← LibrarySchedule Baseline Template & ExampleTemplates & Examples · Project TemplatesLesson 21/23← PrevNext →
TemplatePublished 10 Jul 2026Updated 14 Jul 20264 min readBy Kevin Joginschedulebaselineproject planningproject control
KEVOS®
Templates & Examples · Project Templates
Templates & Examples / Project Templates

Schedule Baseline

Formalise the approved schedule model, lock target dates, and establish the metric against which all project performance will be measured.

4 min read 3 sections Document Template Worked Example
Approved Baseline
Doc № KEV-TPL-104 Sec 4 Sheet 1/1 Drawn KEVOS® 10 Jul 2026

§1 Purpose of the Schedule Baseline

The Schedule Baseline is the approved version of the schedule model. Once signed, it can be changed only through formal change-control procedures.

A schedule is highly fluid during the planning phase. Activities are added, durations are debated, and logic is rearranged. However, before execution begins, the Project Manager must draw a line in the sand. The Schedule Baseline formalises the agreement between the project team and the sponsor regarding when work will be completed.

It acts as the yardstick for performance measurement. If a milestone is missed, the delay is calculated as a variance directly against the dates established in this baseline document.

What makes up the Baseline? The baseline is not just a Gantt chart. It is an aggregated package comprising the Activity List, Activity Attributes, Duration Estimates, Milestone List, and Network Diagram. If any of these underlying components change, the baseline itself is affected.
Contents

§2 Blank Template

A standardized sign-off framework consolidating the planning outputs into a single approved agreement.

SCHEDULE BASELINE

Project Title [Insert Project Name]
Date Prepared [YYYY-MM-DD]

Purpose

This document constitutes the approved Schedule Baseline for the [Project Name]. Per PMBOK standards, the schedule baseline is the approved version of the schedule model that can be changed only through formal change-control procedures. It is used as a basis for measuring schedule performance throughout the project.

Schedule Baseline Components

The Schedule Baseline encompasses the following approved artifacts:

  1. Activity List - defined activities derived from the WBS work packages.
  2. Activity Attributes - detailed attributes and dependencies for each activity.
  3. Duration Estimates - approved duration calculations for each activity.
  4. Milestone List - key project milestones with target dates.
  5. Project Schedule Network Diagram - sequenced activities with logical dependencies.
  6. Project Schedule - calendar-based schedule (Gantt) with start and finish dates.
  7. Project Calendar - working and non-working days governing the schedule calculation.

Baseline Key Dates

Milestone Approved Target Date
[Milestone 1 Name] [YYYY-MM-DD]
[Milestone 2 Name] [YYYY-MM-DD]
[Final Delivery Milestone] [YYYY-MM-DD]

Baseline Approval

[Project Manager Name]
Project Manager
Date: _______________
[Sponsor Name]
Project Sponsor
Date: _______________
Contents

§3 Worked Example: Mary's Consulting

A completed example demonstrating the formal lock-in of an 8-month digital implementation project timeline.

Notice that the baseline summarizes the key dates, but explicitly references the underlying documentation (like the Activity Attributes) as part of the total locked package. Approval by the Sponsor transitions the schedule from a planning draft to an executable baseline.

SCHEDULE BASELINE

Project Title Mary's Consulting - New Company Website
Date Prepared May 12, 2026

Purpose

This document constitutes the approved Schedule Baseline for the Mary's Consulting Website project. Per PMBOK 8th edition, the schedule baseline is the approved version of the schedule model that can be changed only through formal change-control procedures. It is used as a basis for measuring schedule performance throughout the project.

Schedule Baseline Components

The Schedule Baseline consists of:

  1. Activity List - defined activities derived from the WBS work packages.
  2. Activity Attributes - detailed attributes for each activity.
  3. Duration Estimates - approved duration for each activity.
  4. Milestone List - key project milestones with target dates.
  5. Project Schedule Network Diagram - sequenced activities with dependencies.
  6. Project Schedule - calendar-based schedule with start and finish dates.
  7. Project Calendar - working/non-working days governing the schedule.

Baseline Key Dates

Milestone Date
Project Start (Charter approved) May 08, 2026
Planning Complete; Baselines Locked Jun 08, 2026
Requirements Approved Jul 02, 2026
Design Approved Aug 07, 2026
Build Complete Oct 09, 2026
UAT Sign-off Nov 19, 2026
Production Go-Live Nov 24, 2026
Hypercare Complete Dec 10, 2026
Operations Handoff Dec 15, 2026
Project Closeout Dec 29, 2026

Baseline Approval

Andrew
Andrew
Project Manager
Date: Jun 08, 2026
Mary
Mary (CEO)
Sponsor
Date: Jun 08, 2026

Formal Change Control

Once both parties sign this document (on Jun 08), the dates cannot be changed simply by updating a Gantt chart. Any future shift to these dates requires an approved Change Request.

Variance Tracking

This document is the "control" state. If the actual UAT Sign-off occurs on Nov 21, the project manager will report a 2-day negative schedule variance against this baseline.

The Package Deal

The sponsor isn't just approving a list of dates. By signing the baseline, they are implicitly approving the logical dependencies (Network Diagram) and effort calculations (Estimates) that generated those dates.

Contents

Continue learning

Lessons Learned RegisterTemplate · Project TemplatesFinal Report Template & ExampleTemplate · Project TemplatesNEXT LESSON →Project Schedule Network Diagram Template & ExampleTemplate · Project TemplatesProduct Transition TemplateTemplate · Project Templates