting.

Project Title [Insert Title]
Reporting Period [Date] to [Date]
Date Prepared [Date]

Schedule — Activity Status

ID Activity Planned Finish Actual Finish % Complete Notes
      
      
      

Cost — Actual Cost (AC)

Cost Item Planned (PV) Actual (AC) Variance
    
    
TOTAL to date   

Quality & Events

Quality metrics

Defect Counts

[Count] new this period. [Count] cumulative. [Count] resolved.

Observation log

Notable Events

Log any delays, sponsor requests, or safety/compliance events observed during the period.

Contents

§3 Worked Example: Company Website

This worked example demonstrates how raw data is collected for a real-world scenario (Mary's Consulting - New Company Website) during Week 19 of execution.

Project Title Mary's Consulting - New Company Website
Reporting Period Sep 7–13, 2026
Date Prepared Sep 14, 2026

Schedule — Activity Status

ID Activity Planned Finish Actual Finish % Complete Notes
A021 Set Up Dev/Staging/Prod Environments Aug 14 Aug 13 100% Complete (1 day early)
A022 Configure CMS Aug 25 Aug 26 100% Complete (1 day late)
A023 Build Component Library Sep 11 Sep 11 100% Complete (on time)
A024 Build Page Templates Oct 2 35% In progress; 4 of 12 templates complete
A025 Develop Backend APIs Sep 30 60% In progress; CRM endpoint blocked (see 1-006)
A011 Develop Visual / Brand Design Aug 4 Aug 5 100% Complete (1 day late)
A014 Write Marketing Page Copy Sep 18 75% In progress; on track
A015 Produce Case Studies Sep 25 55% In progress; 11 of 20 done
A016 Collect Consultant Bios Sep 30 40% Behind plan; bio response rate 38% (target 60%)

Cost — Actual Cost (AC) Through Sep 13

Cost Item Planned (PV) Actual (AC) Variance
Internal labour (PM, Dev, UX, Content) $66,200 $72,500 +$6,300
Frontend contractor (D-1 paid) $800 $800 $0
Cloud/hosting (env. setup) $800 $850 +$50
CMS license (annual) $3,000 $3,000 $0
Stock imagery (partial) $1,200 $1,150 -$50
TOTAL Actual Cost (AC) to date $72,000 $78,300 +$6,300
Quality data

Defect Status

  • Logged this period: 14 (8 from component testing, 6 from design review)
  • Cumulative logged: 23
  • Resolved this period: 9
  • Open at end of period: 14

Severity Breakdown: Sev 1: 0, Sev 2: 3, Sev 3: 9, Sev 4: 2.

Observation log

Notable Events This Period

  • Sep 8: CRM API discovery revealed a missing "industry vertical" field. Logged as 1-006; mitigation in progress.
  • Sep 10: Sponsor signed design review early (3 days ahead of plan).
  • Sep 11: Component library completed on schedule.
  • Sep 12: Bio response rate below target. Triggered Risk R-05 mitigation actions. Change request CR-007 drafted.
  • Sep 13: Sponsor requested new Press / Media section.